84 P. 200 | Cal. | 1906
Lead Opinion
[EDITORS' NOTE: THIS PAGE CONTAINS HEADNOTES. HEADNOTES ARE NOT AN OFFICIAL PRODUCT OF THE COURT, THEREFORE THEY ARE NOT DISPLAYED.] *731 The opinion heretofore rendered in Department is modified by striking therefrom all of paragraph 6 down to and including the words "fees were excessive." So modified, the opinion and judgment in Department are approved and adopted as the opinion and judgment of the court in Bank.
The following is the opinion rendered in Department Two November 25, 1905, omitting the paragraph stricken out: —
Addendum
This is a consolidated action to enforce on the part of certain materialmen and laborers their liens against the property of appellant Charles Franzoi, upon a building contract entered into between him and the contractor, Christensen. The owner appeals from the judgment against him and from the order denying his motion for a new trial. The United States Fidelity and Guaranty Company likewise appeals from the judgment given against it upon *732 the contractor's bond. The court found that the contract in all respects was valid and in compliance with the law concerning mechanics' liens, and that it was duly recorded as required by law. The contract price was payable in five installments. The fourth installment, payable on the completion of the building, was two thousand dollars, and twenty-five per cent payable thirty-five days after completion, was $2,750. Franzoi, the owner, did not join issue with the lien claimants as to the amounts which they respectively alleged to be due them, nor as to the validity of their respective liens. He joined issue only upon the allegations as to the sum due from him to the contractor, which, in the cases of some of the lien claimants, was alleged to be in excess of six thousand dollars. Upon trial, the court aggregated the completion and final payments, amounting to $4,750, and added to this the amount admitted to be due for extra work, ninety-six dollars, making a total of $4,846. This sum, reduced by certain payments credited to Franzoi, amounted to $4,030.70, which last sum he found to be due from the owner to the contractor and subject to the liens of the claimants. He refused to reduce this sum by certain other payments and disbursements found to have been made by Franzoi, and his refusal so to do as to these separate items is the basis of the principal complaint upon this appeal. For convenience we will refer to the two-thousand-dollar payment due upon completion as the "completion payment," and the twenty-five per cent payment retained for thirty-five days as the "final payment."
1. The court refused to allow credit to the owner for the sum of $905.21 paid for glass, hardware, etc. This amount was admittedly paid under the following circumstances: Before the completion of the building, Christensen represented to the owner that he could obtain no credit from materialmen, and, consequently, could not complete the building. He requested the owner to guarantee his accounts with these materialmen for the material necessary for completion, and to deduct these amounts from the completion payment when it became due. This Franzoi did, his obligation to pay the materialmen having been assumed before the completion payment was due, but the payments to these men having been made after the completion payment was due; the court upon this finding that "All of said payments, though actually made *733
by the said Franzoi after the completion payment was due, were, and each and all of them was, assumed by the said Franzoi, and the said Franzoi actually obligated himself to pay the same . . . at a time when no payment whatever was due from him, the said Franzoi to the said Christensen." From this the court concluded that the obligation to pay, thus assumed, was the equivalent of the prohibited payment of section 1184 of the Code of Civil Procedure, where it is declared that "No payment made prior to the time when the same is due . . . shall be valid for the purpose of defeating, diminishing or discharging any lien in favor of any person except the contractor; but as to such liens, such payments shall be deemed as if not made." No liens had been filed against the property at the time these payments were made. No notice to withhold had been served upon the owner, with the exception of one, amounting to $509.08. Conceding that under this notice it became the duty of the owner to withhold the sum of $509.08, with attorneys' fees and costs, it was not his duty to withhold any other part of the two thousand dollars which became due to the contractor upon completion, and it is not disputed that he would have been justified in paying this difference of about fifteen hundred dollars over to the contractor. The contention of respondent, however, is — and this contention was adopted by the trial court — that because Franzoi, before the completion payment became due, had "obligated himself" to pay these materialmen, this obligation in some way, by operation of law, became a prepayment out of the fund in advance of the date of its falling due. It is true that equity in many instances, under the maxim that it will regard as done that which ought to have been done, will treat a promised performance of an act as an actual performance as of the time when it should have been performed. But it does this always in aid of natural justice, and never to further the harsh rule of law exacting penalties and forfeitures, which equity abhors. In West Coast Lumber Co. v.Knapp,
2. The court found that there were certain materials, trifling in their individual character, but aggregating in value $194.79, which the contractor failed to furnish and which Franzoi himself was compelled to supply, by reason of the failure of Christensen to place these materials in the building. But it refused to allow appellant deduction from the full contract price of this amount. The right of the owner under this contract to such a deduction is sufficiently shown by the pleadings and findings. The court's refusal is justified by respondent upon the language of section 1183 of the Code of Civil Procedure to the following effect: "In case of a contract for the work between the reputed owner and his contractor, the lien shall extend to the entire contract price, and such contract shall operate as a lien in favor of all persons except the contractor to the extent of the whole contract price," together with the language of section 1184 of the Code of Civil Procedure to the following effect: "As to all liens, except that of the contractor, the whole contract price . . shall not be diminished by any prior or subsequent indebtedness, offset or counterclaim in favor of the reputed owner and against the contractor." The contract also contained a provision that for delay in the completion of the work the owner should be entitled to damage from the contractor in an amount not to exceed ten dollars per day. The court found that the owner had actually sustained damages in the sum of five hundred and fifty dollars, but refused also to deduct this amount from the contract price. Although these two items are dissimilar in character, they are in one respect essentially the same. They are both deductions claimed by the owner to be due him under the very terms of the contract, and the disallowance of both was based upon the same provisions of the law. They may, therefore, be discussed together. By appellant it is contended upon the authority ofKellogg v. Howes,
If the owner, for example, is obliged to furnish material and labor to complete a contract abandoned by the contractor, or if material of cheaper value is substituted in the building, or if upon default of the contractor to complete, the owner enters into the possession of the uncompleted building, no one could question the justice of the owner's claim for an allowance for any of these matters — if an allowance for them was contemplated by the provisions of the contract — for the contract price is established and agreed to in express contemplation *737
of the fact that the particular material shall be used, and that the building shall be turned over to the owner completed. If the particular materials are not used, if the building is turned over uncompleted, so that the owner has to accept it unfinished, or complete it at his own cost, there has been a failure by so much to put the amount of the contract price into the structure, and it would be manifestly unjust that the owner should be expected to pay for that which, without any fault of his own, he has not received. The second item of damages for failure to complete in time, differs somewhat from the first, where the loss was occasioned by the necessity of the owner to make good the deficiencies of the contractor in the furnishing of omitted material. It is a perfectly legal contract which makes time of completion of its essence, and provides that the contractor, for a failure to perform in time, shall make good to the owner such loss as the latter may sustain thereby. More than this, it is a deduction or offset which, but for the Lien Law, the owner would have the unquestioned right to claim from the amount found due the contractor under the contract. Reference to the following cases will disclose that it is well settled that the owner is entitled to an allowance for damages for noncompletion; Mehrle v.Dunne,
Due owner ...................................... $ 744 79 Due lumber company ............................. 509 08 Plus attorney's fees ........................... 100 00 Paid Whittier, Fuller, and others .............. 905 21 Paid Mangrum Otter, and others ............... 807 25 ---------- Making a total of .......................... $3,066 33
But, as has been said, there was, for the payment of these demands, no more than the sum of two thousand dollars. This excess of $1,066.33 is not chargeable against the twenty-five per cent final payment until the demands of all the lien claimants have been first satisfied out of that fund, and in this case the demands are in excess of the fund. If hardship to the owner seems to result from this, it may be answered that it is always in his power to guard against loss by making the completion payment large enough to protect him, or by exacting an undertaking from the contractor for this purpose; while, upon the other hand, if encroachments were allowed upon this fund, the practical result would be, in most instances, to deprive materialmen and laborers of the lien guaranteed them by the constitution. For this excess payment then, of $1,066.33, the owner's right of recovery is against the contractor alone.
3. We think the notice to withhold, served on behalf of the Humboldt Lumber Mill Company, though inartificially drawn, was sufficient under the requirements of section 1184 of the Code of Civil Procedure. (Schallert-Ganahl Lumber Co. v. Neal,
4. The firm of Sanborn Vail had sold picture-molding to Christensen, used in the building, to the amount of $145.73. They filed no lien, and the court found and decreed, and its decree was carried into the judgment, that Sanborn Vail were entitled to a judgment against the defendant, Christensen, for this amount, with interest, but that they were not entitled to a lien upon the property of Franzoi. So far, there is no objection to the finding. But the finding proceeds: "The said Sanborn Vail Company are entitled to have said judgment satisfied out of any residue that may appear in the hands of the said defendant, Franzoi, after the claims of all the lien claimants herein adjudicated have been fully satisfied." If "residue" here means surplus moneys due from the owner to the contractor after payment of all liens, this also is unobjectionable. If it means a residue belonging to Franzoi, as appears from the further finding that Sanborn Vail are entitled to have their judgment satisfied "from the product of the sale of the property after the claims of all the lien claimants have been fully satisfied," then, manifestly, it is error in awarding a judgment payable out of the funds of the owner in favor of one who has no lien upon the owner's property.
5. The appeal of the United States Fidelity and Guaranty Company is sustained, with directions to the trial court to enter judgment in its favor upon the ground that the purported undertaking given by it is void. (Shaughnessy v. American SuretyCo.,
A new trial in this case is unnecessary, and it is therefore ordered that the consolidated judgment of the court here appealed from be, as to the appellant the United States Fidelity and Guaranty Company, reversed, with instructions to enter a judgment upon the findings in its favor, and as to the appellant Franzoi, that, upon the findings, the judgment be modified to conform to the views of the court above expressed. Appellants will recover their costs upon appeal. *741
Lorigan, J., and McFarland, J., concurred.