Hall County School District v. C. Robert Beals & Associates, Inc.Hall County School District v. C. Robert Beals & Associates, Inc.
Currahee Construction Company (“Currahee”) is a general contractor hired by the Hall County Board of Education (“school board”) to construct a new elementary school. As the contractor, Currahee was required to provide the school board with performance and payment bonds in the contract amount of $2,590,400. During performance of the contract, the school board learned that the bonds provided by Currahee were invalid, and the contract was terminated. Several of Currahee’s unpaid subcontractors, who could not make payment claims under the invalid bonds (the “subcontractors”), subsequently sued the school board under
“To prevail at summary judgment under
Although many of the
relevant
facts in this case appear undis
puted, we note that the school board has failed to cite, the record to support most of its factual assertions. Furthermore, the numerous attempts by both parties to establish facts by reference to attachments to their briefs are inconsequential. Attachments to the briefs do not constitute evidence and are insufficient to establish facts.
Crotty v. Crotty,
In this regard, the record shows that the school board advertised a public invitation to submit bids for the construction project and notified potential bidders that 100 percent performance and payment bonds would be required. See
On September 28, 1993, when the project was near completion, the school board was notified that the bonds were not issued by American Specialty and were therefore invalid. While investigating the situation, the school board’s associate superintendent contacted the Licensing Division of the Georgia Insurance Commissioner’s Office (“Insurance Commissioner”) and learned that American Specialty was no longer authorized to issue insurance. Apparently, a June 30, 1992 quarterly statement showed that the company was in unsound financial condition. On September 28, 1992, after investigating American Specialty, the Insurance Commissioner suspended the surety’s Certificate of Authority to issue insurance.
Based on the information the school board obtained about the invalid bonds, it notified Currahee that the company was in default of the contract and demanded that it provide valid bonds within seven days. Currahee failed to comply, and on October 29, 1993, the school board notified Currahee that the contract was terminated. At the time of termination, the project was 98 percent complete. A payment request form approved on September 13, 1993, shows that as of that date there remained approximately $180,247 in undisbursed funds for the project, of which $129,523 was a percentage retained by the school board for work already completed by Currahee. Several subcontractors were not paid for work they completed, however, and they asserted a claim against the school board for $291,184.21. A portion of the remaining funds was used to settle some of the claims, but when the remaining subcontractors’
Case No. A97A1940
1. The trial court properly denied the school board summary judgment because there is conflicting evidence concerning liability under the relevant bond statutes.
The applicable requirements for payment bonds for the school board’s construction project are contained in
Instead,
Importantly, however,
It is clear that the school board is a public body within the meaning of these Code sections and can therefore be held liable for its failure to comply with the statutory requirements
In this case, it is clear that the bond taken by the school board purports, on its face, to be submitted on behalf of Currahee, the general contractor by American Specialty, a surety. Contrary to the subcontractor’s arguments, the school board was not required to “make any further inquiry or investigation” into the propriety of the information presented on the face of the bond in order to defeat the subcontractors’ direct action remedy. See J & A Pipeline, supra at 649. Accordingly, the school board’s liability under these statutes, if any, must result from its failure to investigate the solvency of the surety.
As stated above, the school board admits that it did not perform such an investigation or otherwise approve the solvency of the surety. The school board contends, however, that even if it had investigated the solvency of American Specialty, such an investigation would have revealed that the surety was solvent and would not have provided any indication that the bonds were invalid. The school board relies on evidence showing that “[Information regarding matters under investigation or proposed orders of suspension or revocation is
typically
not disclosed [by the Insurance Commissioner] to the general public while the investigation or proposed order is pending.” (Emphasis supplied.) This evidence, however, construed in a light most favorable to the subcontractors, does not show that such information is
never
provided, only that it is “typically” not disclosed. Furthermore, even if the Insurance Commissioner never provided the information, this does not preclude the possibility that the school board could have obtained the same report, which showed American Specialty in unsound financial condition, from another source such as the surety. A jury could certainly infer that with this information in hand, the school board would not have approved Currahee’s bid and the subcontractors would have avoided their injurious situation. Finally, because the school board never conducted any solvency investigation and
2. We also find that the trial court properly denied the school board’s motion for summary judgment on the ground that it was entitled to sovereign immunity against the subcontractors’ claims. The school board properly concedes in its appellate brief that it can be held liable for failing to comply with the requirements of
Case No. A97A1941
3. The subcontractors are correct that their claim for liability under
4. Notwithstanding the existence of undisputed evidence showing that the school board did not take any action to approve the bonds or investigate the solvency of American Specialty, we disagree with the subcontractors that they were entitled to summary judgment based on this evidence. As stated in Division 1, there is no express statutory requirement that a school board presented with a facially valid bond, “make any further inquiry or investigation” concerning the information contained on the face of the bond. See J & A Pipeline, supra at 649. Accordingly, in light of evidence addressed in Division 1 which shows that the bonds are facially valid, the trial court did not err in denying the subcontractors’ motion on this ground.
The subcontractors’ assertion that they were entitled to summary judgment because the undisputed evidence showed that the school board failed to investigate the surety’s solvency is also without merit. “ ‘[E]ven when negligence per se has been shown, proximate cause must still be proved. (Cits.)’ [Cit.]” Holbrook, supra at 107. In Division 1 we cited evidence which, when viewed in a light most favorable to the subcontractors, created a jury issue concerning whether the school board’s failure to investigate American Specialty’s solvency caused the subcontractors’ damages. This same evidence, when viewed in a light most favorable to the school board, similarly presents a jury issue concerning whether such failure proximately caused the subcontractors’ injuries. That evidence showed that the Insurance Commissioner’s office typically does not disclose to the general public evidence concerning matters under investigation, such as American Specialty’s financial problems. And, although a June 30,1992 quarterly statement showed that American Specialty was in unsound financial condition, such evidence does not conclusively show that the school board could have obtained a copy of the report or otherwise learned that the surety was insolvent. Finally, as stated in Division 1, it is unclear whether the school board’s solvency investigation would have revealed anything concerning the validity of the bonds at issue. Accordingly, material issues of fact remain concerning whether the school board’s failure to approve American Specialty’s solvency caused the subcontractors’ damages.
5. The subcontractors correctly assert that the trial court erroneously granted the school board summary judgment on their equitable lien claim. We note initially, that although the subcontractors did not file a separate direct appeal concerning this issue,
As stated above, the record shows that as of September 13, 1993, there remained approximately $180,247 in undisbursed funds under the contract, of which $129,523 was a percentage retained by the school board for work already completed by Currahee. Although a portion of those funds was used to settle some of the claims, the subcontractors have pointed to deposition testimony given by the school superintendent showing that “[t]he remainder is in an escrow account.” In light of this evidence, which shows that the school board has retained money earned by Currahee for work completed, we find that the trial court erred in granting the school board summary judgment on the subcontractors’ equitable lien claim. Id.
Judgment affirmed in part and reversed in part.
Notes
The record in this case consists of approximately 2,000 pages.