14 Haw. 448 | Haw. | 1902
OPINION OF THE COURT BY
H. Hackfeld & Go., Ltd., brought an action in the Circuit Court of the Fourth Circuit to enforce a lien claimed against certain property of the defendant. The case was tried without a jury and judgment rendered for the defendant. Thereupon a petition for a writ of error was filed,' error being assigned in. certain findings of fact and rulings of law made by the trial court. Undisputed evidence shows the following facts:
On April 5, 1900, J. H. Smith and W. W. Corey, copartners, entered into a contract with the Hilo E. E. Co1, whereby they agreed to do, according to certain specifications, all the grading, necessary for the construction of “the Hilo railroad for a distance of about ten miles, being from station 431 at the southerly limit of the Olaa Cane Land to the Lava Flow of
The trial court found, in substance, the foregoing facts. The following findings of facts and rulings of law were also made:
“10. That the evidence in this case shows quite clearly and satisfactorily that the pláintiff herein never had a contract, written or oral, expressed or implied, with the defendants Smith and Corey or the Hilo R. R. Co., Limited.
“11. That no privity existed between the plaintiff herein and the Hilo R. R. Co., Limited, or Smith and Corey, in respect of the transaction out of which this litigation grew.
“13. That no assignment of his contract or agreement with Smith and Corey by the sub-contractor, Herman Elderts,’ co-defendant herein, was made to the plaintiff, nor was any substitution of parties plaintiff sought ’or obtained by said plaintiff prior to the filing of the lien by the plaintiff, or prior to the bringing of this suit, or at any other time, or at all.
“1. The court concludes that in the absence of an assignment to which the owners- or original contractors consented in writing to- the sub-contract or agreement by and between the co-defendant, or sub-contractor, Elderts, and the plaintiff herein, that plaintiff cannot be substituted to the rights or liabilities of the- co-defendant, Herman Elderts.
“2. That it is essential in order for plaintiff to- maintain its*451 action that there should exist a privity between the plaintiff and defendants Hilo E. E. Co., limited, and Smith and Corey in respect of the matter sued on.
“3. That the filing of the lien and notice by the plaintiff herein did not make plaintiff a party to the contract nor bring it within the statute in the absence of the assignment and consent referred to' in conclusion number 1 herein, nor does' our statute work a subrogation of the sub-contractor’s rights to the rights of any one else.”
The plaintiff was the. material-man of a sub-contractor. If it falls within the class designated by our statute to which a lieu is given for certain materials, it is entitled to such lien even though no contract was entered into by it with the owner of the railroad or with the original contractor. In the ordinary sense, the lien does not arise out of contract but is given by law to those who are placed under certain stated conditions; it arises out of contract in the sense only, that, the statute declaring that a lien shall exist under those circumstances for the price of certain materials, the owner, when he awards a contract for the erection of a structure of his, is conclusively presumed to have so contracted with reference to the law and to have voluntarily subjected his property to the rights thus given to material-men and contractors. “This argument rests upon a misconception as to the nature and character of a'mechanic’s lien. This lien is a creature of the statute, and was not recognized at common law. It may be defined to be a claim created by law for the purpose of securing a priority of payment of the price and value of work performed and materials furnished in erecting or repairing a building or other structure, and as such it attaches to the land as well as the buildings erected thereon. * * * Now, it is not the contract for erecting or repairing the building which creates the lien, but it is the use of the materials furnished and the work and labor expended by the contractor,, whereby the building becomes a part of the freehold, that gives the material-man and laborer his lien under the statute. The lien is brought into operation by virtue of the statute, and the contract for building is entered into presumably in view of, or wnth reference to, the statute.” — Van Stone v. Stillwell &
The class to which the benefit of such liens is granted, is, of course, broader in some jurisdiction and more limited in others. Just how large it is. in any particular case is to be determined in view of the provisions of the statute in force in that jurisdiction. Section 1 of our statute (Chapter 21, Laws of 1888) reads: “Any person or association of persons furnishing labor or material to be used in the construction or repair of any building, structure, railroad or other undertaking, shall have a lien for the price agreed to be paid for such labor or material (if it shall not exceed the value thereof) upon such building, structure, railroad, or other undertaking, as well as upon the interest of the owner of such building, structure, railroad or'other undertaking in tire land upon which the same is situated.” This language is very broad, broader, perhaps, than that of the statutes in many of the states. Any person, with but two limitations, shall have a lien. Those limitations are (1) that such person shall furnish the labor or material and (2) that such labor or material shall be furnished specifically to be used in the construction or repair of the structure sought to. bé charged with the lien. In Allen & Robinson v. Redward, supra, the lien of a material-man of an original contractor was recognized and enforced, and, while the point was, perhaps, not necessary to be determined, the Court would seem to have been of the opinion that any material-man or sub-contractor had a. lien. At page 153 it said, “the Circuit Court, correctly held that the amount for which the property may be charged with a lien in favor of a sub-contractor or material-man is not limited to the amount payable by the owner to the -contractor,” and, after quoting section 1 (at p. 154), -“This section of the statute .gives a lien to ‘‘any person furnishing material’ and makes no distinction between contractors and sub-contractors. Other sections, 5 and 6, show clearly that sub-contractors vere intended
Another finding made by the trial court is: “That in pursuance of the said contract between the plaintiff and co-defendant Herman Elderts, this plaintiff furnished all of the items and the cash set forth in plaintiffs Notice of Lien, to the said Herman Elderts on his personal account.” To what extent, if at all, the court below based upon this finding its judgment that plaintiff was not entitled to a lien, is not clear. If the finding was intended to- mean that in furnishing the material Hackfeld & Co. relied exclusively upon the credit of Elderts and waived its right to a lien upon the property of the Eailroad Co., the finding was unsupported by the evidence; if, on the other hand, the court meant merely that the' plaintiff charged the goods upon its books to Elderts and that it intended not to Avaive its claim for payment upon Elderts personally, then, while that Avas undoubtedly the fact, it would constitute no defense against the lien. The material-man had a right to' rely upon the lien giAen him by laAA as well as upon the personal liability of the sub-contractor and, having that right, the presumption is, in the absence of any shoAving to'the contrary, that he intended to aA^ail himself of both remedies so far as necessary. “A subcontractor, laborer, or material-man, in dealing Avith tire contractor, is presumed to rely upon his lien upon the property. It is not necessary for him to prove affirmatively that he relied upon the credit of the building, if hisi labor or materials actually entered into its construction. The burden is upon the landowner to show that he relied upon the credit of the contractor alone. The law gives the sub-contractor the right of a lien if
The ruling of the court below to- the effect that the plaintiff has no- lien upon the defendant’s railroad for the cash advanced by it to Elderts with which the latter was to pay the laborers engaged in the grading, was, we think, correct. Cash advanced for that purpose was not, within the meaning of the statute, material to be used in the construction of the road-bed nor was it labor. The position is the same as if the money had been loaned to Elderts for the purpose of purchasing from another material for the road. If, in such case, Elderts had failed to
The foregoing questions are all raised by the plaintiff’s assignment of errors. Whether or not the lumber furnished by the plaintiff and used by Elderts in erecting near the line of road buildings for the protection or accommodation of laborers employed in the grading, was material used in the construction of the railroad, within the meaning of the statute, need not be now determined. A similar question may arise later concerning some or all of the tools used during the progress of the work.
On the part of the defendant in error, the judgment is sought to be supported on the ground, among others, that proceedings to collect the amount due on the lien were not commenced within three months after the completion of the structure against which it was filed and that therefore the lien, if it ever existed, has been forfeited.
It may be 'assumed for the purposes of this branch of the case that the “structure” contemplated .by the statute is the portion of the railroad situate between stations 431 and 642, and not the whole railroad, and that the structure, as thus understood, was completed on October 4, 1900. Other facts material in this connection are that the plaintiff’s declaration, of which a copy of the notice of lien and bill of particulars was made a part, was filed in the Circuit Court of the Fourth Circuit on December 21, 1900, and that summons in the ordinary form was issued on the same day. On or before December 24, 19Ó0, service was made upon one Lambert as the agent of the defendant corporation, but the sheriff’s original return of this service is Uot with the records in the case. On July 31, 1901, a certificate reading as follows, was, by leave of court, filed by the sheriff: “I, Elderts, Deputy Sheriff of the Island of Hawaii, do hereby certify in addition to my certificate made on the summons returned in this cause on the 24th day of December, 1900, that I made due and diligent search within the jurisdiction of
For the defendant it was contended .in the lower court on plea in abatement and is contended now, that the service attempted to be made in December, 1900, was not valid because not made on one authorized by law to receive or accept it for the corporation or to bind it thereby. Let it be assumed for ‘the purposes of this case that this contention is sound. It still remains true and undisputed that the service of March 6, 1901, was good and valid. The question is, when are proceedings to be deemed to have been commenced?
“For certain purposes an action may be held to be commenced, while for other purposes the courts may ■ deny to the action the attribute of a ‘commenced’ suit. But generally speaking, not noting the exceptions to and the qualifications of the doctrines, the legislation of the states and the adjudications follow three main classifications, to wit: the action is commenced when the complaint is filed, when the process is issued, or when the process is served on the defendant.”- — 1 Encycl. PI. & Pr. 119. One class of cases is to the effect that the suit is commenced when the petition is filed, provided it is filed with the intent that process be promptly issued and served, and another class that it is commenced when process is issued provided it is issued with the intent that it be promptly served. As between these two last mentioned lines of decisions, wei need not determine now which is founded on t-he better reasoning, because in -the case at bar not only was the declaration filed but process was
Section 2 of the statute on liens, says, in part: “The lien shall continue for 3 months, and no longer, after the completion of the construction or repair of the building, structure, railroad or other undertaking against which it shall have been filed, unless the same shall have been satisfied, or proceedings commenced to collect the amount due thereon by enforcing the same.” The nature of the proceedings necessary to- be followed in order to enforce the lien is set forth, in a general way, in Section 5. “The liens hereby provided may after demand and refusal of the amount due, or upon neglect to- pay the same upon demand, be enforced by proceedings in any court of competent jurisdiction, by service of summons, as now practiced. Such summons shall set forth the ordinary allegations in assumpsit, and, in addition thereto, note that a lien has been filed. Before proceeding to trial, the defendant shall be served with a detailed specification of the claim, provided that no such specification shall have been furnished before proceedings wex*e- commenced. Judgment xxpon such proceedings shall be as in ordinary cases, and may be- enforced by execution as now allowed. In case the contract for services or material upon which the lien has accrued shall have been directly with the owner of the property, an attachment may issxxe in connection with the suit xxpon the filing of a bond of indemnity to- the said owner in such sum as the Magistrate or Coxxrt may fix. If it shall appear that sxxch bond is insufficient, the Magistrate or Coxxrt, shall cause a new bond to be filed for a greater amo-xxnt, or with additional security.” There is nothing in tire section last quoted 'or in airy other portion of the Act, making it essential that service'-be had before the action can be regarded as commenced. The “service of summons” referred to in section 5 is but oiré step in the proceedings. Other steps are mentioxxed in the same section, as, for example, the service of a detailed specification of the claim, the
In Hail v. Spencer, 1 R. I. 17, 19, 20, in holding that the issuing of the writ is the commencement of the action, the court said: “Now it is admitted that the writ, in this case, was issued prior to the expiration of the six years, and, unless, tire actual receipt of the service of it, by the officer, be necessary to constitute the commencement of the action, it was commenced within the six years. In the ordinary acceptation of terms, the action is certainly commenced when the writ is issued, but to answer the intent of the statute, is something more than this required? If more, what is it? Is it the service of the writ? If so, it is the sheriff who commences the suit, and not the plaintiff. And tire ability of the sheriff to malee the service may depend on -a thousand circumstances, over which neither he nor the plaintiff may have any control; nay, even on the will of the debtor himself, as his absence from the county. We cannot suppose that the legislature, in any event, intended to make a man’s rights dependent bn such contingencies. .
“Is it the receipt of the writ by the sheriff that is required in order to constitute the commencement of an action? If so, its commencement may still depend on contingencies wholly inde*459 pendent of the plaintiff, as the sheriff’s occasional absence, - his sickness, or his want of official qualifications. But at any rate, why should the receipt of it by the sheriff be required. As long as the defendant is untouched by the precept, of what consequence is it to him, whether it be in the hands of the plaintiff or the sheriff? How can his liability be affected by this or that event? The truth is, that in contemplation of law, the writ is issued on the application of the creditor, by the sovereign power of the state, through the instrumentality of its officers. It.is the state’s precept or command, and is issued and the action commenced, whenever it is in the hands of the plaintiff, or his attorney, ready to fulfill its purpose. In this view the commencement of the action depends wholly on the will, or the diligence of the plaintiff. If he loses his right, it is wholly the result of his neglect. It should, however, be followed up by such acts as show that it is a real and not a pretended commencement of a suit. For if there be an unusual lapse of time between the day of the date of the writ, and that of its delivery to the sheriff, and wholly unexplained, it might raise a presumption against the correctness of the date, which would force on the plaintiff the necessity of proving its correctness.” See also Cross v. Barder, 16 R. I. 266; Gosline v. Thompson, 61 Mo. 471; Spofford v. Huse, 9 Allen 575, 6; Bunker v. Shed, 8 Met. 150, 3; Triddy v. Wokee, 74 Tex. 142, 3; Day v. Lamb, 7 Vt. 428.
If, then, the plaintiff in filing its declaration and in procuring the issuance of process, acted with the necessary intent, these proceedings were commenced within the time required and its lien was continued in force. Hpon the present state of the case the judgment under review cannot be supported on the theory that such intent was lacking.
The judgment is set aside and a new trial ordered.