52 P. 512 | Or. | 1900
Lead Opinion
Decided 14 March, 1898.
On Motion to Dismiss Appeal.
f 52 Pao. 512.]
This is a motion to dismiss an appeal. The transcript shows that plaintiff, a private corporation, commenced this suit to foreclose a lien upon lots 5 and 6, in block 92, in the City of East Portland, for material furnished to the defendant J. S. Marks, who, by virtue of a contract with one L. D. Brown, now deceased, had charge of the construction of a brick building for the latter on said premises, then owned by him. The defendants Theodore Jensen, James Lyons, and the East Portland Mill & Fixture Company, filed separate answers, in the nature of cross bills, seeking to foreclose their respective liens upon said premises for material furnished to be used in the construction of said building, and the defendant E. P. Brown, executrix of the last will and testament of L. D. Brown, deceased, and the present owner of said premises, filed an answer to the complaint
On Motion to Advance Case on Calendar.
[53 Pac. 1072. [
Submitted without argument.
delivered the opinion.
Opinion on the Merits
Decided 8 January, 1900.
On the Merits.
[59 Pac. 549.]
delivered the opinion.
This suit was instituted for the purpose of foreclosing a mechanic’s lien. As parties defendant, James Lyons, Theodore Jensen, and the East Portland Mill & Fixture Company also set up, in their respective answers, mechanics’ liens, and prayed their foreclosure. The decree of the court below directed the foreclosure of the liens of plaintiff and the East Portland Mill & Fixture Company, but dismissed the cross complaints of Lyons and Jensen. The last named parties, and the defendant E. B. Brown and E. B. Brown, executrix of the will of L. D. Brown, deceased, who is the owner of the building and premises upon which the liens were preferred, prosecute appeals. At the hearing in this court the appellants only appeared and contested the proceedings as between themselves, so that we shall determine the matter as if the controversy was between them exclusively.
On November 12, 1892, the defendant J. S. Marks entered into a contract with L. D. Brown, since deceased,
Subsequently, on December 30, 1892, the contractor gave Brown another bond for the faithful fulfillment of his contract, similar to the first, but with different sureties. By the terms of this bond, all money that became thereafter due and payable to Marks under the contract was to be paid to E. B. McFarland, and he was authorized to receive all such money and disburse the same for labor and materials furnished in the erection of the building ; and it was further stipulated that the obligation was to be in addition to the bond theretofore given. In pursuance of this arrangement the payments were thereafter made to McFarland, and by him disbursed upon the order of Marks, .until August 5, 1893, when, by another arrangement between Marks and Brown, the latter retained the money after it became due, and paid it out upon the order of Marks on account of labor done and materials furnished. About September 30,1893, Marks abandoned his contract; and on the ninth of October, after giving the required notice to the sureties, Brown took possession of the building in its unfinished condition, and completed it. When Marks quit the work he had received certificates from the architect which entitled him to payments in the aggregate of $26,300, and he had been paid $26,217.50. Aside from this, Brown had expended on concrete work $813.74, and furnished brick to the amount of $522.50, for all of which he was entitled to credit as against the contractor. Brown had also caused to be deeded, as directed by Marks, five of the seventeen lots. On August 29 Marks made a demand upon Brown for a deed to sixteen of the lots, which was declined. The refusal was
“I, John S. Marks, hereby certify that I am unable to complete or carry on my contract for the erection of L. D. Brown’s five-story brick building; and I do consent to his finishing it himself in accordance with the contract, plans and specifications. Up to the time I ceased work, the work was done in accordance with the plans and specifications, and I have no claims for extras against the building, or any claims against L. D. Brown. And that I have been paid according to said contract up to the time I quit work, save and except the lots in Peninsular Addition, which are in litigation between Inman, Poulsen & Company and L. D. Brown and Peninsular Peal Estate Company, which is to be settled in the courts.
J. S. Marks.”
Thereupon he turned over to Brown his subcontracts, bills paid, and receipts for labor and materials.
Under the facts of which the foregoing is an outline, the defendant Mrs. Brown insists that Lyons and Jensen are estopped from claiming a lien upon the building by reason of their surety relationship with Marks ; while on the other hand it is contended that Brown has been guilty of such a breach of performance of the contract on his part as to discharge the sureties, and, the relationship having ceased to exist, they were entitled to their liens for labor performed and materials furnished in the construction of the building. It is claimed that they are discharged as sureties because (1) Brown paid a portion of the first installment before it became due ; (2) he accepted a new bond, with other sureties ; (3) he failed and refused to deed the lots after the fifth payment, when requested; (4) payments were not adjusted to conform to the architect’s certificates of the amount due at the time Marks
6. That the acceptance of the second bond discharged the sureties upon the first is not strenuously urged. The terms of the obligation set the question at rest. It was given as additional security, and so understood and accepted by the parties to the contract. There is some conflict in the testimony touching the matter, but we are convinced from a careful review of the same that the true understanding and agreement was as above stated.
Affirmed .