Appellants/Relators, Hardin Construction Group, Inc. and San Antonio 2000, Ltd. *310 (“Hardin”), seek relief from the trial court’s denial of Hardin’s motion to compel arbitration with Strictly Painting, Inc. (“Strictly”). Pursuant to the Texas Arbitration Act, Hardin has filed an interlocutory appeal of the trial court’s order denying the motion. Hardin has also filed a motion for leave to file a petition for writ of mandamus under the Federal Arbitration Act. We previously granted the motion for leave to file the petition for writ of mandamus and consolidated the two proceedings.
We conclude the Federal Arbitration Act applies; therefore, we dismiss Hardin’s interlocutory appeal. In addition, we conditionally grant the writ of mandamus because we conclude that Judge Peeples abused his discretion in his resolution of the factual issue regarding the existence of an agreement to arbitrate.
Facts
Hardin is a Georgia corporation and was the general contractor on a Hyatt Regency project in San Antonio, Texas. Hardin accepted a bid from Strictly for a painting subcontract. Strictly also is a Georgia corporation.
On November 2,1995, shortly after Hardin accepted Strictly’s bid, Hardin forwarded a form of subcontract to Strictly for execution. The subcontract form was identical to the subcontract executed by Strictly in connection with three previous Hardin projects that were in excess of $100,000.00, with the exception of the performance bond requirement. Each of the subcontracts included an arbitration provision. A similar arbitration provision was also included in Hardin’s short form subcontract that Strictly had executed in connection with numerous smaller Hardin projects.
On November 20, 1995, Strictly submitted its first monthly request for payment. Although Hardin paid the request, Hardin forwarded a letter to Strictly dated December 7, 1995, stating that it was not obligated to make any payments until the signed Subcontract and Bonds were returned to Hardin.
On December 12, 1995, Strictly returned the unexecuted subcontract to Hardin with a letter implicitly agreeing to all of its terms except that Strictly wanted to eliminate the bond requirement. Strictly stated that since the bid documents did not indicate or request bonds, no bonds were quoted. Strictly concluded:
In good faith Strictly Painting mobilized and began work on this project prior to receiving this contract. We will continue to work with the intention that this would not be a stumbling block. Please make these changes and forward the contract so that I may sign and return within 2 days.
Between December 12, 1995, and December 17, 1995, a series of field orders were executed by the parties regarding additional work to be performed by Strictly on the project. On December 19,1995, Strictly submitted its second monthly request for payment, which Hardin paid. Between December 20, 1995, and January 16, 1996, another series of field orders were executed regarding additional work. Then, by letter dated January 18, 1996, Hardin demanded that Strictly immediately execute the subcontract and fulfill the bond requirement. Hardin stated that it would reimburse the cost of the bond.
The parties were never able to subsequently resolve the bond issue, 1 and Strictly never executed the subcontract. Nevertheless, Strictly continued to perform and substantially completed its work on the project.
Ultimately, Strictly sued Hardin alleging breach of contract/estoppel, fraud, quantum meruit and lien claims. Strictly alleged that Hardin “wrongfully refused to make progress payments and to date has wrongfully withheld approximately $557,872.50.” Hardin answered and filed a motion to stay the trial proceeding and to compel arbitration. Strictly responded by denying that it entered into an agreement to arbitrate. After an *311 evidentiary hearing, Judge Peeples denied Hardin’s motion to compel.
Federal or State Arbitration Act
The Federal Arbitration Act applies to contracts relating to interstate commerce.
Jack B. Anglin Co. v. Tipps,
1. Both Hardin and Strictly are Georgia corporations based in Atlanta, Georgia.
2. The project was located in Texas.
3. Strictly retained the services of Texas subcontractors and a subcontractor based in Alabama.
4. Employees were hired in Georgia to perform work on the project in Texas.
5. Supplies were purchased by Strictly in Texas.
Therefore, we conclude that the contract at issue relates to interstate commerce, the Federal Act applies to this dispute, and Hardin may seek relief through the remedy of a writ of mandamus. Accordingly, we dismiss Hardin’s interlocutory appeal and proceed to consider its mandamus petition. 2
Standard of Review
Hardin couches its complaint regarding Judge Peeple’s denial of its motion to compel arbitration in terns of an abuse of discretion standard. Strictly responds that the trial court’s order is reviewed under a “no evidence” standard. Therefore, we must first consider the proper standard of review applicable in reviewing a trial court’s determination regarding the existence of an arbitration agreement in a mandamus proceeding.
For its contention that the trial court’s order should be reviewed under a “no evidence” standard, Strictly cites
Hearthshire Braeswood Plaza Ltd. Partnership v. Bill Kelly Co.,
The Texas Supreme Court has not commented on the appropriate standard of review; however, the Court has stated that if material facts necessary to determine an issue to be summarily decided by the trial court are controverted, the trial court must conduct an evidentiary hearing to determine the disputed material facts.
Jack B. Anglin Co.,
*312
Under the federal law, a district court’s finding regarding the existence of an agreement to arbitrate is reviewed like “any other district court decision finding an agreement between parties, i.e., accepting findings of fact that are not ‘clearly erroneous’ but deciding questions of law
de novo.” First Options of Chicago, Inc. v. Kaplan,
In
Walker v. Packer,
the Texas Supreme Court recognized that the abuse of discretion standard contains both a factual and legal component.
We can discern no reasonable basis for reviewing a trial court’s findings as to the existence of an arbitration agreement differently than other findings a trial court is required to make in exercising its discretion. Accordingly, the factual component of the abuse of discretion standard, which is similar to the clearly erroneous standard applied by the federal courts, appears to be a more appropriate standard for reviewing such findings than a “no evidence” standard. Therefore, we hold that the proper standard for reviewing a trial court’s determination regarding the existence of an arbitration agreement in a mandamus proceeding is abuse of discretion.
Factual Finding
Hardin contends that since Strictly only objected to the bond requirement in the subcontract form, Strictly agreed to all the other terms of the subcontract, including the arbitration provision. Strictly counters that its performance was based upon the contract formed by the bid documents and that the letter establishes that the subcontract form included new terms that were unacceptable. Since Hardin did not remove the unacceptable terms, Strictly asserts that an agreement as to the subcontract form, including the arbitration provision, was never reached.
Although the Federal Act is applicable in the instant case, we apply Texas law in determining whether the parties agreed to arbitrate.
See First Options of Chicago, Inc. v. Kaplan,
Whether Hardin and Strictly agreed to arbitrate is a question of fact governed by the foregoing general contract principles.
See Shearson Lehman Hutton, Inc. v. McKay,
The bond was not an essential term of the contract as is evidenced by the fact that Strictly substantially performed the work in its absence. Given Strietly’s letter stating that it would execute and return the subcontract upon deletion of the performance bond requirement and its continued performance in a manner consistent with the subcontract terms, we find that the only reasonable conclusion that Judge Peeples could have reached was that Strictly agreed to be bound by all the terms of the subcontract except the performance bond requirement. Therefore, Judge Peeples should have determined that Hardin and Strictly agreed to arbitration. Since Judge Peeples reached the opposite conclusion, we hold that he abused his discretion.
Conclusion
When a trial court erroneously denies a party the right to arbitration under the Federal Act, the party has no adequate remedy at law.
EZ Pawn Corp. v. Mancias,
Notes
. Strictly’s president testified in his affidavit and at the evidentiary hearing that a bond could not be obtained after performance commenced. Hardin’s project manager agreed during cross-examination at the evidentiary hearing that obtaining a bond after construction had commenced would be difficult.
. Strictly suggests that we treat Hardin’s interlocutory appeal as an election of remedies or, alternatively, find the interlocutory appeal to be frivolous and take other appropriate action. The Texas legislature’s failure to provide for an interlocutory appeal of the denial of a motion to compel pursuant to the Federal Act has been criticized by the Texas Supreme Court.
See Jack B. Anglin Co.,
