This was a suit by Thomas L. Prather, against John Hadley, for the breach of an alleged parol contract.

The complaint was in two paragraphs.

The first paragraph was upon a contract lor making and burning one hundred and fifty-eight thousand and eight hundred brick, on the land of Hadley, at the agreed price of three dollars and twenty-five cents per thousand, and for putting and laying said brick into a new brick house for said Hadley, on his farm, for the additional sum of three dollars and twenty-five cents per thousand.

The breach complained of was the failure to pay a bal*138anee due of eight dollars for making and burning the brick,’ and the refusal to аllow Prather to lay the brick in the walls of the said new house, to be erected by Hadley on his said farm.

The second paragraph was upon a contract to make and burn a similar quantity of brick on the land of Hadley, at the price of three dollars and twenty-five cents per thousand, and for putting the said brick into a house for Hadley, on his farm, at the further sum of three dollars and twenty-five cеnts per thousand, to be measured in the wall.

The breach complained of was, also, a failure to pay for making and burning said brick, ‍​​​​‌​​‌​‌‌‌‌​​​‌‌‌​‌​​​‌​‌‌‌​​‌​‌​‌​​‌​​​‌‌​​​‌‍and a refusal to allow the said Prather to lay such brick into the walls of said house.

The defendant answered in four paragraphs :

1. The general denial.

2. Admitting the contract for making and burning the brick, but alleging thаt he had paid the plaintiff in full for the same; also alleging that the plaintiff was to make a first-class article of brick, when, in fact, thе “brick made were defective and of an inferior class, for the reasons that the clay out of which they were made was оf a poor quality, that the brick were so set in the kiln that the benches gave way and the kiln burst, causing a great loss of brick, that the plаintiff failed to sufficiently cover the kiln, and the rain beat in upon said kiln while on fire, thus injuring the brick, and that the plaintiff failed to bum the brick long enough, so that they were soft and useless.

3. Admitting, also, the contract to have the brick made and burned, as charged in the complaint, and alleging payment for the same, but denying that there was any contract with the plaintiff for putting and laying said brick into the defendant’s house, as the plaintiff alleged.

4. Again admitting the contract to make and burn the brick as charged, and alleging full payment in discharge *139of suсli contract, but denying any contract with the plaintiff’ for laying said brick in the defendant’s house.

The second paragraph, though nominаlly a part of the answer, was pleaded and intended ‍​​​​‌​​‌​‌‌‌‌​​​‌‌‌​‌​​​‌​‌‌‌​​‌​‌​‌​​‌​​​‌‌​​​‌‍as a counter-claim, and concluded with a prayer for affirmativе relief.

A reply was filed in general denial of the fourth paragraph of the answer, and demurrers were sustained to the second and third paragraphs.

The jury trying the cause-returned a verdict assessing the plaintiff’s damages at one hundred and thirty-four dollars and fifty cеnts, and, disregarding a motion for a new trial, a judgment Avas rendered in accordance Avith the verdict, against the defendant.

Errors are assigned upon the sustaining of the demurrers to the second and third paragraphs of the answer respectively, and upon the overruling of the motion for a new trial.

It has been several times decided by this court, and ought by this time to be regarded as a Avell settled legal proposition, that a single pleading can not be made to perform the double office of an answer and a сounter-claim. Campbell v. Routt, 42 Ind. 410; Wilson v. Carpenter, 62 Ind. 495.

The second paragraph, so-called, of the answer in this case is discussed in ‍​​​​‌​​‌​‌‌‌‌​​​‌‌‌​‌​​​‌​‌‌‌​​‌​‌​‌​​‌​​​‌‌​​​‌‍the argument here as a counter-claim, and as such Ave have considered it.

It is not averred in this counter-claim, that the alleged inferiority of the brick was not knоAvn to the defendant when he accepted and paid for them, nor that any fraud was practised upon him to induce him to aсcept and pay for them. Although he may have contracted for first-class brick, yet, if he voluntarily accepted an inferiоr article, he became bound to pay what the brick he accepted Avere reasonably worth, and, in the absence of any averment to the contrary, it can not be inferred that he did pay for them more than their fair value. There was no *140error therefore in sustaining the demurrer to this second paragraph as a counter-claim. •

The third and fourth paragraphs of the аnswer were substantially the same in their averments, and as all the evidence which might have been given under the third paragraph could have been, and probably was, given under the fourth, the defendant was not, at all events, injured by the decision of the court sustaining the dеmurrer to the third paragraph. Buskirk Practice, 284; Strough v. Gear, 48 Ind. 100.

Upon the trial, evidence was admitted, over the objection of the defendant, tending to show what the value of the alleged contract for putting the brick into the defendant’s house would have been to the рlaintiff, if he had been permitted to do the work contemplated by such contract. It is insisted, that this evidence was inadmissible, in the absence of an allegation of special damages in the complaint.

It is the rule, that, in cases of executory contracts, like the one under discussion, such damages as naturally result from the breach of the contract are presumed to havе accrued to the injured party, and may be recovered under a general ‍​​​​‌​​‌​‌‌‌‌​​​‌‌‌​‌​​​‌​‌‌‌​​‌​‌​‌​​‌​​​‌‌​​​‌‍allegation of damages in the complaint, and that the measure of damages in such cases should be the difference between the contract price of the work to be done and the reasonable cost of the work at the usual and ordinary prices. Lindley v. Dempsey, 45 Ind. 246 ; Dunn v. Johnson, 33 Ind. 54.

We think the evidence objected to was prox^erly admitted.

It is also insisted, that certain instructions given by the court to the jury, on its own motion, were erroneously given, but, as these instructions were in substantial accordance with the rules аbove laid down for the recovery and measure of damages, we are of the opinion that they gave the law corrеctly to the jury, as to all the matters to which they related.

*141Takingthe instructions given to the jury altogether, we are of the opinion, that they were as favorable to the defendant as he had any just reason to expect.

It is further insisted, that the court erred on the trial in refusing to give two instructions prayed for by the defendant.

Waiving any discussion as to the correctness of the instructions prayed, as applicable to the case at bar, we are further of the opinion, that the questions -of law raised by them were bettеr and more fully presented by the instructions given by the court upon its own motion.

Under such circumstances, the court did not err in refusing ‍​​​​‌​​‌​‌‌‌‌​​​‌‌‌​‌​​​‌​‌‌‌​​‌​‌​‌​​‌​​​‌‌​​​‌‍to give the instructions thus prayed for by the defendant.

We are unable to see any reason why anew trial should have been granted.

The judgment is affirmed, at the costs of the appellant.

Petition for a rehearing overruled.