Har-Mar, Incorporated v. Thorsen & Thorshov, Inc.Har-Mar, Incorporated v. Thorsen & Thorshov, Inc.
Plaintiff, Har-Mar, Incorporated, brought this action to enjoin an arbitration proceeding demanded by defendant, Thorsen & Thorshov, Inc., an architectural firm, and for a declaratory judgment declaring defendant’s right to proceed with arbitration of a dispute concerning architectural feеs barred by reason of our 6-year statute of limitations or, in the alternative, by waiver and laches. The trial court, by directing summary judgment for plaintiff, enjoined defendant Thorsen from proceeding further with arbitration, determining that such proceedings were barred by our statute of limitations and that Thorsen had waived its contractural right to arbitrate the dispute. Holding that Thor-sen’s contractual right to compel arbitration of the fee dispute is not barred by the statute of limitations and that the record does not establish a waiver of that right as a matter of law, we reverse and remand for trial on the merits of plaintiff Har-Mar’s allegations of waiver and laches.
In April 1962, the parties entered into a contract whereby Thorsen agreed to furnish architectural services to Har-Mar in the construction of a shopping center in Roseville, Minnesota. Paragraph 12 of the contract provides for arbitration of future disputes arising under the contract and expressly states:
“Arbitration of all questions in dispute under this Agreement shall be at the choice of either party and shall be in accordance with the provisions, then obtaining, of the Standard Form of Arbitration Procedure of The American Institute of Architects. This Agreement shall be specifically enforceable under the prevailing arbitration law and judgment upon the award rendered may be entered in the court of the forum, state or federal, having jurisdiction. The decision of the arbitrators shall be a condition precedеnt to the right of any legal action.”
On December 19, 1963, Thorsen issued a certificate of completion which declared that the construction of the shopping center had been completed in accordance with the plans and specifications. The final billing was subsequently submitted to Hаr-Mar in March 1964. Thereafter, a dispute arose concerning the amount due Thorsen for architectural services. Negotiations were conducted during the months that followed, but unsuccessfully concluded in 1966 when Har-Mar rejected Thorsen’s last compromise offer.
During the pendency of the disаgreement over fees, a dispute arose over alleged defects in the roof of Har-Mar Mall. The roof dispute culminated in an action commenced in September 1966 by Har-Mar against Thorsen and others. Thorsen, whose fee dispute would have been a compulsory counterсlaim, 1 preferred to have its dispute arbitrated rather than tried in conjunction with Har-Mar’s action. For that reason, Thorsen wrote to Har-Mar on September 30, 1966, demanding that Har-Mar submit the fee dispute to arbitration and threatening to apply for a court order compelling arbitration. Through their respective counsel, Thor-sen and Har-Mar reached an agreement on December 27, 1967, which allowed Har-Mar to adjudicate the roof dispute in court and Thorsen to reserve its fee dispute for “independent disposition.”
On July 26,1972, Thorsen caused a formal demand for arbitration of thе dispute to be served on Har-Mar and filed notice of the demand with the American Arbitration Association. On September 8, 1972, Har-Mar commenced this action for declaratory and injunctive relief, which resulted in the entry of summary judgment for Har-Mar. Thorsen appeals.
In a memorandum supporting its ordеr for summary judgment, the trial court stated that “both arbitration and judicial proceedings are equally subject to the Statute of Limitations.” Mindful that
Minn. St. 541.05 reads in pertinent part:
“* * * [T]he following actions shall be commenced within six years:
(1) Upon a contract оr other obligation, express or implied, as to which no other limitation is expressly prescribed.” (Italics supplied.)
Minn. St. 645.45(2) defines “action” as “any proceeding in any court of this state.” (Italics supplied.) However, since our statute of limitations was in existence as early as 1927, and since the definitional stаtute enacted in 1941 expressly limits its application to laws thereafter enacted, it follows that this statutory definition is not controlling.
Har-Mar points to Minn. St. 336.1 — 201(1) of the Uniform Commercial Code as a more recent legislative pronouncement of the meaning of “action,” suggesting that it includes “any * * * prоceedings in which rights are determined.” We believe a full reading requires an interpretation that the term in the context of the issue presented is expressly restricted to judicial proceedings. The statute reads:
“(1) ‘Action’ in the sense of a judicial proceeding includes recoupment, counterclaim, setoff, suit in equity and any other procеedings in which rights are determined.” (Italics supplied.)
The few Minnesota cases which have attempted a common-law definition of the term “action” have restricted it to “the prosecu
tion in a court of justice of some demand or assertion of right by one person against another.” Seе, e.g., Muirhead v. Johnson,
Conceding that there is no controlling statutory definition of the term “action,” Har-Mar argues that arbitration should be held to be an action subject to our 6-year statute of limitations by implication because (1) prior to legislative enactment of the Uniform Arbitration Act in 1957, no controversy could be arbitrated unless specific performance of the arbitration agreement could be judicially compelled;
2
and (2) after enactment, arbitrаtion was even more clearly an action because the act authorizes arbitrators to determine legal as well as factual claims by employing procedures common to judicial proceedings, such as the subpoena of witnesses, the taking of depositions, and judicial аction to confirm, vacate, modify, correct, and enforce an arbitration award. Such argument is contradictory of the historic objective, purpose, and intent of the Uniform Act. The statutory design of the act and its prototypes, the New York act of 1920 and the United States Arbitration Act оf 1925, as advanced by the proponents of arbitration, is to encourage voluntary, speedy, inexpensive, private, and final out-of-court arbitration of commercial contractual disputes by commercial experts.
3
As we declared in Layne-Minnesota Co. v. Regents of University,
“* * * Even thоugh resort to courts is authorized, the basic intent of the act is to discourage litigation and tofoster voluntary resolution of disputes in a forum created, controlled, and administered by the written agreement.”
Supporting this view of the special, non judicial nature of arbitration proceedings is the case of Skidmore, Owings & Merrill v. Connecticut Gen. Life Ins. Co.
“Arbitration is not a common-law action, and the institution of arbitration proceedings is not the bringing of аn action under any of our statutes of limitation. ‘Arbitration is an arrangement for taking and abiding by the judgment of selected persons in some disputed matter, instead of carrying it to the established tribunals of justice * * *.’ ”
Har-Mar cites New York and California cases as authority for the proposition that arbitratiоn proceedings are indeed actions and thus subject to the statute of limitations. The New York cases, however, are of little value since at the time the cases were decided New York’s statutes of limitation included arbitration proceedings. See, Reconstruction Finance Corp. v. Harrisons & Crosfield, Ltd.
Based upon the special nature of arbitration prоceedings and both the statutory and common-law meaning of the term “action,” we feel compelled to hold that § 541.05(1) was not intended to bar arbitration of Thorsen’s fee dispute solely because such claim would be barred if asserted in an action in court.
There remains the question of whethеr the right to compel arbitration, as distinguished from an action on the underlying claim, is barred. In its complaint, Har-Mar requested the district court to bar Thorsen not only from demanding arbitration but also “from bringing any other action on the aforesaid contract.” Such relief necessarily raises the question of the application of the statute of limitations to a judicial proceeding to compel arbitration.
Clearly, an action in district court to compel arbitration is an action arising “upon a contract” and thus must be subject to the 6-year limitation prescribed by § 541.05(1). Such a cause of action accrues upon a demand for arbitration by one party and a refusal by the other. Proof of these two conditions precedent to the birth of such a cause of action is required by the Uniform Act, § 572.09(a) of which reads:
“On application of a party showing an agreement described in section 572.08, and the opposing party’s refusal to arbitrate, the court shall order the parties to proceed with arbitration
* # * 99
It is thus clear that our 6-year limitation statute does not begin to run until
The trial court also ruled that Thorsen, “by its unexplаined 8% year delay in commencing arbitration proceedings, waived any right it may have had to arbitrate.” Review of this conclusion necessarily raises two questions: (1) Whether, upon this record, the court was justified in summarily determining that Thorsen’s conduct “constitutes waiver as a matter of law”; and (2) since it is undisрuted that a written agreement to arbitrate the fee existed, whether the court should have declined to decide this issue as one referable to arbitration.
Fraud in the inducement, waiver, laches, or limitation statutes, when asserted against a breach-of-contract claim, may be chаracterized as collateral defenses raising legal issues which, if established, preclude reaching the merits of the dispute sought to be arbitrated. While the term “waiver” is not susceptible of precise definition, for the purpose of reviewing the trial court’s decision upon this appeаl where the defense was interposed and considered as working a forfeiture of Thorsen’s right to compel
arbitration of its fee dispute, it can be defined simply as “a voluntary relinquishment of a known right.” Beck v. Spindler,
The more difficult jurisdictional question as to which forum should decide the issues of laches and waiver need not be answered. Although implicitly ruled on by the trial court, the question was neither raised nor argued below or here. Moreover, both parties appear agreed that the court, rather than the arbitrators, should decide the merit of these issues on a remand; and agreement, whether or not constituting a modificаtion
Reversed and remanded.
Notes
Rule 13.01, Rules of Civil Procedure.
Minn. St. 1953, § 572.01, repealed by L. 1957, c. 633.
See, e.g., Grover-Dimond Associates v. American Arbitration Assn.
The present statute, 7B McKinney’s Consol. Laws of New York Ann., Civil Practice Law and Rules, § 7502(b) provides in pertinent part: “If, at the time that a demand for arbitration was made or a notice of intention to arbitrate was served, the claim sought to be arbitrated would have been barred by limitation of time had it been asserted in a court of the state, a party may assert the limitation аs a bar to the arbitration on an application to the court * * *. The failure to assert such bar by such application shall not preclude its assertion before the arbitrators, who may, in their sole discretion, apply or not apply the bar.”
See, Jabine, The Statute of Limitation and Arbitration in Connecticut, 19 Arbitration Journal 206.
We are advised that the arbitration clаuse contained in the parties’ agreement was a standard clause suggested by the American Institute of Architects. Subsequent to the decision in Skidmore, Owings & Merrill v. Connecticut Gen. Life Ins. Co.
Cf. Sears Roebuck & Co. v. Herbert H. Johnson Associates, Inc.