125 Wis. 311 | Wis. | 1905
1. When complete performance of an entire contract to do work upon another’s building is prevented by the total destruction of that building, such completion is excused, and the contractor may recover pay at the contract, price for the portion of the work done. Cook v. McCabe, 53 Wis. 250, 10 N. W. 507; Vogt v. Hecker, 118 Wis. 306, 309, 95 N. W. 90. The present case falls clearly within this rule, for plaintiff was only to do work upon a building to be supplied by the owner or its employees.
2. The efficacy of an agreement that an architect’s certificate shall be a condition precedent to a contractor’s right to-payment has often been declared. Coorsen v. Ziehl, 103 Wis. 381, 79 N. W. 562; John Pritzlaff H. Co. v. Berghoefer, 103 Wis. 359, 79 N. W. 564; Mindeman v. Douville, 112 Wis. 413, 88 N. W. 299. Such an agreement is, however, deemed and construed to embody the condition that the architect shall exercise his function as arbitrator honestly and in good faith. He usually is, as in- the instant case, the employee and agent of the owner, and, but for such a condition, can, if he will, absolutely deprive the contractor of all pay for his work, however exactly it may comply with the contract.. An agreement to submit the question of pay or no pay to the-mere whim, or worse, of one in an opposing interest is too-
The evidence as to what transpired after the fire between plaintiff, the architect, and Dr. Capíes, the defendant’s managing officer, is not in dispute. Upon presentation of plaintiff’s final bill the architect assured him that his work was all satisfactory except a mixing table, but said he could not give certificate because Dr. Capíes had withdrawn from him the contract. The architect testified that after such withdrawal of the contract he exercised no authority under it and so stated to plaintiff. At the same time he told plaintiff he must see and deal with Capíes. Thereupon plaintiff applied to Capíes for payment, was met with no suggestion that a' certificate was needed or would vary the situation, but was told the defendant would compromise by allowing eighty-five-per cent, of the total bill, and by giving plaintiff a contract: on rebuilding, and if that were not accepted they would keep' him out 'of his money as long as they could. There was no claim that the defendant did not legally' owe the whole! amount, nor that Capíes needed the certificate or any information from the architect to assure him of the work done or the amount due, of which it appears the architect had already
The item of $150 deduction for a mixing table rejected by the architect as not in accord with specifications cannot be allowed, although there is much evidence to dispute the architect’s decision. On that subject he did act within his agreed jurisdiction and his ruling is conclusive. There is no evidence to support any other deductions from the amount demanded by the complaint.
The fact that the claim for lien filed, as also the complaint, described a twelve-acre tract of land as that upon which lien was demanded, while by the evidence it appears that only one ■acre can be so subject, is urged as an obstacle to recovery. In this contention it is apparent that counsel have confused rulings made in different decisions. Thus in Security Nat. Bank v. St. Croix P. Co. 111 Wis. 211, 94 N. W. 74, and Dusick v. Green, 118 Wis. 240, 95 N. W. 144, the right to
The question whether a lien can be sustained against the land after the building on which the work was done has been-destroyed is forced on our notice by Goodman v. Baerlocher, 88 Wis. 287, 60 N. W. 415, although the point is not raised.. -That case has been understood by some as declaring o.ur adoption of what may be called the Pennsylvania theory — that &■_
By the Gowrt. — Judgment reversed, and cause remanded with directions to take further proceedings and render judgment in plaintiff’s favor in accordance with the foregoing ■opinion.