Hampton v. ChristensenHampton v. Christensen
The case is one which, under the provisions of the constitution as amended in 1904, falls within the appellate jurisdiction of this court. While this court may, on its own motion, order any such cause pending here to be transferred to a district court of appeal, such orders are made solely for the purpose of facilitating the business of this court, with a view to so utilize all of the appellate courts as to speedily enable those courts, working with this court, to clear the calendar of this court of its accumulated business, and considerations of the convenience of the parties to or the necessities of the speedy decision in any particular case play no part in the matter of such assignments. Such reasons as are advanced for the transfer in this case are material only upon the question as to whether the appeal should be advanced for hearing in whatever court it may be pending, and constitute no ground for an order of transfer.
The motion for an order of transfer is denied.
MECHANICS’ LIENS—GUARANTY BY OWNER TO MATERIALMEN—DEDUCTION FROM COMPLETION PAYMENT—GUARANTY NOT A PROHIBITED PAYMENT.—Where the contractor was unable to obtain credit from
ID.—DOCTRINE OF EQUITY—PENALTIES AND FORFEITURES—CONSTRUCTION OF PENAL STATUTE.—The doctrine of equity that a promised performance of an act will be deemed an actual performance is applied only in aid of justice, and never in aid of the harsh rule of law exacting penalties and forfeitures, which equity abhors; and so far as the statute has the effect of compelling the owner of the building to pay the debt twice, it is highly penal, and should be strictly construed in his favor.
ID.—OFFSETS AND COUNTER-CLAIMS—CONSTRUCTION OF CODE.—The provisions of
ID.—DEDUCTIONS ARISING UNDER CONTRACT — MATERIALS SUPPLIED BY OWNER—STIPULATED DAMAGES FOR DELAY.—The owner should be allowed to deduct from the completion payment materials necessarily supplied by the owner, by reason of the failure of the contractor to place them in the building, and also stipulated damages arising under the terms of the contract for delay of the contractor in the completion of the work.
ID.—EXCESS NOT APPLICABLE TO FINAL PAYMENT—RECOVERY AGAINST CONTRACTOR.—Any excess due to the owner under the contract, above the amount of the completion payment, cannot be deducted from the final payment of twenty-five per cent to the injury of lien claimants; but the owner‘s right of recovery for such excess is against the contractor alone.
ID.—NOTICE TO WITHHOLD COMPLETION PAYMENT—GARNISHMENT.—Under a notice by a lien claimant to the owner, which, though inartificially drawn, was sufficient, under the requirement of
ID.—ERRONEOUS JUDGMENT FOR CLAIMANT NOT A LIEN-HOLDER.—A judgment for a claimant who had filed no lien, against the contractor, and also providing that such claimant is entitled to have the claim satisfied out of any residue that may appear in the hands of the owner after all lien claimants have been satisfied, and from the product of the sale of the property after all lien claimants have been fully satisfied, is erroneous in so far as it directs payment out of the funds of the owner.
ID.—REVERSAL OF JUDGMENT AGAINST SURETY OF CONTRACTOR — VOID BOND.—Where the purported undertaking given by a surety company for the contractor is void a judgment against the surety will be reversed, with direction to the trial court to enter judgment in its favor.
APPEAL from a judgment of the Superior Court of the City and County of San Francisco and from an order denying a new trial. Frank J. Murasky, Judge.
The facts are stated in the opinion of the court.
Wal J. Tuska, Rigby & Rigby, P. F. Dunne, Walter H. Linforth, and Jackson Hatch, for Appellants.
S. Rosenheim, Barna McKinne, and Jordan & Brann, for Respondents.
THE COURT.—The opinion heretofore rendered in Department is modified by striking therefrom all of paragraph 6 down to and including the words “fees were excessive.” So modified, the opinion and judgment in Department are approved and adopted as the opinion and judgment of the court in Bank.
The following is the opinion rendered in Department Two November 25, 1905, omitting the paragraph stricken out:—
HENSHAW, J.—This is a consolidated action to enforce on the part of certain materialmen and laborers their liens against the property of appellant Charles Franzoi, upon a building contract entered into between him and the contractor, Christensen. The owner appeals from the judgment against him and from the order denying his motion for a new trial. The United States Fidelity and Guaranty Company likewise appeals from the judgment given against it upon
1. The court refused to allow credit to the owner for the sum of $905.21 paid for glass, hardware, etc. This amount was admittedly paid under the following circumstances: Before the completion of the building, Christensen represented to the owner that he could obtain no credit from materialmen, and, consequently, could not complete the building. He requested the owner to guarantee his accounts with these materialmen for the material necessary for completion, and to deduct these amounts from the completion payment when it became due. This Franzoi did, his obligation to pay the materialmen having been assumed before the completion payment was due, but the payments to these men having been made after the completion payment was due; the court upon this finding that “All of said payments, though actually made
If the owner, for example, is obliged to furnish material and labor to complete a contract abandoned by the contractor, or if material of cheaper value is substituted in the building, or if upon default of the contractor to complete, the owner enters into the possession of the uncompleted building, no one could question the justice of the owner‘s claim for an allowance for any of these matters—if an allowance for them was contemplated by the provisions of the contract—for the contract price is established and agreed to in express contempla-
| Due owner | $ 744 79 |
| Due lumber company | 509 08 |
| Plus attorney‘s fees | 100 00 |
| Paid Whittier, Fuller, and others | 905 21 |
| Paid Mangrum & Otter, and others | 807 25 |
| Making a total of | $3,066 33 |
But, as has been said, there was, for the payment of these demands, no more than the sum of two thousand dollars. This excess of $1,066.33 is not chargeable against the twenty-five per cent final payment until the demands of all the lien claimants have been first satisfied out of that fund, and in this case the demands are in excess of the fund. If hardship to the owner seems to result from this, it may be answered that it is always in his power to guard against loss by making the completion payment large enough to protect him, or by exacting an undertaking from the contractor for this purpose; while, upon the other hand, if encroachments were allowed upon this fund, the practical result would be, in most instances, to deprive materialmen and laborers of the lien guaranteed them by the constitution. For this excess payment then, of $1,066.33, the owner‘s right of recovery is against the contractor alone.
3. We think the notice to withhold, served on behalf of the Humboldt Lumber Mill Company, though inartificially drawn, was sufficient under the requirements of
4. The firm of Sanborn & Vail had sold picture-molding to Christensen, used in the building, to the amount of $145.73. They filed no lien, and the court found and decreed, and its decree was carried into the judgment, that Sanborn & Vail were entitled to a judgment against the defendant, Christensen, for this amount, with interest, but that they were not entitled to a lien upon the property of Franzoi. So far, there is no objection to the finding. But the finding proceeds: “The said Sanborn & Vail Company are entitled to have said judgment satisfied out of any residue that may appear in the hands of the said defendant, Franzoi, after the claims of all the lien claimants herein adjudicated have been fully satisfied.” If “residue” here means surplus moneys due from the owner to the contractor after payment of all liens, this also is unobjectionable. If it means a residue belonging to Franzoi, as appears from the further finding that Sanborn & Vail are entitled to have their judgment satisfied “from the product of the sale of the property after the claims of all the lien claimants have been fully satisfied,” then, manifestly, it is error in awarding a judgment payable out of the funds of the owner in favor of one who has no lien upon the owner‘s property.
5. The appeal of the United States Fidelity and Guaranty Company is sustained, with directions to the trial court to enter judgment in its favor upon the ground that the purported undertaking given by it is void. (Shaughnessy v. American Surety Co., 138 Cal. 543, [69 Pac. 250, 71 Pac. 701].)
A new trial in this case is unnecessary, and it is therefore ordered that the consolidated judgment of the court here appealed from be, as to the appellant the United States Fidelity and Guaranty Company, reversed, with instructions to enter a judgment upon the findings in its favor, and as to the appellant Franzoi, that, upon the findings, the judgment be modified to conform to the views of the court above expressed. Appellants will recover their costs upon appeal.