HAMMERHEAD CONTRACTING & DEVELOPMENT, LLC, and Brandon Holmes, Appellants, v. Dale LADD, Appellee.
No. CV-15-894
Supreme Court of Arkansas.
Opinion Delivered April 14, 2016
Rehearing Denied May 5, 2016
2016 Ark. 162
Here, the summonses and complaints were mailed to appellees by registered mail at their last known address in Costa Rica, return receipt requested. Appellants assert that when the summonses and complaints were “refused,” service was then and there “completed” as provided for by Arkansas Code Annotated section 16-58-132 and the Arkansas Rules of Civil Procedure. Arkansas Rule of Civil Procedure 4(d)(8)(A)(i) (2008) provides in pertinent part: “Service of a summons and complaint upon a defendant ... may be made ... by any form of mail addressed to the person to be served with a return receipt requested and delivery restricted to the addressee or the agent of the addressee.” When the envelopes containing the complaints and summonses were returned to appellants’ attorney, each envelope was marked with a Costa Rican postal service stamp that contained several options for delivery; each envelope was marked “refused.” Rule 4 provides that upon notice of refusal, the plaintiff must promptly send the papers by first class mail, which appellants’ attorney represented to have done. The circuit court relied on affidavits from appellees Douglas and Morrison that they did not refuse mailed service or authorize anyone else to refuse it for them; however, those same affidavits state that they did not personally check their post-office box in Costa Rica and instead sent their farm manager to do so. Thus, while the farm manager may not have been “authorized in accordance with U.S. Postal Service Regulations” under Rule 4(d)(8)(A)(i), we need not decide whether this was adequate to prove service via refusal. We hold that appellants made a timely, completed attempt to serve appellees and should be afforded the benefit of the savings statute. The dismissal “with prejudice” is reversed, and the case is remanded for entry of an order consistent with this opinion.
Affirmed in part; reversed and remanded in part; court of appeals’ opinion vacated.
Murphy, Thompson, Arnold, Skinner & Castleberry, by: Kenneth P. “Casey” Castleberry, El Dorado, for appellee.
JOSEPHINE LINKER HART, Justice
Hammerhead Contracting & Development, LLC, and Brandon Holmes (Hammerhead), appeal from the grant of summary judgment in favor of Dale Ladd. Ladd had sued Holmes to remove a “Laborer’s, Mechanic’s, or Materialman’s Lien” that Holmes had filed on behalf of his wholly owned limited-liability company (Hammerhead). Ladd had withheld payment of $101,676.82 that Hammerhead claimed it was owed. On appeal, Hammerhead argues that: (1) the circuit court erred in finding that the direct-sales exception to the residential-preconstruction notice requirement, codified at
In January 2014, Ladd hired Hammerhead to build a house in Batesville, Arkansas. Under the agreement, Ladd agreed to pay $355,550. A further provision in the job estimate stated that “prices will not change unless upgrades are requested by the buyer.” It is not disputed that prior to beginning construction, Hammerhead did not provide Ladd with the statutory notice provided for in
A dispute arose regarding the amount owed for the construction of Ladd’s home. According to Hammerhead’s records, Ladd paid more than $370,000 through August 2014, but Ladd contends that he paid more. As noted previously, Hammerhead asserted that Ladd owed an additional $101,676.82, and on September 23, 2014, Holmes filed a “Laborer’s, Mechanic’s, or Materialman’s Lien” for that amount on behalf of the LLC.
On October 2, 2014, Ladd filed suit against Holmes to remove the lien. On January 22, 2015, Hammerhead filed an amended complaint against Ladd seeking judgment for the $101,676.82. Ladd moved to dismiss, asserting that the failure to give statutory notice required by
In his summary-judgment motion, Ladd asserted that Hammerhead had failed to give him the notice required by
(a)(1) No lien upon residential real estate containing four (4) or fewer units may be acquired by virtue of this subchapter unless the owner of the residential real estate, the owner’s authorized agent, or the owner’s registered agent has received, by personal delivery or by certified mail, a copy of the notice set out in this subsection.
....
(3) It shall be the duty of the residential contractor to give the owner, the owner’s authorized agent, or the owner’s registered agent the notice set out in this subsection on behalf of all potential lien claimants before the commencement of work.
(4) If a residential contractor fails to give the notice required under this subsection, then the residential contractor is barred from bringing an action either at law or in equity, including without limitation quantum meruit, to enforce any provision of a residential contract.
Ladd further argued that he anticipated that Hammerhead might assert that he was not required to give notice under the “direct sale” exception found in section 18-44-115(a)(8)(A):
(8)(A) If the residential contractor supplies a performance and payment bond or if the transaction is a direct sale to the property owner, the notice requirement of this subsection shall not apply, and the lien rights arising under this subchapter shall not be conditioned on the delivery and execution of the notice.
(B) A sale shall be a direct sale only if the owner orders materials or services from the lien claimant.
Even so, Ladd asserted that, given the statutory definition of “contractor” in
Hammerhead opposed Ladd’s summary-judgment motion, asserting that there was a genuine issue of material fact as to whether notice was required by
In deciding whether to grant summary judgment, the circuit court concluded that it had three issues before it: (1) whether a general contractor, who did not provide predelivery notice, as required by
Summary judgment is appropriate when there are no genuine issues of material fact, and the moving party is entitled to judgment as a matter of law. Lipsey v. Giles, 2014 Ark. 309, 439 S.W.3d 13. On appeal, we determine if summary judgment was appropriate based on whether the evidentiary items presented by the moving party in support of the motion leave no disputed questions of material fact. Id. In our review, we view the evidence in the light most favorable to the party against whom the motion was filed, resolving all doubts and inferences against the moving party. Id. We focus not only on the pleadings, but also on the affidavits and documents filed by the parties. Id. Moreover, we have held that, even when there is no material dispute as to the facts, on review, we will determine whether “reasonable minds” could draw “reasonable” inconsistent hypotheses to render summary judgment inappropriate; if so, summary judgment is not appropriate. Id.
The question of the correct application and interpretation of an Arkansas statute is a question of law, which this court decides de novo. Evans v. Hamby, 2011 Ark. 69, 378 S.W.3d 723. The purpose of the rules of statutory construction is to give effect to the intent of the legislature. State v. Colvin, 2013 Ark. 203, 427 S.W.3d 635. The first rule of statutory construction is to construe a statute just as it reads, giving the words their ordinary and usually accepted meaning. Smith v. Simes, 2013 Ark. 477, 430 S.W.3d 690. Additionally, in construing any statute, we place it beside other statutes relevant to the subject matter in question and ascribe meaning and effect to be derived from the whole. Colvin, supra. Statutes relating to the same subject must be construed together and in harmony, if possible. Id.
As noted previously, the “direct sale” exception that is found in
Reversed and remanded.
Goodson, Wood, and Wynne, JJ., dissent.
Robin F. Wynne, Justice, dissenting.
Because I believe that the majority’s decision in this case effectively abolishes an entire code section, I respectfully dissent.
The statute at issue,
The majority states that “the plain wording of the statute is clear.” However, the majority’s application of the plain wording renders the statute internally inconsistent such that the exception now swallows the rule. In interpreting statutes, we are required to reconcile different provisions to make them consistent, harmonious, and sensible in an effort to give effect to every part. See Smith v. ConAgra Foods, Inc., 2013 Ark. 502, 431 S.W.3d 200. The majority has not done this. Instead, the majority has read the direct-sale exception in isolation and nullified the remainder of the statute. Reading the statute as a whole, it is clear to me that the direct-sale exception was meant to apply to situations in which a potential lien claimant other than the residential contractor has contracted directly with the property owner to provide materials or services. In that instance, it is not necessary for the residential contractor to advise the property owner of the potential for liens by parties unknown to the property owner, because the property owner would be aware of their existence through having directly contracted with them. This interpretation of the statute gives effect to every part and helps to protect property owners from finding liens placed on their property by unknown parties, as the legislature intended in enacting the statute. Because appellants failed to give the statutorily-required notice, and because there is no evidence that the direct-sale exception should apply, I would affirm the circuit court’s finding that appellants’ failure to give the required notice is fatal to their lien.
For these reasons, I respectfully dissent.
Goodson and Wood, JJ., join.
