Defendant, Terry MacHaffie, appeals from a judgment in favor of plaintiff, Hart and Son Hauling, Inc., d/b/a G.J.H. Contracting Company, in a court-tried action for breach of a construction contract for the remodeling of defendant’s residence and from a judgment in favor of plaintiff оn defendant’s counterclaim. We affirm.
Our standard of review in a court-tried case is guided by the oft-cited
Murphy v. Carron,
The evidence at trial established that defendant had received a Housing and Urban Development (HUD) Chapter 312 loan for the renovation of her residence. The loan was to be administered by the City of St. Louis through its Community Development Agency (CDA). On April 6, 1981, defendant and plaintiff, the general contractor, entered into a contract to complete the *588 project for the sum of $51,708. Plaintiff commenced work that same month.
In June, plaintiff filed a request for payment. On June 24, the architect overseeing the project certified that 47 percent of the work had been completed and executed authorization for the first progress payment. Defendant refused to sign the certificate for payment unless plaintiff agreed to substantially complete all work by August 27, 1981. Plaintiff agreed to that condition. When plaintiff’s president went to pick up the check from defendant, howevеr, defendant had a second pre-condition for payment. She required him to sign an agreement which said: (1) that defendant had not contributed to any delay in construction; and (2) that plaintiff would pay $10, as liquidated damages, for everyday after August 27, 1981, for which construction was not completed. Plaintiffs president signed the agreement and received the check for $24,184.
On July 29, 1981, plaintiff stopped work on the project and requested a second progress payment. On August 5, the architect certified that 65 percent of the work had been completed and exeсuted a second authorization of payment in the amount of $9,202. Defendant refused to sign this certificate for payment. On August 13, 1981, after its workers had attempted to return to the job but were unable to gain entry into the house, plaintiff wrote a letter to defendant. Defendant did not respond. Plaintiff then terminated work at defendant’s residence.
After a final evaluation on April 1, 1982, the architect authorized a payment of $10,-456 for the work plaintiff had performed from the time of the first progress payment until construction was halted. Defendant again refused to sign the certificate for payment. After trial, the court awarded plaintiff that final progress payment and loss of profits of $10,040.68, plus prejudgment interest thereоn, for a total of $26,041.03 in damages.
Defendant raises two points on appeal. She alleges trial court error in the denial of her cоunterclaim for damages and in the award of damages to plaintiff. The threshold issue is whether defendant breached the contract by prеventing its completion. If she did, she would not be entitled to recover damages.
Defendant asserts that plaintiff repudiated the contraсt when its workers left the job on July 29. Anticipatory breach by repudiation occurs when a party to a contract manifests a “positive intеntion not to perform” either by expressed statements or by conduct.
Carmel v. Dieckmann,
Additionally, when the owner prevents a contractor from completing performance, the contractor’s failure to complete his work is excused and he is not regarded аs having breached the contract.
Curators of the University of Missouri v.
*589
Nebraska Prestressed Concrete Co.,
We turn now to defendant’s specific points on appeal. In her first point, defendant asserts that she was entitled to damages for plaintiff’s failure to completе, particularly in light of the liquidated damage provision which plaintiff signed. The owner’s prevention or hindrance of the contractor’s performance of a building contract within a specified time, however, excuses any delays on the part of the contractor and thе contractor cannot be held liable for liquidated damages.
Ark Constr. Co. v. City of Florissant,
In her second point, defendant contends that the amount of damages awarded to plaintiff was incorrect. The trial court awarded plaintiff the final progress payment as well as its loss of profit.
At the final accounting the architect authorized а payment for the work which had been completed but for which plaintiff had not yet been paid. At that point, plaintiff had a right to the payment. Additionally, a party injured by the breach of a contract may recover “whatever net gain he would have made under the contraсt.”
Artcraft Cabinet, Inc. v. Watajo, Inc.,
The judgment of the trial court is affirmed.