247 F. 569 | S.D. Fla. | 1918
The plaintiff in his declaration sues for damages caused by an alleged breach of contract on the part of the defendant. The case made by the declaration may be succinctly stated as follows:
The defendant, after due advertisement, let a contract for sewer construction in three sections, as theretofore planned, to a firm, who subsequently with the .consent of the defendant assigned the contract for sewer construction in two of these sections to the plaintiff, and thereupon the plaintiff and the defendant entered into a contract for such construction, containing the same terms as the contract with the original contractor would have, had it been entered into with them. This contract provided for progress payments on certificates of the engineer of the amount of work done of 80 per cent. After commencing work upon the construction, under a provision of the contract, these progress payments were by written agreement increased from 80 per cent, to 90 per cent., and it was further agreed that 90 per cent, of the value of all iron pipe delivered, whether laid or not, should be paid. Defendant breached this contract as modified, first by the arbitrary refusal of the engineer to certify the full amount of the work performed and iron pipe delivered, and the arbitrary refusal of defendant’s board of commissioners to pay for same. Other breaches set up are that defendant on certain days refused to make progress payments in cash, but insisted upon the plaintiff accepting written promises to pay; that defendant modified its written contract with the original contractors, thereby changing the progress payments from
To the first, second, and fifth counts the defendant interposed eight pleas. A motion is made by the plaintiff to strike the fourth of these pleas, which'motion will be granted.
If this modification of the original contract is void under the circumstances stated in the pleas, the pleas are not susceptible to the motion to strike or the demurrer. There is no contention that the original contract was not duly advertised. This original contract provided that the same might be modified as the work progressed. The declaration alleges this modification was made pursuant to this clause, and the plea does not negative this allegation, nor does it state facts showing fraud in the original advertisement, nor in the contract modified. I am of opinion that the failure to advertise the modification is not a violation of the charter provisions and does not avoid the modification. The suit is upon the contract as modified, and therefore the first plea is amenable to the demurrer.
A demurrer was interposed to this plea on the ground that all the breaches are not negatived, and the facts set up do not show a waiver of the breaches. A motion is also made to strike out certain portions-of this plea. If this motion to strike out the portions of the plea attacked by the motion should be granted, the plea would be demurrable. I therefore take up that motion first.
After carefully considering those portions of the plea attacked by the motion, I am of opinion that they are material to the proper decisión of the issues between the parties. The plaintiff in this case elected to abrogate the contract on August 18th, and bring his suit for work done, materials furnished, and damages resulting to him. I recognize that upon the breach of a contract by one party the other may continue the work, and is not precluded from claiming any damages such breach may have occasioned him. But that is riot this case. I do not recognize any principle by which one party to a contract, after a breach by the other party, may continue acting under such contract to some future time, and then abrogate the contract by reason of such former breach; and that is the case made if the allegations of the plea are true. As I understand the law, one party to a contract may abrogate it upon a breach of said contract by the other, or he may waive such breach and proceed with the execution of the contract. He must do one or the other. He cannot waive the breach and afterwards declare an abrogation upon such waived breach. The motion for compulsory amendment will be denied. The demurrer will also be overruled.
The defendant, in addition to the pleas above noticed, filed three additional pleas to the first and second counts to which those were pleaded,, and one additional to the fifth count. Motions to strike, for compulsory amendment, and demurrers were filed to all these pleas.
To the fifth count the defendant pleaded one additional plea, which is in effect the plea of nil debet, which is forbidden by the rules of court. Rule 68, Supreme Court Rules in Common-Law Actions. However, no motion is made to strike said plea, but a motion for compulsory amendment, by striking therefrom certain words incorporated by reference to other pleas. This motion will be granted.
The demurrers to the first and second pleas to the third count and the first and second pleas to the fourth count will be sustained. The incorporation of the allegations of the first and second additional pleas add no strength, but incorporate the weakness of said additional pleas and make them demurrable.
The demurrers to the third plea to the third and fourth counts will be overruled, and the motions denied.
I have considered the pleadings and files as of the time of filing the same. The granting of the defendant’s motion to strike certain portions' of the declaration will necessitate a reformation of the pleas now standing in that regard.