68 Ill. App. 186 | Ill. App. Ct. | 1896
delivered the opinion op the Court.
The main controversy in this case arises over that portion of the decree of foreclosure of the Circuit Court which provided that out of the proceeds of the sale of the mortgaged premises the master should pay a pro rata sum of $20,468.40 in equitable consideration of the fact that appellees were entitled to that many bonds of the railroad company, under the contract of April 24, 1894, and supplemental contract, June 8, 1894, with the Brown & Windsor Construction Company for procuring the right of way, and expenses incurred therein; that the said sum should prorate with the authorized issue of bonds to the amount of $120,000, the same as though the first named sum had been an additional issue, and held by the appellees, thus in effect scaling down the amount that would be otherwise paid to the holders of the bonds actually issued in case the sale failed to produce enough to pay the entire amount foreclosed in this suit to the extent of the pro rata per cent of the claim for right of way and right of way expenses.
. It is insisted on the part of the appellees that the decree cm be sustained upon the ground that they had a vendor’s lien on the right of way to the amount of its cost, and the expenses incurred and paid by appellees, and although the basis of the decree was not on that theory, yet the amount they would receive would be less than they were entitled to on the proper basis.
We need not stop to inquire whether this position is based on proper grounds, as it will not be involved in the consideration of the case. We shall treat the claim as the bill did, as being one for a vendor’s lien on the right of way. It appears from the abstract of the various right of way deeds that they were all procured by appellees and executed to the Galesburg, Etherly & Eastern Railroad Company, between and including the dates of April 26, 1894 and August 18, 1894, except one deed dated June 1,1895, and of the consideration of $135. Something over two-thirds of the entire amount of $15,351.80 was paid out, and the deeds procured prior to June 6,1894, and the balance after that date.
The deeds in question were not handed over to the railroad company as they were obtained, but were retained by the appellees and were produced at the hearing and were ordered by the court in its decree to be turned over.
The building of the railroad by Harms was commenced immediately after the date of his contract of May 4, 1894, and completed October 27, 1894, and the bonds delivered to him in accordance with his contract as collateral security.
The bonds held by appellee have been sold and bought in by them under the provisions of their contract, and the Home National Bank and Henry Harms are the owners of the bonds not held by appellees. The Home National Bank became the owner of its forty bonds for money advanced to the Brown & Windsor Construction Company.
The lien claimed by appellee is not a lien by virtue of anything contained in the tripartite contract between them and the Galesburg Coal Company and the Brown & Windsor Construction Company, or the supplement thereto, but if a lien at all, is one created by the equitable principles of the law. It is not a statutory lien under any provision of the statute.
Under certain circumstances a vendor’s lien is created as between the vendor of real estate and the vendee where no intervening interests come in.
It is not a lien very much favored by law but is often enforced in equity. Whether or not such a lien will be enforced in any given case, depends so entirely upon the facts involved that no general rule can be very well laid down that will cover every kind of a case. As between vendor and vendee alone there can be no question but that a lien would be sustained, but as between that lien and a mortgage lien the latter is generally preferred.
" In the case of Fisk v. Potter, 2 Abb. App. Dec. 138, it is laid down as a general rule, that where two liens accrue at the same instant of time, and it becomes a question which of the two has superiority (the one a constructive one only arising out of a secret trust by operation of law or based upon the ground of its being a natural equity connected with the consideration of the property purchased, the other arising from a specific legal lien based upon written contract and matter of public record), the preference will be given to the latter. The facts in the latter quoted cases are not precisely as they are in this case, but the principle above announced we regard as sound. In Bagley v. Greenleaf, 7th Wheaton, 46, Justice Marshall lays down the following rule: “ A vendor relying upon this lien ought to reduce it to a mortgage so as to give notice to the world. If he does not, he is, in some degree, accessory to the fraud committed on the public by an act which exhibits the vendee as the complete owner of an estate upon which he claims a secret lien. It would seem inconsistent with the principles of equity and with the general spirit of our laAvs that such a lien should be set up in a court of chancery to the exclusion of bona fide creditors.”
The Supreme and Federal Courts of the United States hold a mortgage lien good as against equitable liens in favor of the claimants for claims for original construction, rails, frogs, etc., rental of leased lines, claims for rolling stock, salaries of officers, lost goods and sureties .on appeal bonds.
Liens are sometimes alloAved for wages performed for the railroad in producing its income, or “ going expenses,” as it is sometimes called.
We think all the circumstances show that they did not intend, when they entered into the contract of April 24, 1894, to retain a vendor’s lien on the right of way which they undertook to procure for the railroad company, and the outside circumstances and relationship of all the parties but strengthens this supposition.
The appellees Avere OAvners of the entire stock in the Galesburg Coal Company as appears from the evidence of R. W. Frost, who testifies that on April 24, 1894, Robert Frost’s Sons, S. L. Charles and W. H. Bates were the OAvners and holders of the capital stock of the Galesburg Coal Co., of Galesburg, Ill., that is, it was held by different members of the firm, not as a firm, but it was held by six individuals, four of whom composed the firm, and those were the Frosts who succeed to the rights of Charles and Bates.
There was also another project on hand and that was to lay out a town site on the lands owned by the Frosts which they were to sell by the terms of the contract, or a portion of it, at $60 per acre to the Brown & Windsor Construction Company, which company was to have a four-tenths interest therein.
It was therefore a great personal interest, or supposed to be, to Frosts, appellees, to have the railroad built as projected, otherwise the coal mine could not be developed nor the town built.
The contract of April 24,1894, signed by the appellees as the party of the third part, as also the contract to appellant Harms and Spikings, were both entered into and signed prior to the issuing of the first mortgage bonds in question; but, no doubt, under the circumstances, all parties knew what bonds were to be issued because the bonds were provided for in the two contracts, and it must have been known that they were to be issued, otherwise they would not have been mentioned.
Under the contract signed by appellees the Brown & Windsor Construction Company agreed to construct the railroad and depots and purchase a locomotive and such other equipment as might be necessary, and the appellees and Bates and Charles, whose rights they have succeeded to, agreed to furnish the money necessary to purchase the right of way and condemn it where it could not be purchased, and the title to the right of way was to rest in the railroad company, and to guarantee the contract of the Brown & Windsor Construction Company with the Illinois Steel Company for the purchase of the rails to be used in the construction of the railroad, not to exceed $30,000; and was to receive and did receive eighty of the bonds and the entire stock of the railroad company.
The right of way and steel rails were thus only provided for, and all the balance of the expenses and costs of building the railroad must be furnished by the Construction company.
And how was the Construction company to procure the money and build- the balance of the road % Manifestly, it must be out of money procured by the sale of the railroad bonds, which mtist have been contemplated would come into its hands from the railroad company, and which did actually come into its hands, as shown by the subsequent contracts and proceedings.
.These appellees must have understood this, as it is a legitimate conclusion from all the evidence and from a consideration of the various contracts. Appellees agreed with the Construction company to furnish the money and to procure the right of way, and take bonds as collateral security at seventy-five cents on the dollar, and there was no provision in the contract that they were to retain a lien of any kind.
Appellees, no doubt, perfectly understood that the railroad company must have the right of way clear before it could issue any bonds that would be salable, and must have, known that these bonds would be put on the market for sale, and that the purchasers would expect to get a clear title to the railroad right of way and franchisé for their security; therefore they were, no doubt, willing to accept the responsibility of the Construction company under their contract for their reimbursement for the money to be furnished for the right of way.
The Construction company and the railroad company were separate and distinct organizations, and as to the contract in question between appellees and the Construction-company, the railroad company had no privity, so far as the evidence discloses.
We must suppose, however, that the Construction company received some consideration for its undertaking to furnish the railroad company with the right of way, and that was, no doubt, the secret of its agreement with appellees to furnish the right of way to the railroad company, and the railroad company was required to do nothing.
It did, however, issue the bonds contemplated, mortgaging the right of way secured and to be secured.
Under these circumstances, whenever the deeds were made out and executed by the owner's of the land for the right of way, and paid for by the appellees, being in the name of the railroad company as grantee, the contract was contemplated and the title vested in the railroad company, the transaction amounted to a delivery of the deeds to it, and the mortgage immediately attached free of any incumbrance of a vendor’s lien. And the retention of the right of way deeds, on the part of appellees, without any authority by their contract so to do, made no difference as between them and the railroad company and the mortgage bondholders, and no record of the deeds was necessary to pass the title.
A deed without being recorded, if delivered to the grantee or some one for him, passes the title as effectually as though it were recorded. The appellees were the mere agents of the Oonstruction company by virtue of their contract with it to procure the conveyances of the right of way to the railroad company, and having accomplished that, the title passed free of any vendor’s lien.
The appellees knew very well that the mortgage would attach to the right of way as soon as the deeds were executed and that the railroad company was under no obligation to fulfill the contract of the construction company.
By the terms of the contract, and especially the supplemental contract of June 5, 1894, it was not contemplated that the railroad bonds should be delivered to the appellees to secure them in the advancement of the right of way money upon the procurement of the right of way deeds, because the supplemental contract provided that “ in the future and as soon as it can be done,” there should also be deposited with and assigned and delivered to appellees an additional amount of the said railroad bonds sufficient, at seventy-five cents on the dollar of their face value, to equal the money paid out for the right of way.
It will be seen that at this time over two-thirds in value of the deeds for the right of way had been procured, placing the title thereof in the railroad company, and afterward, knowing that the Construction company could not then deliver the bonds according to the contract as originally made, procured the balance of the right of way at a cost of over. $5,000.
, The procuring of the deeds and the delivery of the contemplated railroad bonds, were not required to be a contemporaneous act, and the non-delivery of the bonds was not to delay the procurement of the deeds.
It is insisted by counsel for appellees that the words “ as soon as it can be done,” referring to the delivery of the bonds, meant as soon as the total amount of right of way could be ascertained.
We do not think this is a fair construction of the clause. It is broader. It refers to any cause of delay, and a significant fact is that after delivering the eighty bonds to appellees, the Construction company had hypothecated, by contract or otherwise, all the remaining issue to appellant Harms and Spikings, and the Home Hational Bank.
We think it is a fair inference that appellees knew that fact and were willing to wait for their redemption by the Construction company so that they could be delivered.
We^do not think, however, that this is a vital point in appellant’s case.
In addition to those facts and circumstances, Harms and the railroad company and the Construction company were allowed to take possession of the right of way and spend their money in the building of the road, and The Home Hational Bank to furnish its money on the security of the railroad bonds.
During all this time appellee made no protest or claim of any vendor’s lien.
It would be inequitable now to allow them to set up such a claim.
It is insisted that, as the right of way deeds were not of record, the appellants purchased the railroad bonds at their own peril; but even if this be so, the appellants would only be held to notice of what they might have learned upon diligent inquiry, and an inquiry would only have resulted in ascertaining the facts as they actually existed at the time, and that would not defeat the attaching of the railroad mortgage or trust deed to the right of way.
We find these facts from the evidence : That it was the actual intention of appellees, at the time their contract and supplemental contract were made, to furnish the money and procure the right of way and place it in subordination to the lien of the first mortgage bonds; and it was their intention to accept the obligation of the Construction company for their security, and to not hold any lien on the right of way as against the mortgage.
They can not, therefore, be allowed to interpose any claim for a vendor’s lien against the holder of the mortgage bonds actually issued.
Their claim for the money advanced for the right of way and expenses must be regarded as an unsecured claim as against the mortgage sought to be foreclosed in this suit, and such claim is not entitled to be paid out of the proceeds of the sale to be made under a decree for the payment of the mortgage bonds in question.
If any surplus should remain after paying the mortgage bonds and costs of foreclosure and sale, such surplus will remain in court to .be distributed, according to t q lity and justice, to the parties entitled to it.
For the errors above noted'in the decree, allowing appellees to share in the payment of their claim for right of way, disbursements out of the proceeds of the sale ordered in the decree, and not holding the mortgage bonds a paramount lien to all others, the decree of the court below is reversed and the cause remanded, with direction from this court to the Circuit Court to render a decree in accordance with this opinion, and to reject the claim of appellees for reimbursement out of the proceeds arising from the sale to be ordered for the payment of the first mortgage railroad bonds.