KENDALL HARRIS, Appellant, v CITY OF NEW YORK, Respondent.
Supreme Court, Appellate Division, First Department, New York
April 5, 2011
923 NYS2d 2
APPEARANCES OF COUNSEL
Wade Clark Mulcahy, New York City (Nicole Y. Brown and John Mulcahy of counsel), for respondent.
OPINION OF THE COURT
CATTERSON, J.
In this personal injury action, the plaintiff‘s
The project on which the plaintiff was employed entailed the removal of the bridge‘s deck, a steel grid filled with concrete. The deck was first divided into sections by workers using saws. Then the sections were removed by attaching each segment to cables and chokers which in turn were attached to the hook of a crane that hoisted each section vertically, and then away from the bridge.
The facts relating to the plaintiff‘s accident are undisputed. By affidavit, the plaintiff‘s foreman stated that, on the day of the accident workers were attempting to lift from the bridge road deck a 10-foot-by-20-foot slab which weighed approximately one ton. As the crane raised the slab from the surface, the foreman saw that one corner of the slab lifted three or four feet in the air while the opposite corner remained attached to the roadbed. In order to separate the slab entirely from the surface, the foreman directed that the slab be lifted until the cables were taut, then told the plaintiff to wedge a piece of four-by-four lumber into the spot where the slab remained attached to the roadbed. Then, the crane was to slowly lower the slab to place pressure on the four-by-four wedge in order to pry loose the attached portion of the slab. After several unsuccessful attempts, the plaintiff took a piece of four-by-four lumber that was approximately six-to-eight-feet long and wedged one end of it into the place where the slab remained attached. He then stood on the other end to keep it in place. The four-by-four was at an angle, with the low end wedged between the slab and the roadbed, and the high end (upon which the plaintiff stood) three to four feet off the ground. The plaintiff then motioned to the signalman asking him to direct the crane operator to slowly lower the slab. Instead, the slab descended quickly, causing the
By summons and complaint dated September 22, 2003, the plaintiff sought damages for, inter alia, the defendant‘s violation of
By notice of motion dated December 19, 2008, the defendant sought summary judgment dismissing the complaint in its entirety. The defendant argued that the plaintiff‘s
By order dated June 26, 2009, the motion court granted the defendant‘s request for summary judgment dismissing the complaint on the grounds that “the alleged injury was not a result from a difference in the elevation level of the required work and that this was an ordinary peril of a crane lifting operation which does not implicate
On appeal, the plaintiff asserts that
“[a]ll contractors and owners and their agents . . . in the erection, demolition, repairing, altering . . .
of a building or structure shall furnish or erect, or cause to be furnished or erected for the performance of such labor, scaffolding, hoists, stays, ladders, slings, hangers, blocks, pulleys, braces, irons, ropes, and other devices which shall be so constructed, placed and operated as to give proper protection to a person so employed.”
To establish liability under
Once again, we are called upon to reiterate that
”
Labor Law § 240 (1) . . . evinces a clear legislative intent to provide ‘exceptional protection’ for workers against the ‘special hazards’ that arise when the work site either is itself elevated or is positioned below the level where ‘materials or load [are] hoisted or secured.‘” (Ross, 81 NY2d at 500-501, quoting Rocovich v Consolidated Edison Co., 78 NY2d 509, 514 [1991]; see also Narducci v Manhasset Bay Assoc., 96 NY2d 259 [2001].)
More recently the Court held that courts have historically read
Runner involved circumstances that are markedly similar to those of the instant case. In that case, the plaintiff and two coworkers attempted to move an 800-pound reel of wire down a
The Court concluded that the specific task being performed at the time of the plaintiff‘s injury was moving a heavy reel from a higher to a lower elevation, that the danger to be guarded against arose from the reel‘s insufficiently checked descent, and that the plaintiff‘s injury flowed directly from the effect of gravity on the reel as it descended. (Runner, 13 NY3d at 603-604.) The Court found
Although Runner was decided after the motion court‘s ruling in the instant case, the Court made it clear that it was not establishing any new principles, merely expounding on the governing principle enunciated almost 20 years previously. (Runner, 13 NY3d at 604, citing Ross, 81 NY2d at 501.) In Ross, the Court held unequivocally that ”
In the instant case, the task being performed involved removing a one-ton slab of concrete and steel which was partially attached to a roadbed surface, using a piece of wood as a wedge to extricate the slab from the road deck. The portion of slab attached to the crane by steel cables and chokers was lowered from a higher to a lower elevation in order to exert pressure on the wedge and dislodge the attached portion. The uncontroverted evidence shows that the slab descended too quickly, causing the wedge upon which plaintiff stood to shatter, and in turn causing plaintiff to fall and sustain injury.
As in Runner, “the danger to be guarded against plainly arose from the force of the very heavy [slab‘s] unchecked, or
Although there is precedent indicating that
The defendant‘s argument attempting to circumvent the plain meaning of, and the strict liability imposed by, the statute is without merit. Acknowledging that the only acceptable defense to a
This is not a situation where a plaintiff, on his own initiative, took a foolhardy risk which resulted in injury. (See e.g. Montgomery v Federal Express Corp., 4 NY3d 805 [2005].) To the contrary, the uncontroverted evidence shows that the plaintiff‘s foreman directed him to stand on top of the piece of wood in order to keep it in place. Hence, as a matter of fact and law the plaintiff cannot be the sole proximate cause of his injuries. (See Pichardo v Aurora Contrs., Inc., 29 AD3d 879 [2d Dept 2006] [plaintiff was not sole proximate cause of his injury
More significantly, a
Although the defendant argues that it exercised no control over its contractor‘s work on the Macombs Dam Bridge project, it is well established that the duties imposed by
Finally, the evidence demonstrated violations of the additional Industrial Code sections alleged in the plaintiff‘s proposed amended bill of particulars, namely,
Accordingly, the order of the Supreme Court, Bronx County (Mary Ann Brigantti-Hughes, J.), entered June 26, 2009, which, to the extent appealed from as limited by the briefs, granted defendant‘s motion for summary judgment dismissal of the complaint insofar as it alleged violations of
TOM, J.P., FRIEDMAN, RENWICK and MANZANET-DANIELS, JJ., concur.
Order, Supreme Court, Bronx County, entered June 26, 2009, reversed, on the law, without costs, defendant‘s motion denied, plaintiff‘s
