151 Ky. 71 | Ky. Ct. App. | 1912
Opinion of the Court by
Affirming.
On May 19, 1910, plaintiff, for the consideration of $400 cask, sold to defendants, Z. Harrell & Company all tke timber on tke soutk side of tke public road where be then lived, with tke exception of tke sassafras and mulberry, wkick were reserved. Tke contract was in writing and contained tke following provision:
“Z. Harrell & Co. to kave twelve months to work tke timber off tke land.”
On motion of defendants, the case was transferred to equity. On final hearing, the chancellor rendered judgment in favor of plaintiff for $200. Defendants appeal.
The evidence shows that the defendants never began to cut the timber until the month of August, 1910, and that they did not begin to haul the timber from the land until the middle or latter part of November, 1910. They then hauled until about the first of January. After that they did no hauling until after May 19, when the time for removing the timber expired. The timber for which a recovery is sought was removed during the months of June and July. The defendants showed by several witnesses that there was a freeze in December, followed by a thaw a few days later, which caused the'roads to become very muddy. In addition to this, there was an unusual rainfall during the winter months, and the early spring, and during all this time it was practically impossible to do any hauling.' On the other hand, there was testimony to the effect that the weather during the fall of 1910 was fine for hauling, and that with one team and one crew of hands the timber could have been removed from the land in 100 days, and with more teams it could have been removed in a shorter time. It was also shown that while the roads were muddy during the winter months, the conditions were not much worse than usually prevailed at that time of the year.
Defendants insist that as the trees in question were severed within the time fixed by the contract of sale,,
In an extended note to McRae v. Stillwell, 55 L. R. A., 513, the authorities on the question are collated, and the rule to be deduced therefrom is thus stated by. the editor:
“Where the conveyance specifies a particular time for the removal of the timber, the purchaser has generally been held to have forfeited all rights in the timber not removed within,the time specified, although a few cases hold that he still retains the title to the timber but cannot remove the same, as his right of entry is gone. It would seem that the mere cutting of the trees within the time specified, without their removal from the land, is insufficient to preserve the purchaser’s rights in the timber; but the manufacture of them into timber has been held a sufficient removal of them, although such timber still remains on the land.”
The question is: Are the facts of this case sufficient to bring it within the exception to the rule that the timber must be removed within the time specified in the contract? In other words, were defendants prevented from removing the timber by extraordinary rainfalls, or by the act of the seller? There is evidence to the effect that there were unusual rains during the winter and early spring of 1911; that during this period the roads were very muddy, and the timber could have been removed only with great difficulty and expense, if, in
The only other circumstance relied upon to bring the case within the exception to the rule is the testimony of one of defendants’ drivers to the effect that plaintiff stated that he, plaintiff, “would not haul through the mud.” Plaintiff denies making the statement, but whether he made it or not, we are not inclined to hold that the remark'was a sufficient interference on the part of plaintiff to excuse the defendants from the necessity of removing the timber within the time specified in the contract. The remark, if made at all, was made in the month of January, 1911, when defendants say that the roads were so muddy that they were unable to haul to any advantage.
Judgment affirmed.