Tom Hall claimed that Lone Star Gas Company excessively used its easement and violated the Texas Deceptive Trade Practices Act (“DTPA”). The trial court rendered summary judgment for Lone Star on several stated grounds. Mr. Hall appeals the trial court’s order in various points of error alleging there existed genuine material fact issues. Mr. Hall also claims the trial court erred in granting summary judgment because he had improper notice of the hearing. While we will reject one ground supporting summary judgment in favor of Lone Star, we nevertheless will affirm the summary judgment on other grounds.
FACTUAL AND PROCEDURAL BACKGROUND
In the late 1920’s Lone Star built a dry gas line (Line R) to provide residential and commercial gas service along State Highway 67. In 1928, Mr. Hall’s grandfather, the predecessor in title to Mr. Hall, executed an easement which grants Lone Star “the right of way and easement to construct, maintain, and operate pipe lines.” Lone Star also has the right to “ingress and egress from the premises, for the purposes of constructing, inspecting, repairing, maintaining, and replacing the property of [grantee].” From September to mid-November of 1992 Lone Star worked on Mr. Hall’s land in order to replace Line R.
On March 6, 1995, Mr. Hall filed suit against Lone Star alleging damages to his real property and fixtures and basing his claims on breach of contract, excessive use of the 1928 easement, and violations of the DTPA. Lone Star filed a motion for partial summary judgment which the trial court granted on April 24, 1996. The motion included a statute of limitations defense and a request for declaratory judgment that the easement was a multiple-line easement. Shortly thereafter, the court rescinded its partial summary judgment. Lone Star, again, sought partial summary judgment and a second hearing was held on November 25, 1996. On December 3, 1996, the trial court granted Lone Star’s motion by rescinding its Order to Rescind its Order, thereby reinstating the April 24 partial summary judgment in favor of Lone Star. Because the remaining issues had been severed from the ease, the trial court’s order constituted a final judgment and Mr. Hall’s appeal comes properly under this Court’s jurisdiction.
STANDARD OF REVIEW
The standards for reviewing a motion for summary judgment are well established: (1) the movant for summary judgment has the burden of showing that no genuine issue of material fact exists and that it is entitled to judgment as a matter of law; (2) in deciding whether there is a disputed material fact issue precluding summary judgment, evidence favorable to the nonmovant will be
*176
taken as true; and (3) every reasonable inference must be indulged in favor of the nonmovant and any doubts resolved in its favor.
See Nixon v. Mr. Property Management Co.,
DISCUSSION
Multiple-line Easement?
Lone Star sought to defeat Mr. Hall’s damages claim for excessive use of the easement by requesting a declaratory judgment that the easement is an expansible multiple-line easement of perpetual duration which allows Lone Star to lay additional lines. As movant, Lone Star had the burden to establish conclusively it was entitled to lay such lines. A matter is “conclusively established” for summary judgment purposes if ordinary minds cannot differ regarding the conclusion to be drawn from the evidence.
See Zep Mfg. Co. v. Harthcock,
Whether a contract is ambiguous is for the court to determine.
See Roman Catholic Diocese v. First Colony,
The
Boland
court determined the gas company was permitted to lay an additional line years after the original had been laid because the easement expressly granted a right of way for an initial pipeline and “any additional pipeline described by Grantee, for the transportation of gas ... at route or routes selected by Grantee.”
Boland,
Similar to
Russell,
the easement here used the term “pipe lines” but contained no express provision granting the right to lay additional lines in the future. To the contrary, the compensation clause for future lines was specifically deleted from the form contract. In arriving at the true meaning and intention of the parties, a court may consider the deletions made by the parties.
See Houston Pipe Line Co. v. Dwyer,
Notice of the Hearing
In point of error one, Mr. Hall claims the trial court erred because by failing to act on Lone Star’s second motion for summary judgment and, instead, reinstating its earlier grant of summary judgment, Mr. Hall had improper notice for the November 25 summary judgment hearing. We find Mr. Hall failed to preserve this point of error for appeal. Under the Texas Rules addressing summary judgment, “[ijssues not expressly presented to the trial court by written motion, answer or other response shall not be considered on appeal as grounds for reversal.” Tex.R. Civ. P. 166a(c). Generally, a complaint regarding notice is required to be in writing and before the court at the summary judgment hearing.
See City of Houston v. Clear Creek Basin Auth.,
Because the record is devoid of any post-judgment motion by Mr. Hall preserving his complaint of improper notice, we find that he waived any such right to appeal. However, if we were to reach this issue, we would hold that the trial court was within its rights to reinstate its earlier order because the subsequent recission constituted an interlocutory judgment.
See Evans v. Hoag,
Excessive Use of the Easement
Mr. Hall brings no point of error attacking the trial court’s ruling that Lone Star’s activities constituted a replacement of its worn-out line, a right expressly granted by the original easement. When the trial court’s summary judgment order does not specify the grounds on which the summary judgment is granted, an appellate court will affirm the judgment if any grounds stated in the motion are meritorious.
See Carr v. Brasher,
The April 4, 1996 order stated, among other grounds, that “Lone Star’s construction of a pipe line across Hall’s property in September of 1992 was the installation of a
replacement
line for its original Line R, not an
*178
additional line” (emphasis added). As neither party disputes that the "easement grants Lone Star the right to replace pipe lines, we need only determine whether Lone Star was exercising its right to replace or laying an additional line. This Court has already determined that activities similar to Lone Star’s constitute a proper and valid exercise of replacement rights under a like easement.
Harris v. Phillips Pipe Line Co.,
In Harris the easement granted Phillips the right of way for the “laying, maintaining, use, operation, repair, replacement and removal of a ten inch pipe line.” Id. at 362. When Phillips decided to replace the original line with a line buried to a greater depth for safety reasons, it laid the new line parallel to and fifteen feet away from the original line, the closest distance at which construction was not hazardous. Phillips continued to use the original line while constructing the new line in order to avoid interrupting service to its users, and upon completion switched service to the new line and discontinued use of the original. This manner of replacing pipe line was considered a common practice in the industry. See id. at 363. This Court concluded that an easement necessarily carries the right to do those things which are reasonably necessary for the full enjoyment of the easement. Id. at 364. Because Phillips clearly had the right to replace its pipe line, incidentally it had the right to take the course of action it did; “to require Phillips to cease use of the pipe line in order to replace it with a new line would deny [it] a right expressly given by the grant, the right to use, maintain and operate the pipe line.” Id. at 364-65.
Due to leakage problems caused by an increased demand, Lone Star decided to replace a section of ten-inch Line R pipe line with ten-inch pipe line that could withstand greater pressure. Lone Star laid the new line parallel to and some feet away from the original; it continued using the original line to supply gas to its customers and upon completion switched the service to the new line and discontinued using the original. At no time did Lone Star use the two pipes simultaneously. The easement gives Lone Star the right to “construct, maintain, and operate,” and further allows ingress and egress for the purposes of “constructing, inspecting, repairing, maintaining, and replacing the property of Grantee.” Requiring Lone Star to cease operating and remove the original line before replacing it would deny Lone Star the maintenance and operation rights granted by the easement. By industry practice it would unduly burden Lone Star’s ability to continue servicing its customers.
The present circumstances are distinguishable from those in
Phillips Pipe Line Co. v. Clear Creek Properties, Inc.,
Lone Star’s right to reasonably use the land pursuant to its enjoyment and use of the easement is not a right without limits. The supreme court has held that while the terms “operate” and “maintain” include the right to remove and replace original pipe, replacement pipe is only within the extent of the easement when such replacement is necessary and the new pipe is not substantially larger than the original.
Dwyer,
The DTPA claim
In points of error four and five Mr. Hall asserts the trial court erred in holding that he was not a “consumer” under the DTPA and that the two-year statute of limitations barred his claims. Consumer status is a question of law based upon all the evidence.
See Coker v. Burghardt,
Mr. Hall submits he meets the first prong because he or his predecessor acquired the original and subsequent pipeline under the land for consideration and presently he receives gas through the pipeline at cost. He contends this transaction forms the basis of the complaint. While we do not dispute that Mr. Hall consumes gas through the pipeline in question, his claim for damages to his land arises out of Lone Star’s use of the easement. His complaint did not in any perceivable manner rest on his receipt of gas which was
incidentally
provided by Lone Star. A plaintiff establishes its standing as a consumer by a relationship with the transaction, not by a relationship with the defendant.
See Tuscarora Corp. v. HJS Indus., Inc.,
CONCLUSION
Although we reject the trial court’s holding that the easement granted Lone Star the right to lay multiple lines in the future, we affirm summary judgment in favor of Lone Star as to excessive use of the easement on the ground that this was a replacement line and that the original easement granted Lone Star the right to replace its line. We further affirm summary judgment in favor of Lone Star on Mr. Hall’s DTPA claims, holding that the trial court properly found, as a matter of law, that Mr. Hall was not a consumer.
Notes
. We note that on November 15 Mr. Hall filed a timely response to Lone Star’s motion before the hearing on November 25. The trial court considered the attached affidavits and apparently concluded they failed to defeat Lone Star’s motion for summary judgment.
. While the record reveals no confirmation the replacement line is the same size, Mr. Hall stated in Plaintiff’s Answers to Defendant’s Second Set of Interrogatories (September 8, 1995), that it was his "understanding now that the pipeline replaced was a ten inch pipeline replaced by a ten inch pipeline.”
. This conclusion does not address whether the replacement caused compensable damage to Mr. Hall's fixtures. The claim for damages to fences was severed by the trial court on December 2, 1996.
