267 Mass. 541 | Mass. | 1929
These two actions of tort are brought by a construction company against the defendant bonding company and its president, respectively. In each case the defendant is alleged to have unlawfully and maliciously induced, persuaded and coerced The Chatham, Inc., hereinafter called the Hotel Company, to break a contract which it had entered into with the plaintiff, in order to obtain the benefits thereof for the Longacre Engineering and Construction Company, hereinafter called the Longacre Company.
The cases were formerly before this court on exception of the plaintiff to directed verdicts for the defendants, and it was then held that the verdicts should not have been ordered. 260 Mass. 599. At the second trial a verdict in the sum of $322,400 was returned for the plaintiff in each case. The defendants’ exceptions relate to the refusal of the judge to grant their motions for directed verdicts, to his refusal to grant certain requests for rulings, to the admission and exclusion of evidence, and to rulings given and refused.
There was evidence that the plaintiff, in July, 1922, had entered into a contract to construct an apartment hotel for the Hotel Company. In August, 1922, the defendant corporation contracted to underwrite an issue of bonds of the Hotel Company to provide the money required to construct
1. The evidence in the present record permits substantially the same inferences by the jury on the question of liability as did the evidence in the first trial. In support of the motions for directed verdicts the defendants have sought to point out material differences in the evidence in the two trials.
It was not contended in the presentation of the case to this court at the former trial, and it does not now appear to be contended, that Moore, while acting for himself, was not also acting for the bonding company. He testified that he acted for that company in all he did.
At the present trial evidence was introduced which at the former trial had been in the form of offers of proof. There was some variance between the evidence thus introduced and that contained in the offers, but the changes are not such as to require the court to reach a different conclusion on this issue. In both trials there was evidence that, about the middle of September, 1922, after the question of the bond to be given by the plaintiff for the performance of its contract had been considered, and after Watts, the plaintiff’s president, at Moore’s suggestion had submitted the plaintiff’s figures on costs to be checked up by one Thomas, vice-president and manager of the Longacre Company, Watts told Moore that Thomas and the plaintiff were not far apart on figures which he offered to show Moore, and the latter said, “I don’t wish to discuss this matter any further with you. Mr. Clark and Mr. Tobey know what I want, and they are handling this matter for me, and anything more that you have got to say, say it to them.” There is no difference in the legal significance of this evidence and of that contained in the offer of proof at the first trial. The jury could have found that notwithstanding the employment of Clark by the Hotel Company he later became an agent of the defendants. The evidence that Watts had direct dealings with Moore after Moore’s statement concerning Clark and Tobey was made to him did not require an inference that the agency of Clark and Tobey had thereby been terminated.
The defendants contend in support of their motions for directed verdicts that there was no evidence at the second trial that Moore induced the Hotel Company to repudiate its contract with the plaintiff and award a contract to the
The statement of Moore set forth above was made about the middle of September, 1922. There was testimony that about the middle of October, 1922, Clark, just after an interview with Moore, from which Watts had been excluded, said to Watts, "It looks dark and gloomy for Grabow in this matter, because Moore is going to have Tobey president of this company. And ... it looks dark for you, too, because he is not going ahead unless Longacre gets the building contract.” Moore testified or admitted that Clark and Tobey told him in New York that they were going to Boston to eliminate Grabow and others and to install a "new crowd,” that this substitution of new officers for the Hotel Company met with his approval, and that he made it conditional that he was to deal with the new set of men; that they were proposing to eliminate Qrabow as a step toward getting the contract for the Longacre Company.
In October, 1922, there was a conference at Tobey’s office in New York at which Clark, Tobey, Watts and two officials of the Hotel Company, one of whom owned substantially all of the stock of that company which had been issued, were present. There was evidence that in the course of that meeting Tobey said he was going in as president of the Hotel Company in place of Grabow, asked Watts what he would take for his contract then and there, and stated that he and Clark had seen Moore the day before and “there wasn’t any earthly way of going ahead with the contract unless . . . [Watts] got out of the picture and Longacre built the building.” Tobey tried to induce the plaintiff to give up its contractual rights, and the officials of the Hotel Company joined in urging it to compromise.
The jury could have found this evidence significant because of its tendency to prove the result which the defendants, through the agency of Clark and Tobey, intended to accomplish, and because of the suggestion in it of means to be employed; and could have found that the officials of the Hotel Company had been persuaded by the agents of the defendants to favor their interests and that as a result of what was
This series of events culminating in the execution of a building contract with the company in which Moore had a financial interest, thereby excluding the possibility of the performance by the Hotel Company of its contract with the plaintiff, and followed by the execution of a new underwriting contract with the defendant corporation, when considered in the light of the other testimony, leads us to the conclusion reached in the former opinion that there was evidence upon which the jury could find that the defendants, through Clark and Tobey as their authorized agents, wrongfully induced the Hotel Company to break its contract with the plaintiff. The contention of the defendants, that the evidence permits of no further inference by the jury than that the defendants simply refused to enter into a new underwriting agreement while the plaintiff had the construction contract, cannot be maintained. The differences in testimony at the two trials are not sufficient to justify the court in coming to a different conclusion on this point from that reached in the first opinion.
The defendants further contend in support of their motions for directed verdicts that by virtue of Exhibits 10 and 10A the contract of the plaintiff with the Hotel Company had been cancelled by the parties. The first of these exhibits was considered in the earlier opinion but Exhibit 10A was not then in evidence. It is dated October 13,1922, and provides,
The contentions that these exhibits contemplated that a new construction contract was to be entered into by the Hotel Company; that there was no default in performance of any of the conditions stated in the exhibits before the new contract was entered into, and hence the making of the new contract could not be a breach of the contract with the plaintiff, fail to give consideration to the obvious purport of the exhibits. The conditions contained therein were apparently conditions precedent to any release becoming operative. In the absence of any evidence of performance of the conditions we must follow the decision reached in the earlier opinion when the court was considering one of these exhibits and hold that the documents in and of themselves do not constitute a release or cancellation of the contract.
The reference in the plaintiff’s contract to the plans in evidence did not make it too indefinite to be a valid enforceable contract.
2. The defendants contend that there was no evidence to justify a verdict for substantial damages.
The damage recoverable for inducing a breach of contract is “the loss of advantages, either of property or of personal benefit, which, but for such interference, the plaintiff would have been able to attain or enjoy.” Walker v. Cronin, 107 Mass. 555, 565. Lopes v. Connolly, 210 Mass. 487, 494, 495.
If the contract between the plaintiff and the Hotel Company had been performed, the plaintiff would have been entitled to a sum equal to the cost to it of the materials and of the performance of all the work required to be done under the contract, “and in addition to such cost a net builder’s fee or compensation of two hundred sixty thousand dollars ($260,000).” The verdict for the plaintiff was evidently based upon this agreed compensation with interest from the date of the writ.
The evidence upon which the plaintiff contends that the jury could find to a practical degree of certainty that it would have received this compensation if the Hotel Company had not been wrongfully induced to break the contract is substantially as follows: A building of the kind planned and described could have been built for the price called for in the plaintiff’s contract or less. Prior to November 10, 1922, the Hotel Company held options for the purchase of the land on which the hotel was to be built, some of them having been obtained in the name of an official of the company in March and April, 1922. .One of the options expired October 2,1922, but was reinstated November 18,1922. Subscriptions to the amount of $640,000, for supplying funds upon security secondary to any first mortgage, had been obtained and there were other funds available to the Hotel Company; a responsible stock brokerage house was to be engaged to sell
The title to the real estate on which the building was to be erected was taken January 9, 1923, and was paid for in part with money advanced by the defendant corporation under its new contract with the Hotel Company for the sale of bonds dated November 10, 1922. The Longacre Company started to erect the building in February, 1923, and all work stopped late in March of that year.
The jury were instructed, in substance, that the plaintiff could recover only nominal damages for wrongful interference with the contract unless substantial damages were proved with reasonable certainty, and that there could be no recovery for speculative or conjectural profits. They were told that if they could not with reasonable certainty determine how much of the builder’s fee stipulated for in the contract the plaintiff would have received, only nominal damages could be recovered. The judge in stating the law as to recovery of prospective profits substantially followed what has been said in John Hetherington & Sons, Ltd. v. William Firth Co., supra, Randall v. Peerless Motor Car Co. 212 Mass. 352, 379, 380, 382, Neal v. Jefferson, 212 Mass. 517, Burnham v. Dowd, 217 Mass. 351, 360, Orbach v. Para
The evidence showing that the hotel was not completed by the Longacre Company, that several actions were brought against the Hotel Company, and that the defendant corporation after paying $200,000 under its new bonding contract foreclosed its mortgage because of the failure of the Hotel Company to meet its obligations, was strong evidence tending to prove that the Hotel Company would not have been able to fulfil its obligations under the building contract with the plaintiff; but we cannot say that it was conclusive. The jury could have found that the financial aid promised for putting the project through under earlier management was largely lost when the officers were changed and the contract was made with the Longacre Company. It also appeared that while the new financing was in progress there were transactions in connection with it which led to complaints in the criminal court. The president then in office gave this as the reason why the Hotel Company became unable to raise further money to finance the enterprise. The jury may have found that changes in the situation after Grabow was eliminated and the plaintiff’s contract broken were the cause of this failure rather than any unsoundness of the plan of financing upon which the Hotel Company had placed reliance to carry out its contract with the plaintiff.
Proof that one of the three options of the Hotel Company on real estate was not in force when the plaintiff’s contract was broken, that the Hotel Company then had no physical property or money, that the first contract with the defendant company had been terminated, and that the Hotel Company
3. We have examined the defendants’ exceptions to the rulings on the admission and exclusion of evidence, in so far as they have been argued, and in those rulings no reversible error appears.
4. The defendants asked in several requests for rulings that the jury be instructed that the defendants had a right to refuse to undertake to raise money for the Hotel Company, to refuse to be a party to any project for financing the building contemplated, and to refuse from any motive to deal with the Hotel Company even if, as an incidental result of such refusal, that company broke its contract with the plaintiff. The judge in giving each of these and several somewhat similar requests qualified them by adding “unless the defendant in making such refusal had in mind the bringing about of a breach by The Chatham, Inc., of its contract with the plaintiff,” or by adding other words of like import. The effect of the qualifying words was to give the jury to understand that if the defendants’ motive in refusing to enter into contractual relations with the Hotel Company was to bring about a breach of the contract of that company with the plaintiff, such refusal would afford ground for liability.
A party not under contract with another has a right to refuse to enter into contractual relations with him, no matter what his motive for such refusal may be. “Every man has a right to determine what branch of business he will pursue, and to make his own contracts with whom he pleases and on the best terms he can .... He may refuse to deal with any man or class of men.” Carew v. Rutherford, 106 Mass. 1, 14. Commonwealth v. Hunt, 4 Met. 111, 133. Winchester v. Howard, 97 Mass. 303, 305. Heywood v. Tillson, 75 Maine, 225. McMaster v. Ford Motor Co. 122 S. C. 244. “It is the right, Tong-recognized’, of a trader engaged in an entirely private business, 'freely to exercise his own independent dis
It is evident from the foregoing authorities that the qualifying words appended by the trial judge to the defendants’ requests, interpreted as they must be to mean that the unexpressed motive of the defendants in refusing to enter into a second underwriting agreement with the Hotel Company might afford a ground for holding the defendants liable, were erroneous. After repeating these qualifying words several times the judge, in later instructions, stated to the jury in substance that if the defendants simply refused to finance, or assist in financing, the building project, but did nothing in the way of active solicitation or persuasion for the purpose of procuring the Hotel Company to break its contract with the plaintiff, the defendants would not be liable; that the plaintiff had the burden of proving the defendants guilty of active solicitation or persuasion calculated or intended to cause the Hotel Company to break its contract with the plaintiff; and that the plaintiff must prove that the defendants directly undertook to procure a breach of the contract and that it was not enough that such breach was brought about incidentally as the result of conduct of the defendants which was otherwise lawful.
In none of these later portions of the charge was the error which appeared in the qualifying words, to the effect that in the exercise of an absolute right unexpressed motive alone may make a party liable, specifically corrected, and it is impossible to know whether the jury based their verdict on the erroneous instructions referred to or on the more accurate statements of law which were thereafter given.
Exceptions sustained.