HARRIS, dba Bob Harris Construction, Petitioner on Review, υ. DYER, Respondent on Review.
No. 78-1378-E-3, CA 17650, SC 27670
In the Supreme Court of the State of Oregon
December 22, 1981
petition for rehearing denied January 26, 1982
292 Or 223 | 637 P2d 918
Argued and submitted June 30, affirmed as modified December 22, 1981
Susan P. Graber and Richard E. Alexander, Portland, argued the cause and filed a brief for respondent on review. With them on the briefs were Stoel, Rives, Boley, Fraser and Wyse.
LINDE, J.
Peterson, J., filed a dissenting opinion.
A dispute between the parties to a construction contract led the owner to terminate the contract. The construction contractor demanded the amount he claimed to be owing under the contract, and upon the owner‘s refusal to pay, the contractor filed a claim of lien, followed by a suit to foreclose the lien. As the contract provided for arbitration, the circuit court abated the proceeding pending arbitration.1 The arbitrators awarded the contractor $64,089.71 plus interest. The contractor then moved for a decree foreclosing the lien in a total amount comprising the arbitrators’ award, interest, lien preparation and recording fees, court costs, and reasonable attorney fees incurred in the arbitration as well as in the judicial proceeding. Defendant, the owner, tendered the amount of the award, with interest, and when plaintiff rejected this tender as insufficient, the circuit court dismissed the foreclosure suit on defendant‘s motion.
The Court of Appeals reversed the dismissal, holding that an arbitration provision alone does not waive the contractor‘s right to file a construction lien to secure eventual payment of his claim, and that plaintiff was entitled to have judgment in the foreclosure suit for all items included in the arbitration award that were properly covered by the lien. The court also held that plaintiff was entitled to costs and attorney fees related to the filing of the lien and the foreclosure proceeding, but excluding attorney fees incurred in the arbitration, and it remanded the case to the circuit court for determination of the proper amount of the judgment. 50 Or App 223, 623 P2d 662 (1981). The only issue before us on review is whether plaintiff is entitled to reasonable attorney fees incurred in arbitrating the amount of his claim.
Plaintiff‘s second argument, however, is that this contract did preserve for the parties such rights to attorney fees as the parties would have had in the absence of the arbitration clause. The contract was a standard form construction contract published by the American Institute of Architects. Two provisions are relevant to the present issue.
The arbitration article begins:
“7.9.1. All claims, disputes and other matters in question between the Contractor and the Owner arising out of, or relating to, the Contract Documents or the breach thereof * * * shall be decided by arbitration in accordance with the Construction Industry Arbitration Rules of the American Arbitration Association then obtaining unless the parties mutually agree otherwise. * * * The foregoing agreement to arbitrate shall be specifically enforceable under the prevailing arbitration law. The award rendered by the arbitrators shall be final, and judgment may be entered upon it in accordance with applicable law in any court having jurisdiction thereof.”
Nothing in the record elucidates the reference to the “Construction Industry Arbitration Rules of the American Arbitration Association,” and there is no evidence that either contracting party knew what they were. The arbitrators’ award ordered that the association‘s fees and expenses and those of the arbitrators be borne equally by the parties, but there is no suggestion that either the arbitration rules or the award covered attorney fees.
Plaintiff contends that when the last sentence of art. 7.9.1., supra, refers to entry of judgment on the award “in accordance with applicable law,” the “applicable law” includes the attorney fee provision of the lien law and thereby also includes attorney fees for the arbitration. Assuming plaintiff‘s premise that “applicable law” in art. 7.9.1 includes more than the “prevailing arbitration law” mentioned in the preceding sentence, nevertheless this clause only provides for the entry of judgment upon the award itself. It says nothing about attorney fees which the “applicable law” allows for the enforcement of a lien.
“The duties and obligations imposed by the Contract Documents and the rights and remedies available thereunder shall be in addition to and not a limitation of any duties, obligations, rights and remedies otherwise imposed or available by law.”
The question is what “duties, obligations, rights and remedies” are reserved by this clause.
The record does not offer any explanatory material bearing on the intended meaning and scope of art. 7.6.1. of the standard form contract. We disregard “duties and obligations” as referring most likely to the substantive performance required of the respective parties. Their “rights and remedies” clearly extend to the contingency of nonperformance. One of the standard remedies that must have been contemplated in this provision is the security of a construction lien and its eventual foreclosure, a procedure which in Oregon gives the prevailing party a right to attorney fees. The lower courts held that, despite art. 7.6.1., lien foreclosure had to await the result of arbitration under the contract. Had the dispute ended with the award, or with its enforcement under the arbitration statute, there would be no right to attorney fees for art. 7.6.1. to reserve. Cf. Oakdale Park Ltd. v. Byrd, supra. But the Court of Appeals held that after the award foreclosure was proper, and that holding is not challenged here. Article 7.6.1. provides that the rights and remedies under the contract (which includes the remedy of arbitration) shall not be a limitation of rights and remedies otherwise available by law. It does not seem the most likely reading of this reservation of rights that it meant to sacrifice attorney fees which the law allows when all phases of the foreclosure remedy are litigated in court. Rather, it seems more consonant with the apparent objective of including a reservation of rights to read art. 7.6.1. as disavowing such a limitation on the otherwise available right to attorney fees.
Accordingly, we conclude that the contract between the parties reserves to the prevailing party in a lien foreclosure suit the full “reasonable” attorney fees available in such a suit under
Affirmed as modified.
PETERSON, J., dissenting.
I understand the majority opinion to hold, consistent with our precedent in Jackson v. Penny Duquette Knits, 276 Or 465, 555 P2d 201 (1976), consistent with the opinion of the Court of Appeals opinion below, and consistent with the holdings of most other courts considering the issue,1 that although an agreement to arbitrate bars judicial determination of arbitrable issues, the arbitration agreement does not bar the invocation of lien procedural remedies to collect the award of the arbitrators. I further read the majority opinion to hold, consistent with the Court of Appeals and other jurisdictions considering the issue,2 that even though attorney fees are recoverable incident to the foreclosure, absent a “rights and remedies” clause, one who prevails in the arbitration proceeding who seeks judicial assistance in collecting the award via lien foreclosure is not entitled to recover attorney fees incurred in the arbitration proceedings.
If the foregoing analysis of the majority opinion is correct, I concur with the majority to that point. I disagree, however, with the holding that because of the existence of the “rights and remedies” clause set forth on pages 237 and 238 of the majority opinion, the parties meant to retain the right to recover arbitration attorney fees in the lien foreclosure suit.
Written arbitration agreements are enforceable,
The majority believe that the right to recover attorney fees incurred in the arbitration proceedings still is available to the plaintiff because of the contractual provision that “* * * the rights and remedies available thereunder shall be in addition to and not a limitation of any duties, obligations, rights and remedies otherwise imposed or available by law.” The majority construes this contractual provision in three sentences, saying:
“* * * Article 7.6.1. provides that the rights and remedies under the contract (which includes the remedy of arbitration) shall not be a limitation of rights and remedies otherwise available by law. It does not seem the most likely reading of this reservation of rights that it meant to sacrifice attorney fees which the law allows when all phases of the foreclosure remedy are litigated in court. Rather, it seems more consonant with the apparent objective of including a reservation of rights to read art. 7.6.1 as disavowing such a limitation on the otherwise available right to attorney fees.”
That analysis is contrary to the purpose of our arbitration statutes and misconstrues the contractual language. In Harrell v. Dove Mfg. Co., 234 Or 321, 326, 381 P2d 710 (1963), we stated:
“* * * One of the primary purposes for which parties agree to arbitrate their disputes is to avoid what they fear may be costly and time-consuming litigation. See generally, Note, 63 Harv L Rev 681 (1950). It would be patently unfair to allow a party to an arbitration proceeding for which both parties have voluntarily contracted to turn the proceedings into a lawsuit in the event the arbitrator‘s decision is unfavorable to him. * * *”
Second, the analysis of the majority, carried to its logical conclusion, guts virtually all arbitration agreements which contain “rights and remedies” language similar to that at bar. All of these rights listed above—the right to a jury trial, the right to a written record, etc.,—are “rights and remedies otherwise imposed or available by law.” Under the majority opinion, even though the parties had agreed to a submission to a decision by arbitration, these rights and remedies would still be available to them. I find it difficult to follow the analysis that notwithstanding the waiver of such rights, such rights are nonetheless reserved to the parties.
The clear purpose of the arbitration agreement is to obtain ready relief as a shortcut to the judicial procedures otherwise available to the parties. The parties have agreed that any determination as to the amount due is to be determined by arbitration. That includes, in my opinion, the waiver of all judicial procedures and rights assertable therein, which would normally be available to them incident to the determination of the amounts due. Forgetting the lien for the moment, if a statute provided for attorney fees to the prevailing party, and if the parties had agreed to a submission of that dispute to arbitration, that would amount to a waiver of the right to attorney fees under the
I believe that the arbitration statutes aim to provide a procedure outside of court procedures for the determination of personal liability, if any, but to make court procedures available for the collection of the amount determined to be due.
Tongue, J., joins in this dissent.
Notes
“If any action, suit or proceeding is brought upon any issue arising out of an agreement which contains a provision for arbitration of the matter in controversy in such action, suit or proceeding, then, upon application, any judge of a circuit court, upon being satisfied that the issue is referable to arbitration, shall abate the action, suit or proceeding so that arbitration may be had in accordance with the terms of the agreement. The application shall be heard similarly to hearings on motions.”
See Floors, Inc. v. B. G. Danis of New England, 80 Mass Adv Sh 647, 401 NE2d 839 (1980), affirming the Massachusetts Appeals Court, Suffolk, 7 Mass App 356, 387 NE2d 1166 (1979); Beach Resorts Intern. v. Clarmac Marine Const., 339 So 2d 689 (Fla App 1976); Oakdale Park Ltd. v. Byrd, 346 So 2d 648 (Fla App 1977).“When notice of intention to commence suit to foreclose the lien has been given, pleaded and proven as provided for in
