125 Va. 106 | Va. | 1919
delivered the opinion of the court.
On July 2, 1912, William Rueger, the then owner of certain real estate located at the southeast corner of Ninth and Bank streets, in the city of Richmond, entered into a written agreement with F. T. Nesbit & Co., Inc., builders, for-the construction on the above-mentioned site of a hotel: building, to be known as “Hotel Rueger.” On August 26, 1912, the “Hotel Rueger” was incorporated under the name of “Hotel Rueger, Inc.,” and took over the real estate and the building contract. The building was completed about March 14, 1914.
A large number of sub-contracts were let by F. T. Nes-bit & Co., Inc., for parts of the work; and when the building was approaching completion it became financially embarrassed and subsequently went into bankruptcy.
On February 2, 1915, the cause was referred to a commissioner (to whom the other two causes, as above mentioned, had already been referred), and the three causes were directed to be thereafter heard together. Among other inquiries, the commissioner was directed to report an account of all liens against the property.
The commissioner, on February 15, 1916, returned his report showing that there remained in the hands of the owner due to F. T. Nesbit & Co., Inc., and subject to the valid liens of the sub-contractors, the sum of $4,359.79; and disallowing upon technical grounds the claims of liens of H. N. Francis & Co., Inc., Pittsburg Plate Glass Company, and Standard Engineering Company. With respect to the Warren-Ehret Company’s claim, the commissioner reported that it was barred by the statute of limitations.
We think, too, that the case of Taylor v. Netherwood, 91
2. That where the account contains such statement, and the fact that the work or materials were contracted for as an entirety is established by the evidence, a general statement of the fact and the sum charged therefor under the contract will suffice.
What has been said of H. N. Francis & Co.’s account applies with more force to the claims asserted by the Pittsburg Plate Glass Company and the Standard Engineering Company, whose accounts afford illustrations of, perhaps, a stricter compliance with the statute (invoking where needed the aid of ample admissible extrinsic evidence) than the first-mentioned account. Let it be observed of all these accounts that no question is raised as to their bona fides. They were disallowed upon technical grounds, based largely, we conceive, upon a too literal adherence to some of the language used in the opinion in Taylor v. Netherwood. The court there was dealing with the facts of the particular case, and held the account sufficient; but it neither decided, nor intended to decide, that the sufficiency of all other accounts was to be measured by the account filed in that case.
The reporter will set out all three of these accounts in reporting the case, and it would serve no good purpose and uselessly add to the length of the opinion, to notice in detail the various items of the last-mentioned claims. Both should have been allowed.
1. That there is no personal liability upon the Hotel Rue-ger, Inc., for any of the liens set out in this record. When notified of the H. N. Francis & Co. claim of lien, it set apart a fund sufficient to discharge it; which fund was after-wards paid into court, and is now the subject of controversy.
2. That the commissioner was in error in rejecting the liens of H. N. Francis & Co., the Standard Engineering Company and the Pittsburg Plate Glass Company on the ground of deficiency of statement.
Section 2481 of the Code provides that no suit shall be brought or petition filed to enforce a mechanic’s lien after six months from the time when the whole amount covered by the lien has become payable. By contract the whole amount sought to be covered by the Warren-Ehret lien became payable November 15, 1913, and the six-months’ limitation expired May 15, 1914. The suit by Hotel Rueger to which this claimant was a party was not brought until June 4, 1914, too late to stop the running of the statute of limitations as to that lien. Warren-Ehret Company was not a party to either of the other two suits, and the account of liens ordered in each was not made until after the lien was barred.
4. That the Engleby & Bro. Co.’s claim, to the extent to. which it was allowed, is sufficiently definite within the meaning of the statute.
Affirmed in part; reversed in part.