Harrell v. City of Lufkin

280 S.W. 174 | Tex. Comm'n App. | 1926

NICKELS, J.

With certain supplementary statements to be made, the case is sufficiently stated in the opinion of the honorable Court of Civil Appeals (265 S. W. 179). To that court’s expression that the contract between Hadden & Austin and Shear, on the one hand, and the city, upon the other, stipulated for “alternative material” for the “waterbound macadam base,” should he added this statement: The “alternative material” had to’ he “stone” of sizes and quality equal to a standard prescribed. The statement that the city permitted “a novation in the contract” (between the builders and itself) as to the “alternative materials,” so as to permit part substitution of Galveston Bay “mudshell” for “stone,” should be elaborated by saying that this “novation” was made several months after the making of the contract between the city and Harrell, and that Harrell was not consulted about and was in no sense a party to the “novation.” The city’s right to recover is predicated alone upon the terms of the contract made with Harrell, which incorporated the original contract between the city and the builders. Performance of that original contract is expressly made the consideration of Harrell’s contract. Tjie city averred performance. Harrell denied, arid alleged lack even of" substantial performance, and existence of fraud and' mistake in the acceptance of the work and materials by the city.

That there was not a strict performance of the original (building) contract was affirmatively proved by the city and by Hat-rell, and found as a fact by the Court of Civil Appeals. All parties proved, also, the “novation” and intentional substitution of materials, and this is found as a fact by the Court of Civil Appeals. The jury returned a verdict (on a special issue submitted) to the effect that the pavement was not laid in substantial conformity to the requirements of Harrell’s contract.

With the record in that condition the honorable Court of Civil Appeals reversed the judgment of the district court and rendered judgment for the city for the amount claimed. That action rests upon these conclusions of *176law: (a) There is “no evidence raising an issue against an honest effort on the part of “the city” to protect “Harrell’s interests”; (b) there was an “acceptance” by the city, which is conclusive against Harrell in respect to performance, in accordance with the following term of the contract sued upon, to wit:

“It is agreed that the acceptance of said improvements by the city shall be conclusive between the parties hereto of the proper performance of the contract therefor.”

The first stated conclusion means (and was applied as me'aning) that there is no evidence to present an issue of fraud or gross mistake in the “acceptance.”

It is unquestionably true that parties to an executory contract may include in their agreement a provision designating a person or agency to supervise the work to be done or the materials to be used, and to inspect the same and report as to compliance, or not, of the work or materials, or both, with the contractual requirements, and they may give the supervisor’s acts and decisions res judicata effect. G. H. & S. A. Ry. Co. v. Henry & Dilley, 65 Tex. 685; Kilgore v. Baptist Ed. Soc., 35.S. W. 145, 89 Tex. 465; Jones v. Risley, 32 S. W. 1027, 91 Tex. 1; Craven v. Davison (Tex. Com. App.) 276 S. W. 196, 197; Deal v. Craven (Tex. Com. App.) 277 S. W. 1046; Blum Milling Co. v. Moore-Seaver Grain Co. (Tex. Com. App.) 277 S. W. 78, and other cases there cited. But whenever that effect is claimed, an inquiry about the scope of the referee’s power, immediately projects itself; his acts beyond that scope are coram non judicé, plainly, and perhaps in a stricter sense than is applicable to analogous judgments of courts. G. H. & S. A. Ry. Co. v. Henry & Dilley, supra, and the authorities to the point cited in Blum Milling Co. v. Moore-Seaver Grain Co., supra.

The inquiry exists regardless of presence (or absence) of contentions of fraud, gross mistake, etc.; and if the act done, or the decision made, is beyond the authority conferred, it lacks any element of conclusiveness, though done in utmost good faith and with proper skill. Id. He is not empowered to interpret the contract differently from its proper meaning, or to act “upon such construction as he may choose to give it”; and (save in exceptional cases, at least) he is not made the arbitrator to whom “is referred differences as to the meaning of the contract; and he cannot adopt rules of measurement,” etc., etc., “that it does not authorize”—all of which means, of course, that he cannot make a new contract for the parties. . Id. Application of these principles to the city’s “acceptance” here dispels its supposedly binding effect.

Eor Harrell’s contract was made in July, 1920, and, of necessity, “the proper performance of the contract” for “said improvements” (referred to in the provision for “acceptance by the city”) related to the' “improvements” stipulated for in the specifications then existing and the pre-existent “contract” of Hadden & Austin. There can be no warrant for saying that the agreement,between the city and Harrell, thus plainly made in July, 1920 (and which is the sole agreement as to “acceptance by the city” and the effect thereof), exerts operative force in respect to an “acceptance” of work done and materials used, under another and different (novated) contract made in October, 1920, to which Harrell was in no sense a party. The “improvements” thus “accepted” were not “said improvements” named in the stipulation relied upon, nor was the judgment used by the city in the “acceptance” exercised in respect “of the proper performance” of “the contract” referred to in the stipulation. It was not such an “acceptance” as was, or could have been, within the contemplation of Harrell and the city when they signed the contract upon which the suit was- brought; hence it was in no sense binding upon Harrell.

Because of the conclusions just stated, the question of whether or not there was evidence raising the issues of fraud or gross mistake in respect to the “acceptance by the city” is immaterial; hence, we do not discuss it. And because there is no alchemy in the city’s “acceptance” efficiently converting demonstrated nonperformance into that compliance which was within the parties’ expectations when the contract sued upon was made, the judgment of the trial court cannot be overturned for any of the reasons assigned by the Court of Civil Appeals. However, since a judgment may be right notwithstanding designation of an unsound reason, we notice some other things suggested by the record and the arguments of counsel.

Neither the pleading nor the evidence presents a condition under which the city might recover upon a quantum meruit, or in virtue of the doctrine of substantial performance. The essential basis of such relief is not alleged, nor is it prayed. Besides, the jury’s verdict is that there was not a substantial performance. That finding not only has ample support in the evidence, but the evidence is all one way upon it, for, as a matter of law, there is absence of “substantial performance,” since the changes were intentionally made and “structural” in their nature. Intentional material changes preclude existence of at least two of the primal elements of “substantial performance.” Linch v. Paris Lbr. & G. Co., 15 S. W. 208, 80 Tex. 23; Graves v. Allert & Fuess, 142 S. W. 869, 104 Tex. 614, 39 L. R. A. (N. S.) 591; City of Sherman v. Connor, 29 S. W. 1053, 88 Tex. 35; Atkinson v. Jackson (Tex. Com. App.) 272 S. W. 616, 619, 620; Ellison F. & C. Co. v. Langever, 113 S. W. 178, 135 S. W. 1059, 52 Tex. Civ. App. 50; Fessman v. Barnes (Tex. Civ. App.) 108 S. W. 170; Page on Con*177tracts, §§ 2780, 2781, 2783; 1 Beach, Modern Baw of Contracts, §§ 203, 204. The jury’s finding, in view of conflicting testimony as to comparative merit of the pavement contracted for originally and that finally laid, removes the third element of “practically equivalent quality and value.” Id.

In argument (oral and written) in behalf of the city, estoppel was suggested. Harrell’s' silence — failure to object to the character of pavement being laid, after knowledge of the change of materials, and consequent enhancement of his property values, is the predicate of that supposed estoppel. But he did not cause, or contribute by word or act to cause, the substitution. He was not consulted or otherwise called upon to affirm or disaffirm. The pavement was not on Harrell’s premises; it did not become his property, as a fixture or otherwise; nor did he accept the supposed benefits otherwise than as the same were (externally) imposed upon him. Such obligations as were involved in City of Sherman v. Connor, supra; Anderson Electric Co. v. Cleburne (Tex. Civ. App.) 44 S. W. 929; Jennings v. Willer (Tex. Civ. App.) 32 S. W. 24; Blakeslee v. Holt, 42 Conn. 226; Mercantile Trust Co. v. Hensey, 27 App. D. C. 210; and Twitty v. McGuire, 7 N. C. 501, could not arise against him. And, too, the injured party’s “ignorance of the truth” which is an element of estoppel by silence (16 Oye. p. 759) was wholly lacking. And no assignment of error relating to the question of estoppel was filed or presented in the city’s appeal from the district court’s judgment. The suggestion, therefore, cannot be well taken.

Accordingly, we recommend that the judgment of the Court of Civil Appeals be reversed, and that the judgment of the district court be affirmed.

CURETON, O. J.

The judgment recommended in the report of the Commission of Appeals is adopted and will be entered as the judgment of the Supreme Court.

midpage