179 Mo. 38 | Mo. | 1903
— This is an action for two thousand dollars damages, alleged to have been caused to the premises, of the plaintiff, numbers 2734-2748, Chouteau avenue, in the city of St. Louis, and to the stock of furniture, goods, etc., therein, by an overflow of the Mill ■Creek sewer, on July 8, 1898. The plaintiff recovered judgment in the circuit court, for the amount claimed, ■and the defendant appealed.
The petition sets out the plaintiff’s ownership of the premises and personal property aforesaid’ and then alleges that the defendant constructed the Mill Creek sewer from Ohio avenue westwardly for several blocks under LaSalle street and Chouteau avenue, near the plaintiff’s property, and connected it with the portion of said sewer running eastwardly to the Mississippi river, and required property owners in the district to be drained thereby to connect with the same or its laterals, and that it thereby became bound to keep and maintain? the sewer in good order, so that plaintiff’s property would be free from danger or injury on account of said sewer or the use thereof; that the sewer was provided with openings, at or near the street crossings to admit and carry off surface waters.
The petition then contains the following statement ■of the plaintiff’s claim:
“The said Mill Creek sewer was constructed by defendant with a wooden bottom, composed of timbers and logs laid crosswise; and said defendant wholly neglected to keep same in proper repair, but carelessly, negligently and knowingly, permitted said timbers and logs to bulge and project up from the bottom of said sewer, which caused the sides and top of said sewer to crack and become displaced, and' placed and permitted large stones, a large iron wagon box and other articles to be and remain in said sewer in*46 places therein, between California and Montrose avenues, under said LaSalle street, which with the bulging and projection of said bottom as aforesaid, formed obstructions to the passage of the water and sewage which said sewer was designed and intended to carry off to said river, and caused said sewer in case of ordinary heavy rains, to ■ choke and dam up the flow through same and to back up the contents thereof out through said openings, flooding the streets and adjacent property for long distances, all of which was well known to defendant long; before the 8th day of July, A. D. 1898, or by the exercise of reasonable care and diligence would have been known by defendant.
“That the defendant prior to last-mentioned date and since the original construction of said Mill Creek sewer, extended said sewer and constructed a large number of public and district sewers and permitted a large number of private sewers to be constructed, and caused the same to be connected with, and empty into said Mill Creek sewer: and thus caused said Mill Creek sewer to-drain a large territory of over 6,500 acres of land, which was more than double the capacity of said sewer to carry off in case of ordinary heavy rainfalls, all of which was well known to defendant for several years before the 8th day of July, A. D.' 1898.
‘ ‘ That on many times before and more particularly, on or about the 8th day of July, A. D. 1897, plaintiff and others notified defendant, its officers, and agents, of the condition and insufficiency of said sewer, and damage and danger the same were causing and liable to cause to plaintiff’s property, and prayed an abatement thereof, which petition and prayer were ignored and no action taken thereon by defendant in anywise for plaintiff’s protection and relief. . .
“That on said 8th day of July, 1898, there was a heavy rainfall in said city, such as had previously frequently occurred, and by reason of said sewer being out.*47 of repair, and obstructed as aforesaid and by reason of the insufficiency of said sewer as aforesaid, the water and sewage in said sewer was backed and forced through said openings in such large quantities as to •flood the streets and force its way and come into and flood the plaintiff’s said property, greatly damaging and ruining same.’-’ etc.
The answer is a general denial, with the following special defense:
“Further answering, the defendant avers that Mill Creek sewer is, and for many years last past has been, a main public sewer of the city of St. Louis, and extends for a distance of five miles or more from a point in the western part of the city in a generally eastwardly direction to the Mississippi river, into which the water and sewerage of said sewer are discharged at a point a short distance south of Chouteau avenue. And defendant avers that said sewer is one of the largest sewers .in the world, and on July 7th and 8th, 1898, was a safe sewer and fully adapted to carry off all surface water, sewage and other- matter properly within said sewer, or which, according to the rules of experience in the building of sewers, could reasonably or properly be expected or anticipated; and said sewer was at said time well adapted for the uses for which it was constructed and maintained.
“The defendant avers that .on the 7th and 8th days of July, and especially on the night between said 7th and 8th days of July, 1898, there was a great and unusual, and extraordinary and unprecedented rainfall, and such' a rainfall as had never before occurred in said city of •St. Louis, and the rain water and surface water from the streets and ground rushed down the hills from the •higher ground to the low ground in which plaintiff’s premises were located and gathered in the streets and in said low ground near and about the said premises of plaintiff in such an unusual and unprecedented quantity that the said water formed a flood which flowed*48 along the streets and ran in upon the adjacent streets and ground in the neighborhood and upon the adjoining property. ’ ’
The trial developed the facts to be as follows:
Mill Creek sewer is one of the largest (if not the largest) and best constructed sewers in the world: It is a public sewer and runs along a natural watershed. It is substantially the original creek — called Mill Creek-converted into a sewer. It drains a large area — about 6,400 acres — just as the original creek did. The city began to construct it in 1864, and has extended the construction by sections, westwardly from time to time as the public revenues permitted. The last work of extension was completed in May, 1891, and the sewer as thus constructed begins at the west bank of the Mississippi river and extends westwardly for about five miles and ends at a point on Whittier street at a point 330 feet north, of Lindell avenue. The sewer is sixteen by twenty feet at its mouth and gradually diminishes in size until it is ten feet in diameter at its western terminus. Its drainage capacity is 3,340 cubic feet per second, in the portion near the plaintiff’s premises. It has a capacity for carrying off a rainfall of one inch an hour, which was the maximum capacity then required by experienced engineers throughout the country, and upon which basis the sewers óf other cities were built. Its cost was $1,-495,482.74. It was originally built by laying a bottom of timbers about a foot square and twenty-nine feet long, close together. The walls were four feet and eight inches thick and rested on the timbers. It had an arched top eight or ten feet in radius, and two feet thick. It was shown that the section of the sewer near the plaintiff’s premises was completed in 1.874 and 1875. Between November, 1881, and May, 1898, the city expended for the re-construction and repair of this sewer the sum of $227,328.77.
In the latter part of the year 1896 a crack and ‘ ‘ subsidence” was discovered in the sewer at Fourteenth and
The plaintiff’s premises were located at, perhaps, the lowest point of the area naturally drained by the Mill Creek, and later drained by this sewer. The testimony of persons who had lived in that neighborhood for over forty years was that before the sewer was constructed the land (including plaintiff’s premises) was overflowed by the creek many times. The testimony further shows that after the sewer was constructed there were three or four overflows, one was on a Sunday in May, 1897, another on the night of the cyclone in 1896, and the third on July 8, 1898. The date of the fourth is not disclosed.
The United States signal officer testified that the records of his office showed that the greatest rainfalls in St. Louis were as follows: On May 27,1896, the day of the great cyclone,, the fall was 2.23 inches, of which 1.33
It further appeared that on July 8, 1898, the sewer overflowed, the tops were lifted off the manholes, the water spouted up as much as ten feet into the air, the lowlands, including the plaintiff’s premises, were overflowed, the cellars of the houses were filled with water, and in some places the water stood several feet deep on thefirst floors of the houses, the streets were covered with water to a depth of from a few inches to waist deep, and the houses were damaged and the goods injured, and a deposit of filth and slime, which was very offensive to the smell and injurious to property, was left. The overflow lasted only a few hours after the rain ceased, and after that the usual conditions were restored, and-the sewer proved adequate to efficiently cany off the surface waters and the sewage, as was ordinarily the case.
At the close of the plaintiff’s case and again at the-close of the whole case, the defendant demurred to the evidence, but the court overruled the demurrer and the-defendant saved proper exceptions. In the view herein
I
The plaintiff predicates a right to recover upon two grounds: first, that the defendant was negligent in not keeping the sewer in repair, but permitted it to become racked, and the timbers on the bottom to bulge up, and allowed stones and other obstructions to accumulate in it so that its capacity was diminished; and, second, that the sewer was inadequate and insufficient to drain the territory connected with it, and therefore it overflowed.
The first ground is unsupported by any substantial evidence. The crack or “subsidence,” that is referred to in the evidence, occurred in 1896, nearly two years before the injury complained of, and was at Fourteenth and Gratiot streets, which is nearly fourteen blocks east of plaintiff’s premises, and was promptly remedied, as emergency work by the city, and was completed in April; 1898, about three months before the accident, and therefore had no possible bearing upon this case.
The testimony shows that some of the bottom timbers had bulged up from an inch to a foot, but all the experts called by both the plaintiff and the defendant, said that it had no appreciable effect upon the capacity of the sewer, and could not have caused the injury complained of. One of the plaintiff’s witnesses testified that he found a stone about two feet in diameter in the sewer, and that some sand and filth had banked around it. But no one pretended to say, for it would have been palpably absurd for any one to so say, that this had any effect upon this case, or that the accident would not have occurred if this stone had not been there, and the physical facts show that such effect of the stone was impossible.
Hence, no further attention need be given to the first ground relied upon by the plaintiff.
The learned counsel have devoted the bulk of their briefs and arguments, as they did most of their testimony, to a consideration of the sufficiency of the sewer to drain the territory connected with it, and to the question whether or not the city can be held liable if it failed to provide in the first place, a sewer of sufficient size, and capacity, and construction, to drain the area connected with it, and to enlarge such capacity from time to time so as to meet the increased burdens cast upon it by the building up of the city.
Counsel for the plaintiff showed by the reports of the sewer commissioner, and of the committee on sewers of the Board of Public Improvements, that this sewer needed enlarging, and that it had been many times overflowed, and they also showed that for more than two years before the date of this accident the city had been engaged in the construction of the Tower Grove storm sewer for the purpose of relieving the overburden on the Mill Creek sewer, but counsel contends that even that will not prove efficient, as only twenty-five per cent of the burden will be thereby removed, and counsel contends it is now overtaxed fifty per cent of its capacity. On the other hand, counsel for defendant show that in the seventeen years preceding the the accident, the city had expended upon the reconstruction and repair of this sewer $227,328.77. And they further show that the sewer is ordinarily competent to take care of all the demands upon it, and that it is only on occasions of violent and unusual storms like that that occurred on the occasion of the cyclone in 1896, and like the storm that occurred on the occasion here involved, July 8,1898, that there has been an overflow.
On the other hand, counsel for plaintiff contends that the city is liable if it fails to exercise ordinary care in the adoption of plans for a sewer, or in the construction of a sewer, which turns out to be insufficient to drain the territory connected with it, and cites cases in support of this contention.
Dillon on Municipal Corporations (4 Ed.), p. 1046, says the late cases properly tend to hold that the city is liable on the ground of negligence where the sewer is not of sufficient size, “under ordinary conditions,” to' drain the district connected with it, and in consequence overflow and injure private property.
These are interesting questions concerning which courts are disagreed. But it is not necessary or proper to consider or decide them in this case, because, in this case, there is no room for controversy that this sewer has always proved amply sufficient to meet the demands upon it under ordinary conditions, and that it is only in cases of unusual and extraordinary storms like that of May 27, 1896, when the cyclone visited St. Louis, and that of July 8, 1898, when there was a rainfall of 5.10
If, therefore, it be conceded for the sake of the argument, that the discretion of the city can be reviewed by a jury and the city be made liable for a failure to construct a sewer of sufficient size to meet the demands upon it under ordinary conditions, and even if it be likewise conceded that the city acts ministerially and not in its governmental capacity when it constructs its sewers, still the plaintiff would not be entitled to recover in this case, because this injury did not arise from any breach of its duty or from any municipal negligence under ordinary conditions, but it arose from the act of God, from an unusual and unprecedented storm which was the greatest of which there is any record known to the signal service.
This sewer was scientifically built, according to the best judgment of the engineers of the days when it was built, and with the maximum capacity then deemed necessary or proper, of one inch an hour, which the United States signal service says is excessively heavy. It has proved efficient and sufficient under ordinary conditions. On a few occasions when there were unusual, unanticipated and extraordinary floods, it has not been sufficient to carry off storm waters as fast as they fell, and the lowlands, where the plaintiff’s property is located, have been flooded. But while this is true, it is uncontradicted in. this case that these same low lands were overflowed on like occasions before this sewer was built and wnen the drainage afforded by nature was insufficient to carry off the extraordinary rainfalls. So that this is not a case where the sewer constructed by the city affords less efficient drainage than was afforded naturally, nor is it a case like Rychlicki v. St. Louis, 98 Mo. 497, where the city collected surface water into drains and projected it in bulk and not naturally upon a man’s lands.
This case falls within the rule laid down in Flori v. St. Louis, 69 Mo. 341, where the city was held not liable for damages produced by the fall of a market-house
To hold a municipality for damages in a case like this would be to make it prohibitory upon the city to construct sewers at all. For if the city could be held liable under circumstances like those present in this case, it would practically be to say that the city is an insurer against all damages that may arise in any manner whatever, the act of God included. If this was the law no city could afford to build or maintain a sewer at all. Drains would have to be left in their natural condition. And in this case the damage to the plaintiff would have been the same, according to the undisputed testimony in the case, if Mill Greek had never been converted into a sewer.
In Brash v. St. Louis, 161 Mo. l. c. 438, this court, speaking through Brace, J., quoted with approval the rule laid down in 1 Shearman & Eedf. on Neg. (5 Ed.), sec. 39, wherein it is said that if the negligence of the city concurs with a superior force, as the act of God, the city is liable, “but if the superior force would have produced the same damage whether the defendant had been negligent or not, his negligence is not deemed the cause of the injury.” And the learned judge added: “And this is the prevailing doctrine in this State,” and cited many cases in support thereof; concluding with the remark, “There is nothing in the rul
The plaintiff, however, invokes section 21 of article 2 of the Constitution, which provides “that private property shall not be taken or damaged for public use without just compensation,” etc.
This provision has no application to this ease. If the defendant could be held liable at all, it would be on the ground of negligence and not as for a taking or damaging of private property for public use. [Van De Vere v. Kansas City, 107 Mo. 83; Rude v. St. Louis, 93 Mo. 416.]
These considerations produce the conclusion that the plaintiff failed to make out a case against the city, and that the demurrers to the evidence should have been sustained. The judgment is reversed.