5 Ga. App. 637 | Ga. Ct. App. | 1909
The questions in this case arise in a suit on a contractor’s bond for the construction of a house. The judgment ef the trial court, in refusing to allow an amendment to the petition and in sustaining a demurrer thereto, was reversed by the Supreme Court. Adams v. Haigler, 123 Ga. 659 (51 S. E. 638). Subsequently the casé was before this court on exceptions to the award of a nonsuit, and that judgment was reversed. Adams v. Haigler, 2 Ga. App. 99 (58 S. E. 320). It is now before this court on exceptions to the refusal of the trial court to allow certain amendments of the answers, and to the judgment overruling the defendants’ motion for a new trial. We will consider the exceptions in so far as we regard them material and meritorious.
When the case was first before this court, we held, construing the decision of the Supreme Court, that the defenses that could be made to the suit in the then state of the pleadings were three: (1) that the delay in completing the work was due to alterations and additions made by the plaintiff, and not to the fault of the •contractors; (3) that there were material changes in the contract, not embraced in the admitted changes set out in the petition, and which were not consented to by the defendant Bazemore, and which increased his risk as surety; (3) the separate defense of Frey, one of the contractors, that with the consent of Haigler, the •other contractor, the plaintiff had released him from compliance with the contract. On the last trial Haigler, one of the principal defendants, offered an amendment to his original answer, by which amendment he in effect set up that the plaintiff and himself had entirely abrogated the original contract on which the suit was predicated, and had substituted therefor a new and entirely differ
Bazemore, who was sued as surety on the original contract, ■offered the following amendment to his original answer: that Haigler and Frey jointly began the construction of the house named in the petition; that a few days thereafter, one of the contractors, 'Frey, was driven from the premises by the plaintiff, and warned
These amendments are elaborated with great detail, but it will, be seen that in substance they set up, as defenses: First, thatHaigler, one of the original' contractors, was released from that-contract by the second contract or agreement which he made with, the plaintiff; in other words, that this second contract under which the house was constructed was accepted by the plaintiff and by Haigler as a substitution for the original contract, and for this.
Judgment reversed,.