204 Mass. 513 | Mass. | 1910
This is an action to recover a balance due a contractor for the construction of a building. One of the counts was upon an account annexed, which opened to the plaintiff the right of recovery upon a quantum meruit for labor and materials. The defendant requested, among others, the following instructions:
“ That if the jury believe that pages one and two of the speci
“ If the jury shall be of the opinion that pages, one and two of the specifications entitled ‘ General Conditions ’ were not apart of the original contract, then that where a payment is due only on completion of the contract, as here, the plaintiff must show substantial completion; that is, if the plaintiff unknowingly omitted to do certain things required by the contract, and they are of such a nature that the work is complete in all material respects, then the contractor may recover the contract price less what it would necessarily cost to complete the work, but the performance so far as it goes must be in exact compliance with the terms of the contract; that to constitute substantial performance a general adherence to the plans and specifications is not sufficient, the builder not being entitled to wilfully or carelessly depart from minute details or to leave his work incomplete in any material respect; that the builder is not entitled to make changes that are so substantial that an allowance out of the contract price will not give the owner substantially what he contracted for, or to omit work that cannot be done by the owner except at great expense or with great risk to the building.
“ That this doctrine of substantial performance does not apply where omissions by the builder were intentional, or where the contract is to be performed to the satisfaction of the owner.”
The law relative to the matters mentioned in these requests has been considered in different cases, and it was discussed at length in Bowen v. Kimbell, 203 Mass. 364. To entitle the plaintiff to recover in a case of this kind there must be an honest intention to perform the contract and an attempt to perform it. There must be such an approximation to complete performance that the owner obtains substantially what was called for by the contract, although it may not be the same in every particular, and although there may be omissions and imperfections on account of which there should be a deduction from the contract price. It is not necessary that the work should be complete in all material respects, nor that there should be no omissions of work that cannot be done by the owner except at great expense
There is no reason why the doctrine of substantial performance should not apply where the contract is to be performed to the satisfaction of the owner, according to the usual meaning of this expression as applied to contracts of this kind, namely, to his satisfaction, so far as he is acting reasonably in considering the work in connection with the contract. This doctrine does not apply where the builder intends not to perform the contract. But an intentional omission to do certain things called for by the contract, if he believes that they are not called for, and intends in good faith to do all that he has agreed to do, does not , prevent the application of the doctrine. These requests for rulings were rightly refused.
Another request numbered three,
The erection of a building upon real estate ordinarily confers a benefit upon the owner, and he should not be permitted to escape payment for it on account of a personal idiosyncrasy. Indeed, under the law of Massachusetts, this question is usually of little practical application to contracts for buildings upon real estate; for if the contract is not performed by reason of the failure of the owner to be satisfied with that which ought to satisfy him, there can be a recovery upon a quantum meruit; and in most cases the deduction that would be made from the contract price, for the difference between the literal performance of the contract and that which would have been a complete performance if the owner had acted reasonably and accepted the work, would be little if anything. This request for an instruction was rightly refused.
The instruction requested “ that Article II of this contract, to the effect that the decision of the architect as to the true construction and meaning of the drawings and specifications shall be final, is a condition binding upon the parties ” was correct, and should have been given. It is well established that, where a building contract makes the architect an arbitrator between the parties to determine practical questions of construction that arise under the plans and specifications in the execution of the work, his decision upon these matters is binding. Norcross v. Wyman, 187 Mass. 25. Hubbard v. Dewey, 191 Mass. 403. This rule of law had an important bearing upon the claims of the plaintiff for extra work, about which there was a dispute
The defendant also requested three other instructions, which were a concrete application of this, provision of the contract to specific matters in dispute under the plaintiff’s claim for extra work, and these were also correct statements of the law, if, without express language to that effect, we may assume that the architect’s construction of the specifications referred to in each request was his real construction, made in good faith, and not a pretended or fraudulent construction. In the present case there are circumstances from which it might be contended that the architect was not acting fairly. The fact that he was the husband of the owner, and acted as her agent in procuring the erection of the building and in dealing with the plaintiff while the work was going on, brings the question of good faith into prominence. It may be that the judge was not obliged to give these instructions because they did not in express terms include the element of good faith as entering into the architect’s conduct. But the judge’s attention was directed to these important* subjects, upon which the jury well might have been instructed.
The defendant is right in her contention that, under article ten of the contract, no payment shall be construed to be an acceptance of defective work or improper materials. This does not mean that, upon a question whether there has been an acceptance by the owner, a payment without objection may not be considered, in connection with other evidence, as other similar conduct may be considered, so far as it indicates his purpose and state of mind. It simply means that such a payment does not of itself constitute such an acceptance. The instruction requested on this question properly might have been given, although it was
The request for an instruction, that upon the “ auditor’s report the plaintiff cannot recover the balance due on the contract price,” evidently had reference to the fact that certain amounts which were allowed by the auditor as a set-off should have been used directly in diminution of the contract price. This did not affect the result, and the request ivas covered in substance, although not in terms, by the language of the charge.
Exceptions sustained.
This request is quoted in full, ante, p. 517.