244 A.D. 815 | N.Y. App. Div. | 1935
The judgment allows liens of certain persons as to the public improvement contract of the defendant village, and directs payment thereof from a fund representing sums earned by the original contractor. Other claims for liens were rejected. There is no dispute in the facts. The contractor defaulted with the work only partially completed and the village let the contract for completion to another. The cost of completion was in excess of the original contract price. After the work had been completed the village sued the original contractors and the .surety and recovered the damages it had suffered. (Village of Freeport v. National Surety Co., 264 N. T. 553.) There were in the hands of the village certain sums which had been certified to be due to the original contractor and which had not been paid. This money constitutes the fund from which the liens were payable. A portion of this fund consists of a percentage withheld by the village under the terms of the contract. The only question on this appeal is whether this latter sum belongs to the village or is applicable to the payment of liens. Very likely, under the terms of the contract, if the village had suffered a