THE HANOVER INSURANCE COMPANY, Plaintiff-Appellee, v. BINNACLE DEVELOPMENT, L.L.C., formerly known as BINNACLE DEVELOPMENT AND CONSTRUCTION, L.L.C.; LONE TRAIL DEVELOPMENT, L.L.C.; SSLT, L.L.C., Defendants-Appellants.
No. 21-40662
United States Court of Appeals for the Fifth Circuit
January 12, 2023
Appeal from the United States District Court for the Southern District of Texas USDC No. 3:19-CV-111
Before HIGGINBOTHAM, SOUTHWICK, and HIGGINSON, Circuit Judges.
An insurer sued three developers for reimbursement of expenses. The developers seek to reduce their obligation through a damages clause they say is permissible for “district contracts” under the Texas Water Code. The relevant contracts, though, were not executed by a district. Summary judgment for the insurer is AFFIRMED.
FACTUAL AND PROCEDURAL BACKGROUND
This dispute involves three construction projects (the “Projects“) in Galveston County, Texas. Hanover Ins. Co. v. Binnacle Dev., L.L.C., 493 F. Supp. 3d 585, 587 (S.D. Tex. 2020). The defendants, Binnacle Development, Lone Trail Development, and SSLT, are land developers. Id. All three are controlled by Jerry LeBlanc, Jr.
Each developer contracted with R. Hassell Properties, Inc. to complete paving and infrastructure projects in Galveston County Municipal Utility District (“MUD“) No. 31.1 Id. The three Hassell contracts were form MUD contracts created by MUD attorneys. Each contract stated that it was “for Galveston County Municipal Utility District No. 31.”
Hassell won the contracts after a public bidding process mandated by statute. See
At Hassell‘s request, Hanover “issued payment and performance bonds as a surety in favor of the [developers] for” the Projects. Hanover Ins. Co., 493 F. Supp. 3d at 587. As part of the surety arrangement, Hanover and Hassell entered into an indemnity agreement. Id. Under that agreement, Hanover would be assigned the contract balances for the Projects in the event that Hassell defaulted. Id.
Hassell ultimately failed to complete construction on the Projects and defaulted. Id. Hanover then took over the contracts and completed the Projects after the contract deadlines.
Hanover subsequently sued the developers in federal court to recover the contract balances on the Projects. The parties agreed that — absent any offsets, described
5. LIQUIDATED DAMAGES FOR DELAY/ECONOMIC DISINCENTIVE . . . Therefore, the Contractor and the Owner agree that for each and every calendar day the Work or any portion thereof shall remain uncompleted after the expiration of the time limit(s) set in the Contract, or as extended under [other contract provisions] . . . Contractor shall be liable to Owner for liquidated damages in the amount of $2,500 for each such calendar day, which sum the parties agree is a reasonable forecast of the damages the Owner will sustain per day that the Work remains uncompleted and in no way constitutes a penalty. Said $2,500 per day shall also be considered an “economic disincentive for late completion of the Work” pursuant to Section 49.271(e), Texas Water Code.
Section 49.271 of the Water Code authorizes “economic disincentives for late completion of [] work” to be imposed in a “district contract.”
Both parties moved for summary judgment. Id. The district court addressed two issues: “(1) Whether the Texas Water Code applies to the parties’ contracts, and (2) if not, whether the liquidated-damages clauses constitute unenforceable penalties under Texas common law.” Id. at 588-89. On the first issue, the court analyzed the Texas Water Code. Id. at 589-90. It concluded that because no district is a party to the contracts at issue, the economic disincentive provision from the Water Code does not apply. Id. at 590. On the second issue, the court found that the damages clauses in the contracts constitute an unenforceable penalty. Id. at 592. The court granted summary judgment for Hanover. Id. The developers appealed.
DISCUSSION
Summary judgment is proper when “there is no genuine dispute as to any material fact.”
“In Texas, the construction of a contract presents a question of law.” Balfour Beatty Constr., L.L.C. v. Liberty Mut. Fire Ins. Co., 968 F.3d 504, 509 (5th Cir. 2020). This court “review[s] de novo questions involving the construction or interpretation of contracts.” L & A Contracting Co. v. Southern Concrete Servs., Inc., 17 F.3d 106, 109 (5th Cir. 1994). Similarly, “[t]he construction of a statute is a question of law which the Court reviews de novo.” Grigg v. C.I.R., 979 F.2d 383, 384 (5th Cir. 1992).
The developers make two arguments here. The first is that the Hassell contracts are district contracts, with their liquidated-damages provisions validated by the Water Code‘s authorization of economic disincentives in contracts. The second is that even if the provisions are not protected by the Water Code, the liquidated-damages provisions are enforceable because they are not a penalty.
I. District contracts
We first consider whether Chapter 49 of the Water Code applies to the Hassell contracts. Even if it does, the second issue is whether the Water Code authorizes the terms of the liquidated-damages provision. We conclude the Water Code does not apply and end our analysis there.
Chapter 49 of the Water Code is titled “Provisions Applicable to All Districts” and applies to “all general and special law districts.”
(a) Any contract made by the board for construction work shall conform to the provisions of this chapter.
. . .
(e) A district contract for construction work may include economic incentives for early completion of the work or economic disincentives for late completion of the work.
The “board” refers to the “governing body of a district.”
Hanover sees this as a straightforward case. Section 49.271 begins by noting its limited applicability: “Any contract made by the board for construction work shall conform to the provisions of this chapter.” (emphasis added). The plain language of Section 49.271, Hanover argues, forecloses its application to contracts between two private parties. Hanover contends that legislative history reiterates this conclusion. That history demonstrates that Section 49.271 “authorize[s] districts to include economic incentives for early completion of construction contracts.” H. Research Org. Bill Analysis, Tex. H.B. 1541, 78th Reg. Sess., at 4 (2003) (emphasis added).
“[I]f a statute is unambiguous,” courts must “adopt the interpretation supported by its plain language unless such an interpretation would lead to absurd results.” TGS-NOPEC Geophysical Co. v. Combs, 340 S.W.3d 432, 439 (Tex. 2011). The text of Section 49.271 certainly supports that the “economic disincentives” language is relevant only to a contract “made by the board” of a district.
First, the developers argue that because Section 49.271 is not, like some other sections, limited “only to a district,” it does not require a district to be a contracting party. We disagree with the premise, as Section 49.271(a) limits its applicability to contracts “made by the board,” and boards govern districts. Still, we examine the developers’ examples. We find the cited sections to limit their applicability to specific types of districts. One example is a section which “applies only to a district that is located wholly within the boundaries of a municipality with a population of more than 1.5 million.”
Though some sections in Chapter 49 are limited only to certain types of districts, that does not support that Section 49.271, which lacks identical language, should apply regardless of whether a district is involved. In fact, we find the opposite conclusion more reasonable. Chapter 49 is titled “Provisions Applicable to All Districts.” The structure of Chapter 49 suggests that the chapter, as a whole, applies only to districts unless a section narrows its application to certain types of districts.
Next, the developers argue that Section 49.278 of Chapter 49, which is entitled
Third, the developers argue that Chapter 2253 of the Texas Government Code provides that district contracts need not include a district as a contracting party. Chapter 2253 governs performance and payment bonds on public works projects. See
The developers argue Chapter 2253 contemplates that a “public works contract” can include a contract between a prime contractor and a subcontractor, which are two private parties. Thus, the developers reason, Chapter 49‘s incorporation of Chapter 2253 indicates the former also applies to a contract between two private parties.
Whether Chapter 2253 even applies is unclear due to the absence of any public entity in the Hassell contracts. The section of Chapter 2253 that prescribes bonding requirements applies only when a “governmental entity [] makes a public work contract with a prime contractor.”
Fourth, the developers argue that the definition of “district facility” under the Water Code favors a broad reading of “district contract.” “District facility” is defined, in part, as “any plant [or] equipment . . . supplied for . . . the business or operations of a district.”
The developers are correct that the Hassell contracts were “for Galveston County Municipal Utility District No. 31.” Further, the Galveston County MUD planned to purchase the infrastructure upon completion. There is, though, no need to explore other sections of the Water Code when the relevant section here prescribes its own scope. As we stated earlier, Section 49.271(a) states that it applies to contracts “made by the board” of a district. The “district facility” definition does not alter that requirement.3
Finally, the developers argue, in the alternative, that even if the Hassell contracts are not district contracts, they incorporate the economic disincentive provision
The comparison to the FAA is imaginative but inapt. The text of Section 49.271 limits it to “district contracts.” There is no text to support that private parties may rely on, or indeed are protected by, Section 49.271 where there is no contract executed by the district board. The better analogy is based on the fact that the FAA applies to contracts involving foreign and interstate commerce. See
We hold that Section 49.271 allows “economic disincentive” clauses only in contracts where a district is a contracting party. Because no district is party to the Hassell contracts, they cannot incorporate “economic disincentive” clauses permitted under the Texas Water Code.
II. Liquidated damages analysis
Even though the Water Code is inapplicable, that does not automatically invalidate the damages clause here. In Texas, liquidated damages cannot “function[] as a penalty” and “must not be punitive, neither in design nor operation.” Atrium Med. Ctr., LP v. Houston Red C LLC, 595 S.W.3d 188, 192 (Tex. 2020). The developers understandably do not try to make that standard apply. Instead, they seek to avoid it altogether by contending the damages clause is not a liquidated-damages provision but one that limits liability. The damages clause, they say, is meant to “reduce or offset any amount owed, as opposed to being used as an affirmative claim to recover liquidated damages.” Therefore, the argument goes, the damages clause is not subject to Texas‘s liquidated-damages jurisprudence.
To decide what this provision is, we are guided by the need to “look to the substance of the contract‘s terms to determine if [a] provision constitutes ‘liquidated damages.‘” Sunbelt Servs., Inc. v. Grove Temp. Serv., Inc., No. 05-05-01090-CV, 2006 WL 2130144, at *3 (Tex. App. — Dallas Aug. 1, 2006).
The damages clause is entitled “LIQUIDATED DAMAGES FOR DELAY/ECONOMIC DISINCENTIVE” and expressly provides for “liquidated damages in the amount of $2,500 for each [] calendar day” of delay. This provision does not, in substance, set a mere limitation of liability or delimit damages to “an agreed maximum.” 24 WILLISTON ON CONTRACTS § 65:6 (4th ed.). Rather, the clause provides that Hassell is liable for the liquidated damages of $2,500 for every day the Projects are late. Looks like a liquidated-damages provision to us.
Moreover, the damages clause bears little resemblance to recognized limitation of liability clauses. In one of our decisions, for example, we found a limitation of liability clause where the contract stated that “[i]n no event shall the liability of either party . . . exceed $500,000.” Global Octanes Texas, L.P. v. BP Expl. & Oil Inc., 154 F.3d 518, 521 (5th Cir. 1998). In another opinion, a Texas Court of Appeals concluded that a provision stating “liability is
Because the developers do not contend that the damages clause survives a liquidated-damages analysis, we need not consider that possibility. See Cinel v. Connick, 15 F.3d 1338, 1345 (5th Cir. 1994). We do not disturb the district court‘s finding that the clause is an unenforceable penalty under Texas law.
AFFIRMED.
