101 Minn. 116 | Minn. | 1907
The appellant and respondent, together with three other landowners, petitioned the board of county commissioners for the establishment of a public ditch under the provisions of chapter 358, p. 413, Laws 1901, and filed the petition with the auditor as required by law. For the
After consideration of the matter the county commissioners refused to establish the ditch, and from their action no appeal was taken. The expenses connected with the proceeding amounted to $540, which were paid by the county. Had the ditch been established, the benefits above damages to the persons who signed the bond would have been as follows : Gugisberg (appellant), on fifteen acres, $300; Eckert (respondent), on seventy seven acres, $1,540; Stadtherr, on fifty seven and a half acres, $1,150; Lager, on sixty acres, $1,200; Dahl, on thirteen acres, $235. The county, after paying the expenses, demanded from each of the signers of the bond the payment of the $540 in the proportion that his amount of benefit, had the ditch been established, bore to the total amount of benefits assessed against all of such persons. Thus estimated, the payments would have been: Eckert, $187.93; Gugisberg, $36.61; Stadtherr, $140.34; Lager, $146.44; Dahl, $28.68. Stadtherr, Lager, and Eckert refused to pay upon this basis, but later they and Dahl each paid $108, being one-fifth of the total, $540. After' these payments were made, Gugisberg also paid $108 under protest, and then brought this action against Eckert to recover $37.86 by way of contribution. Eckert, in his answer, alleged that his obligation to the county had been discharged, and denied any liability to the plaintiff. The court granted a motion by the defendant, for judgment on the pleadings, and the plaintiff appealed from the judgment entered thereon.
The bond which is called for by section 2, p. 413, c. 258, Taws 1901, is required for the protection of the county against the expenses which ■are necessarily incurred in the preliminary proceedings, which are necessary to determine whether the ditch shall be established. It is required to be signed by one or more of the petitioners; that is, of the landowners whose land will be affected by or assessed for the expenses of- constructing the ditch. Good and sufficient freehold sureties are required, but the sureties need not be persons whose land will be so affected. The bond in question was signed by five of the petitioners, all of whom were freeholders, who evidently could have qualified as ■sureties. It is not now material whether the signers of this bond are treated as principals or sureties. As between the county and the obligors, each was liable for the entire amount of the expense, and, had •either paid the entire amount, he could on general equitable principles have required his co-obligors to contribute his proportion. The general rule is that, where two or more persons are jointly, or jointly and severally, bound to pay a sum of money, and one or more of them pays the whole, or more than his or their share, and thereby relieves the others from their liability, those paying may recover from those not paying the aliquot proportion which they ought to pay. The persons not paying, but being relieved from a positive liability by a payment made by others, who were bound with them, are held to be under an implied promise to contribute each his share to make the whole sum paid. This rule applies equally to those who are bound as original co-contractors and to those who are bound to pay the debt of another or answer for his default as co-sureties. 1 Parsons, Cont. (5th Ed.) 31.
But the appellant is not satisfied with this rule, and claims that contribution should be made in proportion to the prospective benefits which would have resulted to the obligors if the petition had been granted and the ditch constructed. The right of contribution rests, not upon the original contract between the parties, but upon the relation created
Judgment affirmed.