84 N.W. 349 | N.D. | 1900
Action to foreclose a mechanic’s lien. A demurrer to the complaint upon the ground that it did not state facts sufficient to constitute a cause of action was sustained, and plaintiff appeals. The lien is sought to be imposed upon the building only, and for materials that entered into its construction. The defendant is the vendee of the party by whom the building was erected. No personal judgment is claimed, or, under the complaint, could be recovered, in this case, against any one. Unless the complaint entitles plaintiff to the foreclosure of the lien claimed, it cannot be sustained for any purpose. To entitle a party to a lien for materials furnished to be used in the construction of a building, such materials must be furnished pursuant to a contract with the owner of the land upon which the building is situate. Such is the clear requirement of section 4788, Rev. Codes. The complaint in this case alleges that at the time such materials were furnished the