42 Ind. 134 | Ind. | 1873
This was an appeal from a precept issued in favor of the appellant, under an order of the common council of the city of Lafayette, to enforce the payment of certain assessments in favor of appellant, as contractor, for the improvement of Kossuth street in said city.
The substance of such paragraph is, “ that said contract required the work to be completed on the first day of September, 1869, but that said work was not completed until, to wit, the 17th day of December, 1869, which was more than two months after the time required by said contract for the completion of said work; and defendant avers that by the terms of said contract, five per cent, per month should be deducted from said estimate and assessment against the property of said defendant, on account of said delay in the completion of said work, which deduction has not been made in said estimate and assessment; and the defendant avers that by reason of such delay, he has been greatly damaged thereby, in this, to wit, fifty dollars; and the said defendant says that said plaintiff ought not to have judgment for said assessment.”
That portion of the contract referred to in the above paragraph of the answer is as follows:
“ And it is further understood and agreed that if said party of the first part fails to complete said work within the time specified, and desires an extension of time to complete the same, such extension of time shall be granted only on condition that five per centum per month be deducted from the assessments of all work done after such extension* such deduction to operate for the benefit of the respective property holders in proportion to their assessments; and all damages arising on account of any failure on the part of the party of the first part to comply with the conditions of this contract shall be collected from the party of the first part, without any relief from valuation or appraisement laws.”
The contract, of which the clause above quoted is a part, was entered into between the appellant and the common council of the city of Lafayette. The appellee was not a
The court erred in overruling the demurrer to the third paragraph of the answer;
By the agreement of the parties, the cause was submitted to the court for trial; and the evidence being heard, the appellant asked the court to state the facts found in writing and the conclusions of law thereon by the court.
The facts so found and the conclusions of law thereon are as follows:
“ The improvement was finished, approved by the engineer, and accepted by the council, but the work was not done according to contract, in this: The timber of the sidewalks was not free from sap, and some (the number is not definite) of the cross pieces, to which the plank were nailed, were worm-eaten, having been sawed from dead timber. A part of the lumber which was brought to said improvement was rejected by the engineer, and was not used in the improvement; and the engineer testifies that he knew of no objectionable material being used, but the fact that some, in fact, a considerable amount (but hot a definite amount) of lumber with sap from one to two inches wide was used, is established. The contract is positive that the lumber ‘ must be free from sap.’ Had but a few pieces, but slightly injured
The appellant excepted to the conclusions of law drawn by the court upon the facts found.
The appellant moved the court for a new trial, upon written reasons filed, which motion war. overruled, and the appellant excepted.
Thereupon the appellant moved the court for a venire de novo, upon the ground that the findings of the court were imperfect and did not cover all the issues in the cause.
While such motion was pending, the following amendment to the special findings was made by the court:
“I find that the work has been done substantially according to contract, except as shown in the finding heretofore filed; that had the work been done as to the sidewalks according to the contract, the assessment would have been proper, and the precept properly issued. As the amount of lineal feet owned by the defendant and its proportion to the whole line of the street is correctly stated in the complaint, I find that the defendant’s property is in the city, and he is not entitled to damages as set up in his counter-claim.
‘‘John M. LaRue.”
To the making of which additional finding the appellant, at the time, objected and excepted.
After the filing of such amendment, the court overruled the motion for a venire ele novo, to which appellant excepted.
The appellant then moved the court for judgment in his favor upon the special findings, which motion was overruled, and appellant again excepted.
The next assignment of error calls in question the correctness of the ruling of the court in overruling the motion for a venire de novo.
It is very earnestly insisted by counsel for appellant, that in deciding upon this question, we can only look to the original special findings of the court, for the reason that the court, having made and filed his findings, possessed no power to make any addition thereto. We think the objection is untenable. We are unable to see any valid objection to the action of the court. The special finding of the court stands upon different grounds than the verdict of a jury, but even a jury, before its discharge, maybe required to correct and perfect the verdict or answers to interrogations. The same judge, ordinarily, presides during the entire term, and if he should, in the hurry of business, omit to find upon one of the issues, no injury can result in permitting him, during the term, to correct his finding.
But, conceding the right of the court to render the additional finding, it is maintained by counsel for appellant that he was, for two reasons, entitled to a venire de novo:
1. That the findings rendered are too vague, uncertain, and indefinite.
2. That the findings do not cover all the issues in the cause.
The court finds that the work was substantially done according to the contract, except the sidewalk. In our opinion, the defects in the sidewalks are not sufficiently pointed out to enable us to determine whether such work was done in substantial compliance with the contract.
It is found that some of the timber for the sidewalk'was not free from sap. Again, it is found that a considerable amount of lumber that was not free from sap was used in the construction of the sidewalk, and some of the cross-ties were worm-eaten. The court was required to find the facts, and not to write the testimony of the witnesses. The thing to be found was, what was proved, and not conjectures or
If the court had found the number of pieces of timber and lumber which were used that were not free from sap, and the number of cross-ties that were worm-eaten, we could determine whether there had been a substantial compliance with the contract. The finding is too uncertain and indefinite.
We proceed to inquire whether the findings cover and embrace all the issues in the cause.
What were the issues? They are plainly defined by the statute, as follows:
“And in case the court and jury shall find upon trial that the proceedings of said officers subsequent to said order directing the work to be done are regular, that a contract has been made, that the work has been done, in whole or in part, according to the contract, and that the estimate has been properly made thereon, then said court shall direct the property to be sold,” etc. 3 Ind. Stat. 102.
The special findings wholly fail to show whether or not the proceedings of the city officers, subsequent to the adoption of the order directing the work to be done were regular, and whether or not the estimate had been properly made on the work.
' It is also insisted by counsel for appellant that the court erred in finding as a conclusion of the law, that the acceptance of the work on behalf of the city authorities was only prima facie evidence that the work had been done in sub
The authorities referred, to do not support the position assumed. If the acceptance of the work by the authorities of the city is conclusive evidence that the work has been done according to contract, why is an appeal given to the property-holder from a precept ? and why does the statute provide that one of the questions to be tried on such appeal is, whether the work has been done, in whole or in part, according to the contract? The property-holders have no opportunity to be heard before the common council, and it would be manifestly unjust to hold them concluded, without being heard.
We are of opinion the court erred in overruling the motion for a venire de novo.
The judgment is reversed, with costs; and the causéis remanded, with directions to the court below, to grant the venire de novo, and for further proceedings in accordance with this opinion.