HARRISON COUNTY UTILITY AUTHORITY v. CRAWFORD DIRECTIONAL DRILLING, LLC; SOUTHERN LIGHT, LLC; J. CRUZ UTILITY CONTRACTORS; JORGE CRUZ; and JERONIMO CRUZ
CAUSE NO. 1:15CV264-LG-RHW
IN THE UNITED STATES DISTRICT COURT FOR THE SOUTHERN DISTRICT OF MISSISSIPPI SOUTHERN DIVISION
April 19, 2017
LOUIS GUIROLA, JR., CHIEF U.S. DISTRICT JUDGE
MEMORANDUM OPINION AND ORDER DENYING THE MOTION FOR SUMMARY JUDGMENT FILED BY J. CRUZ UTILITY CONTRACTORS AND JERONIMO CRUZ
BEFORE THE COURT is the Motion for Summary Judgment [92] filed by Defendants Jeronimo Cruz and J. Cruz Utility Contractors. The Motion has been fully briefed by the parties. After reviewing the submissions of the parties, the record in this matter, and the applicable law, the Court finds that the Motion for Summary Judgment should be denied.
FACTS
Defendant Southern Light hired defendant Crawford Directional Drilling to install fiber optic lines in Gulfport and Biloxi, Mississippi. Crawford subcontracted the work out to Defendant Jeronimo Cruz and his company J. Cruz Utility Contractors (hereafter collectively referred to as “Cruz“). The project plans called for Cruz to install the lines via directional boring on the eastern side of Debuys Road from just north of Pass Road in Biloxi to approximately thirty-five feet north
In preparation for the project, Cruz submitted a locate request to Mississippi 811, so that the locations of underground utilities could be marked. The locate request stated, “BEGIN LOC AT INT OF DEBUYS RD & SWITZER RD, LOC ENTIRE INT & CONT SOUTH ON EAST SIDE OF DEBUYS RD APPX 3000 FT CROSSING PASS RD.” The parties agree that the request stated, in plain language: “Begin locate at intersection of Debuys Road and Switzer Road approximately 3000 feet, crossing Pass Road.” Switzer Road becomes Eula Street just after its intersection with Debuys Road. Therefore, Switzer Road and Debuys Road meet just south and east of the directional boring that Cruz performed for the project. Upon receipt of this request, HCUA responded, “clear, no conflict,” which generally means that the utility does not expect excavation to interfere with underground utility lines, based on the description of the site given by the excavator. (See Def.‘s Mot., Ex. E at 32, ECF No. 92-5).
When Cruz was boring underneath Debuys Road, he struck one of HCUA‘s sewer lines. HCUA filed this lawsuit against Cruz and others2 seeking reimbursement of the damages caused by the breach of the sewer line. Cruz argues that he is entitled to summary judgment, because HCUA failed to properly mark the sewer line in compliance with his Mississippi 811 locate request. HCUA
DISCUSSION
A motion for summary judgment may be filed by any party asserting that there is no genuine issue of material fact and that the movant is entitled to prevail as a matter of law on any claim.
The act of giving notice in accordance with
Section 77-13-5 shall relieve the notifying party of all liability to a utility should such notice be ignored or the information provided by the utility subsequent to said notice be materially inaccurate; provided, however, the act of giving advance notice and/or obtaining information as required by this chapter shall not relieve any person making excavations from doing so in a careful and prudent manner, nor shall it relieve such person from liability for any injury or damage proximately resulting from his/her negligence.
Cruz argues that the area where he struck the sewer line was included in his locate request, while HCUA argues that the area was outside the request. Thus, the parties disagree over what should be considered an “entire intersection” for
HCUA was required to locate and provide notice of any underground utility lines “in or near the area of the excavation, so as to enable the person engaged in excavation work to locate the lines and facilities in advance of and during the excavation work.” See
CONCLUSION
The record in this matter raises numerous questions of material fact that cannot be adjudicated as a matter of law by this Court. Furthermore, this may be a case where a jury could reasonably assign a percentage of fault to both parties. Therefore, Cruz has not demonstrated that he is entitled to summary judgment.
IT IS, THEREFORE, ORDERED AND ADJUDGED that the Motion for Summary Judgment [92] filed by Defendants Jeronimo Cruz and J. Cruz Utility Contractors is DENIED.
SO ORDERED AND ADJUDGED this the 19th day of April, 2017.
s/ Louis Guirola, Jr.
LOUIS GUIROLA, JR.
CHIEF U.S. DISTRICT JUDGE
