John Hall, lessor, and JFW, Inc., lessee, entered into an oil and gas lease on August 3, 1990. The lease provided in pertinent part:
“If no well be commenced on said land on or before August 3rd, 1991, this lease shall terminate as to both parties ....
“If the lessee shall commence to drill a well within the term of this lease . . . the lessee shall have the right to drill such well to completion with reasonable diligence and dispatch.”
The lease was altered after it was recorded. The altered lease stated it was entered into on August 13, 1990, and stated the well must be commenced on or before August 13, 1991.
The lease also contained a delay rental clause, but JFW did not timely tender payment.
JFW performed the following activities on the Hall lease:
10-22-90: Title opinion
3-30-91: Measured and staked location for well
4- 2-91: Surveyed elevation of site
6-25-91: Received KCC approval of intent to drill
Talked with geologist
7-18-91: Received bid for drilling mud
7-20-91: Reached verbal agreement with Duke Drilling to drill well; tentative date set for late July or early August
7-24-91: Restaked location for well
More than three days before 8-6-91:
Told Duke Drilling to get rig on lease.
8-10-91: Signed written contract with Duke Drilling Agent of Duke Drilling dug drilling pits and leveled location
8-11-91: Drilled water supply well
8-12-91: Prepared rotary hold and run-around
8-12-91: Duke Drilling picked up surface casing
8-14-91: Duke Drilling moved drilling rig onto lease and spudded well
8-14-91 to 8-20-91:
Well dug to 3,000 feet; production casing installed and cemented
8-20-91 to 9-3-91:
Cement allowed to cure
9- 3-91: Ready to move completion rig onto lease.
Prior to completion of the well, Hall sought a determination that the lease had terminated and requested a temporary restraining order preventing JFW from entering the lease. On September 3, 1991, a temporary restraining order was issued. The trial court later denied a temporary injunction and determined the well had been commenced by August 3, 1991. This court reversed the judgment after finding the trial court prematurely had decided the merits of the case.
Upon remand, the parties completed discovery and filed motions for summary judgment. The trial court found JFW had a “firm commitment” from Duke Drilling prior to the commencement deadline and therefore determined JFW had commenced the well prior to expiration of the lease, and entered summary judgment for JFW.
Summary judgment is proper when no genuine issue of material fact exists and the moving party is entitled to judgment as a matter of law. When considering a motion for summary judgment, the trial court is required to resolve all facts and inferences which may reasonably be drawn from the evidence in favor of the nonmoving party. The same standard is applied on appeal, and summary judgment must be denied where reasonable minds could differ as to the conclusions drawn from the evidence. See K.S.A. 60-256(c);
C.J.W. v. State,
This court is not bound by the trial court’s interpretation of the written contract.
Simon v. National Farmers Organization, Inc.,
“[T]he intent of the parties is the primary question; meaning should be ascertained by examining the document from all four comers and by considering all of the pertinent provisions, rather than by critical analysis of a single or isolated provision; reasonable rather than unreasonable interpretations are favored; a practical and equitable construction must be given to ambiguous terms; and any ambiguities in a lease should be construed in favor of the lessor and against the lessee, since it is the lessee who usually provides the lease form or dictates the terms thereof.” Jackson v. Farmer,225 Kan. 732 , 739,594 P.2d 177 (1979).
Unambiguous contracts are enforced according to their plain, general, and common meaning in order to ensure the intentions of the parties are enforced. See
Wood River Pipeline Co. v. Willbros Energy Services Co.,
When analyzing whether a lease has terminated because the lessee has not timely commenced a well, our Supreme Court has looked to the language of the controlling instrument, reading it as a whole, to determine the nature and extent of the lessee’s obligation. See
Shoup v. First Nat’l Bank,
Our courts have considered clauses which require the lessee to commence operations for drilling in a number of instances. Most recently in
A & M
Oil,
Inc. v. Miller,
In
Herl v.
Legleiter,
In
Phillips v. Berg,
Hennig v. Gas Co.,
The court did find drilling operations had been timely commenced and the operations pursued with reasonable diligence in
Baughman v. Ault,
There is authority in Kansas which hints that something less that actual drilling might satisfy a requirement of the “commencement of drilling.” See
Herl v. Legleiter,
Professor David Pierce offers the following analysis based on the limited authority implying that something less that actual drilling might be sufficient under some leases:
“In Herl v. Legleiter the Kansas Court of Appeals suggests something less than actual drilling may be sufficient to satisfy a commencement clause. However, it appears where something less than actual drilling is being relied upon, the lessee should be required to demonstrate what amounts to an irrevocable commitment to conduct operations, to completion, on the leased land. The best evidence of this, absent actual drilling on the premises, is an enforceable contract with a third party to drill a well on the leased land. However, the lessee runs a risk when something less than an appropriate rig is in place on the lease.” 1 Pierce, Kansas Oil and Gas Handbook § 9.34 (1991).
Allowing an irrevocable commitment to conduct operations to completion to satisfy a lease requiring the commencement of drilling, and not merely operations for drilling, too broadly states the law of Kansas. Here, actual drilling had not been commenced by the lease anniversary date, whether August 3 or 13. The only actions taken on the leased property prior to August 13 were the staking of the well location, an elevation survey, the signing of a written contract with Duke Drilling, an agent of Duke Drilling digging drilling pits and leveling the location, and the drilling of a water supply well.
An analysis of the plain terms of the lease reveals that the trial court erred in granting summary judgment for JFW. The lease provides that the lessee must “commence to drill a well within the term of this lease.” (Emphasis added.) Under the plain terms of the lease, actual drilling was required prior to the termination date.
“American courts have traditionally taken the view that competent adults may make contracts on their own terms, provided they are neither illegal nor contrary to public policy and, in the absence of fraud, mistake, or duress, that a party who has fairly and voluntarily entered into such a contract is bound thereby, notwithstanding it was unwise or disadvantageous to that party. [Citation omitted.]” Metropolitan Life Ins. Co. v. Strnad,255 Kan. 657 , 670-71,876 P.2d 1362 (1994).
JFW alleges no fraud, mistake, or duress and was free to contract on its own terms. JFW is now bound by those terms.
JFW extensively reviews cases from other jurisdictions which would support its position that minimal activities on the leased property are sufficient to constitute commencement. These cases, however, are not persuasive, given current Kansas law. Significantly, the
Shoup
court declined the lessee’s invitation to adopt a more liberal interpretation of the commencement clause in conformance with other jurisdictions. See
Shoup,
JFW also argues a finding that the well had not been timely commenced would be grossly inequitable and would not constir tute a reasonable interpretation of the lease. Kansas courts have refused to apply equity in cases involving commencement. See 1 Pierce, Kansas Oil & Gas Handbook § 9.32 (1991);
Shoup,
The case is reversed and remanded for entry of judgment in favor of Hall.
