Appellee, Guy James Construction Co., brought this action for declaratory relief to determine the constitutionality of Title 61 O.S.1971, § 16.
The trial court based its holding primarily on the due process standard set forth in Fuentes v. Shevin,
This Court recently considered the Fuentes standard for procedural due process in Mobile Components, Inc. v. Layon,
Once it is determined that due process considerations attach, there remains the question of what constitutes due process in a given situation. Morrissey v. Brewer,
In the absence of extraordinary circumstances, certain procedural safeguards must be followed before a person is deprived of a significant property interest. Generally, he must be given notice of the creditor’s claim, and an opportunity to be heard before his property may be seized. However, if the interests of the creditor cannot be protected by allowing such pri- or notice and hearing, then there must be other procedural safeguards to sufficiently protect the property rights of the alleged debtor. Mobile, at 593, 594.
Applying this standard to Title 61 O.S.1971, § 16 it is apparent that the necessary safeguards are lacking.
First, it should be noted that this statute does not address an emergency situation. The claimant may claim against the contractor’s statutory payment bond pursuant to 61 O.S.1971, § 1 et seq., and additionally, the claimant has an equitable claim against money due and owing as recognized in Standard Accident Insurance Co. v. United States Casualty Co.,
Second, the statute contains no provisions for prior notice or hearing. The contractor first learns of the claim only after he receives a payment which reflects the withholding, and he is given no opportunity to contest the claim either before or after the money is withheld. The contractor is faced with two choices: he must either find the claimant on his own and settle the dispute or be deprived of his payment until trial of the issues in a court of law.
Third, even if it were the intention of the legislature that the interests of the materi-almen and laborers could not be adequately protected if prior notice and hearing were allowed, Title 61 O.S.1971, § 16 fails to establish alternative safeguards.
In addition to the grevious omissions concerning notice and hearing, the statute is fatally imprecise. The statute does not specify what information is required to file the claim nor does it require the claim to be verified in any way. The statute purports to require the claimant to post “statutory
Clearly, Title 61 O.S.1971, § 16 fails to meet the constitutional standard for procedural due process. This standard is meant to be flexible to allow protection of the rights of all parties involved. But in the absence of unusual circumstances, the statute must at a minimum provide for prior notice to the alleged debtor and a hearing appropriate to the nature of the case. The form of these safeguards is open to many possible variations, but they must be designed to establish the probable validity of the claim and to minimize the risk of wrongful withholding.
For the reasons stated herein, we affirm the holding of the trial court.
Notes
. Withholding of payment to contractors in default for labor or materials — Institution of legal action
Any person furnishing labor or materials for a public work who has not been paid therefor may file at any time prior to the expiration of twenty (20) days following the completion of a contract for public work a stop notice with the public agency concerned and thereby cause the withholding of payment to the contractor for the public work the amount claimed by such person. Any public agency receiving such notice shall mail a copy of this statute requiring action within twenty (20) days to the party making such claim. Any such person having no direct contractual relationship with the contractor, other than a person who performed actual labor for wages, may file such a notice, but no payment shall be withheld from any such contractor after the expiration of said twenty (20) days, unless the party making a claim shall have served the public agency with proof that he has instituted a legal action within such time to effectuate collection. Upon the filing of a legal action, the public agency shall withhold the amount claimed in the action, and pay the balance to the contractor. Failure by the claimant to comply with the requirements set out in this act and to post statutory guarantees shall release the public agency from the obligations imposed by the act.
. The mechanics’ and materialmen’s lien statutes in Title 42 O.S.1971, § 141 et seq., have not been construed to allow liens against public property, on the basis that such liens would be contrary to public policy and incapable of enforcement. Western Terra Cotta Co. v. Board of Education of City of Shawnee,
