Habitat Education Center appeals from a grant of summary judgment to the United States Forest Service in a lawsuit challenging the environmental impact statement (“EIS”) prepared by the agency in connection with a forest management project in the Chequamegon-Nieolet National Forest in northern Wisconsin. The project at issue is a timber sale known as the “Twentymile” project. In the district court, the plaintiffs made several challenges to the adequacy of the EIS. On appeal, they argue only that the EIS failed to describe the reasonably foreseeable cumulative effects of another proposed timber sale, known as the “Twin Ghost” project. We conclude that at the time the EIS was being prepared, the Twin Ghost project was too nebulous to be discussed in any meaningful way, and thus affirm the district court’s grant of summary judgment to the Forest Service.
I. Background
The Chequamegon-Nieolet National Forest covers approximately 1.5 million acres in Northern Wisconsin. It consists of many lakes, rivers, and streams, is home to over 300 species of wildlife, and is visited by approximately 2.1 million people each year. The forest occupies land that was once clear-cut by nineteenth-century logging and forest fires. In the 1920s, the federal government began purchasing the land and managing it as a national forest. *899 Because it emerged from the government’s purchases of individual tracts of land, it is made up of a patchwork of public and private lands. In 1933, these were aggregated into two noncontiguous units. These came to be known as the Nicolet and Chequamegon units. Since 1993, these units have been managed as a single entity, now known as Chequamegon-Nicolet National Forest, although the two units remain non-contiguous. (The Nicolet unit is located in the eastern half of northern Wisconsin, and the Chequamegon unit is located in the western half of northern Wisconsin.)
Since 2002, the Forest Service has proposed seventeen timber projects covering an area of approximately 130,000 acres. These timber projects are designed to advance a number of forest management goals; in particular, they are intended to ensure a diversity of tree ages in the forest (most of the trees are the same age because they were planted in the 1920s and 1930s when the forest was being restored.) The plaintiffs in this litigation have been involved in challenges to most of these projects through the administrative environmental review process. The plaintiffs have appealed final agency actions to the district court in six cases, settled with the Forest Service in four cases, and have refrained from challenging four timber sale approvals.
On December 23, 2004, the Forest Service announced the proposed Twentymile timber sale. This proposed sale was located immediately to the northwest of a previous timber sale, the Cayuga sale. The proposed Twentymile project would involve logging and roadbuilding on 8,875 acres of public land near Clam Lake in Bayfield County, Wisconsin. During administrative review, the plaintiffs submitted extensive commentary and argued that the cumulative effects from the Twentymile and Cayuga projects would have a significant impact on wildlife habitat. In particular, plaintiffs argued that the Twentymile project would put the American Pine Marten at risk. 1
Over the plaintiffs’ objections, the Forest Service released its final EIS and Record of Decision (“ROD”) in February 2007, authorizing the Twentymile project to move forward largely as originally proposed. The plaintiffs brought an administrative appeal pursuant to Forest Service regulations. That appeal was denied on May 24, 2007.
On June 22, 2007, the plaintiffs filed a civil complaint challenging the Twentymile Final EIS and ROD in the Eastern District of Wisconsin. Among other claims, plaintiffs contended that the Forest Service had violated the National Environment Policy Act’s (“NEPA”) requirement to fully and fairly analyze the cumulative environmental impacts of all “past, present, and reasonably foreseeable future actions” across the forest.
After the parties had briefed cross-motions for summary judgment and shortly before the scheduled oral argument, the Forest Service announced another new timber sale, the Twin Ghost project, located immediately to the south of the Twentymile timber sale and to the southwest of the Cayuga timber sale. The Twin Ghost project is not mentioned in the Twentymile *900 EIS or ROD. However, it was identified in internal Forest Service documents in the Twentymile administrative record as a project “in the timber pipeline.” The district court ordered supplemental briefing on the Twin Ghost project.
In their supplemental brief, the Forest Service conceded that the Twin Ghost project falls within the Forest Service’s designated cumulative effects area for the Twentymile project and that it did not consider the Twin Ghost project during the EIS process for the Twentymile project. However, the Forest Service argued that the project was not reasonably foreseeable and thus its omission from the EIS was not error.
As part of the supplemental briefing, the Forest Service submitted a detailed affidavit describing the history of the Twin Ghost project. Forest Service staff first began to “think about” what types of management activity might be needed in the Twin Ghost area in 2005. The first step was to identify the potential goals of a restoration project conducted at some point in the future. This meant collecting data about the existing state of the vegetation, wildlife, roads, and other resources in the Twin Ghost area. This process began in the spring and summer of 2005 and was completed in the fall of 2007. (Recall that the final Twentymile EIS and ROD were released in February 2007, Habitat’s administrative appeal was denied in May 2007, and this suit was initiated on June 22, 2007.) In November 2007, the Forest Service identified a preliminary project boundary and an initial list of tree stands, to consider for inclusion in the project. In January 2008, the Forest Service developed a list of goals for the Twin Ghost project. However, in February 2008, the Forest Service put planning for Twin Ghost on hold to focus on other priorities, and did not return its attention to Twin Ghost until October 2008, when it was added to the Forest Service’s Schedule of Proposed Actions. In November 2008, Twin Ghost was disclosed to the public. As of the date of the district court’s decision, the Forest Service continued to receive public comment about the proposal and no decision to implement the proposal had been made.
On January 12, 2009, the district court issued an opinion granting summary judgment to the Forest Service. Among other holdings not challenged here, the district court determined that the Twin Ghost timber sale was not “reasonably foreseeable” under NEPA. Plaintiffs appeal, and we now affirm.
II. Analysis
We review de novo a district court’s grant of summary judgment.
Schoenfeld v. Apfel,
However, before reaching the merits of the plaintiffs’ argument, we must address the Forest Service’s claim that the plaintiffs have forfeited them Twin Ghost argument by not raising it in the administrative proceeding or in the district court before cross-motions for summary judgment were filed. In support of its argu
*901
ment, the Forest Service relies on two cases:
Dept. of Transp. v. Public Citizen,
We need not reach the merits of this forfeiture argument, because the argument itself has been waived. When the district court ordered supplemental briefing on the question of whether Twin Ghost was a reasonably foreseeable future project, it asked the parties to discuss whether this question had been forfeited or waived. The Forest Service responded with only a short footnote in their supplemental brief. In this footnote, the Forest Service noted that the plaintiffs did not raise Twin Ghost before the agency. However, they did not claim, even in a conclusory manner, that this amounted to waiver, instead making a somewhat oblique reference to
Vermont Yankee Nuclear Power Corp. v. Natural Res. Def. Council,
It is not surprising that the Forest Service declined to press the argument that the plaintiffs should have argued earlier for the Twin Ghost project to be included in the EIS. This argument cuts directly against the Forest Service’s main argument: that the Twin Ghost project was so far from taking shape that not even the Forest Service, let alone an outsider, could have said anything meaningful about it. The Forest Service did not make any attempt below to establish that the plaintiffs were aware of the Twin Ghost project and could have raised it during the administrative process. Having made the decision not to advance a forfeiture claim below, the Forest Service cannot change tacks and advance such an argument here.
On the merits, the plaintiffs argue that Twin Ghost was either a “present” or a “reasonably foreseeable future action” and thus should have been discussed in the EIS. See 40 C.F.R. § 1508.7 (requiring agencies to consider the cumulative environmental impacts of all “past, present, and reasonably foreseeable future actions”). They rely principally on the fact that during the EIS process, one Forest Service employee noted that Twin Ghost was “in the timber pipeline.” 2 The Forest Service responds by arguing that while it knew in a general sense that there would be a project in the Twin Ghost area in the future, it did not know the scope or aims of this future project and thus could not speak meaningfully about it.
Plaintiffs rely heavily on
Mid States Coalition for Progress v. Surface Transp. Bd.,
The Forest Service, in contrast, relies on
Environmental Protection Information Center v. United States Forest Service (EPIC),
We agree with our sister circuits that an agency decision may not be reversed for failure to mention a project not capable of meaningful discussion. To the extent plaintiffs are arguing that the Eighth Circuit’s decision in
Mid States
is in tension with this consensus, we reject their reading of that decision. The court in
Mid States
concluded that adverse effects from the readily foreseeable increase in coal sales were certain to occur and questioned the defendant’s contention that those effects could not be meaningfully forecast.
To illustrate the danger that the cumulative effects requirement was designed to protect against, it is useful to discuss another case relied on by the plaintiffs,
Blue Mountains Biodiversity Project v. Blackwood,
The contrast between this case and
Blue Mountains
is instructive. In
Blue Mountains,
the nature of all five logging projects was known in advance of the preparation of each project’s environmental assessment. Indeed, all five sales had been disclosed to logging companies, with estimated sale quantities and timelines, before the environmental assessment at issue had even been prepared.
Id.
Here, the Forest Service had not yet developed the goals for the Twin Ghost project, let alone forecast the quantity and timing of logging that would take place. Not until the fall of 2007, months after the agency issued the final EIS and ROD for the Twentymile project, had the Forest Service even gathered enough information about the existing state of Twin Ghost area to identify the goals of the Twin Ghost project. The environmental assessments at issue in
Blue Mountains
made no reference to the other contemporaneous timber sales, be it as past, present, or future sales. Here, because the Twin Ghost project is being developed well after the Twentymile proposal, its EIS must discuss the combined effects of Twin Ghost and Twentymile even if the Twentymile EIS cannot.
Cf. EPIC,
As the district court noted, some notice of Twin Ghost in the Twentymile EIS would have improved the document. It seems that the better practice would be to err on the side of disclosure, both to aid *904 the public in understanding the Forest Service’s plans and to avoid costly litigation. But without some indication that meaningful analysis could have accompanied this mention, it is not a substantial enough ground to invalidate the EIS and start over. The omission of Twin Ghost does not render the EIS any less of a hard look at the environmental consequences of the Twentymile project or cast any doubt on the conclusions drawn in that report.
III. Conclusion
For these reasons, we AFFIRM the judgment of the district court.
Notes
. The American Pine Marten is a "state-listed” endangered animal because its Wisconsin population is very small. The pine marten is a member of the weasel family, similar in size to a small house cat or full-bodied mink. By 1925, logging had driven the pine marten out of Wisconsin entirely. The Wisconsin Department of Natural Resources began reintroducing the pine marten in 1979. That reintroduction has not been particularly successful; however, the pine marten is not endangered in other areas of its range, and the Chequamegon pine marten population is not a significant portion of the total pine marten population.
. This email, sent June 30, 2005, was included in the administrative record for the Twentymile project.