Guerini Stone Co. v. P. J. Carlin Construction Co.Guerini Stone Co. v. P. J. Carlin Construction Co.
delivered the opinion of the court.
This case is before us for the second time, our former decision béing reported in
The controversy arose in the course of . the construction of a federal post office and court building at San Juan, Porto Rico. Plaintiff had a sub-contract for a part of the work under defendant, which was the general contractor under the Government of the United States, Pertinent clauses of the contract and a general history of the case were set forth in our former opinion and need not be repeated at length.
The evidence at the second trial followed the general lines of the first. Defendant was to construct the foundation complete to the basement floor. Upon this, plaintiff was to construct the principal part of the building, including exterior and interior walls, floors, and roof, to be built of concrete. For this work and the necessary mate- . rials defendant agreed to pay to plaintiff the sum of $64,750 in certain monthly instalments on account and the balance on completion. The plans called for certain granite work, for which defendant was to send the cut blocks from the-United States; and under an option set forth in paragraph 25, afterwards accepted by defendant, plaintiff was to set this granite for 40 cents per square foot of surface.
It appeared that after the work had been in progress for some time a disagreement arose between the parties about payments on account.-. Paragraph 12 of the contract provided that there should be “monthly payments on
In the month of February, 1912, the government superintendent of construction found a serious settlement in the foundation, as a result of which work upon the building was ordered to be stopped. This order was communicated verbally by defendant’s representative to . plaintiff’s agent at San Juan on the 9th of March, and was confirmed two days later by letter, in which, however, a request made by plaintiff’s agent for instructions as to what should be done with plaintiff’s force of men pending the suspension of the work was evaded. Plaintiff stopped work pursuant to defendant’s notice, and did nothing more upon the building.
Thus matters remained until May 22, 1912, plaintiff in the meantime having received no payment pursuant to its requisition of March 9 beyond the small sum mentioned above, nor any instructions or permission to pro
The principal ground of action was based upon the contention that in refusing to respond to plaintiff’s requisitions for payments on account, and in the complete and indefinite stoppage of plaintiff’s work under the circumstances mentioned, defendant had committed breaches of the contract so material as to amount to a total breach, justifying plaintiff in declining to proceed further and in suing at once for its damages. See
Anvil Mining Co.
v.
Humble,
The Circuit Court of Appeals attributed error to the trial court in the following respects:
It is sufficiently obvious that a contract for the construction of a building, even in the absence of an express stipulation upon the subject, implies as an essential condition that a site shall be furnished upon which the structure may be erected. In this case the matter was not allowed to rest upon an implication, for, as we held in our former opinion, the 11th paragraph of the sub-con- >• tract, providing: “The general contractors wifi provide all labor and materials not included in this contract in such manner as not to delay the material progress of the work, and in the event of failure so to do, thereby causing loss to the sub-contractor, agree that they will reimburse the sub-contractor for such loss,” as applied to the facts of the case, imported an agreement by defendant to furnish the foundation in such manner that plaintiff might build upon it without delay, and was inconsistent with an implication that the parties intended that delays attributable to the action of the owner should leave plaintiff remediless; and defendant’s obligation to furnish a suitable foundation was not dependent on whether it was at fault or whether the delay was attributable to a stoppage of work by the owner in the exercise of a right con
The Circuit Court of Appeals, howeyer, held (241 Fed. Rep. 549) that although under paragraph 11 defendant would be liable to respond in damages for süch delays if plaintiff completed or stood ready, to complete its contract, yet it did not follow that if plaintiff was delayed in completing its work within the 300 days specified in paragraph 6 it could decline to go on, since by paragraph 7 it was provided that should the sub-contractor be obstructed or delayed in the prosecution or completion of the work by neglect, delay, or default of the owner (among other causes), the time fixed for the completion of the work should be extended for a period equivalent to the time lost from such causes. The court held that this rendered it clear that delays occasioned to the plaintiff by the owner, the general contractor, etc., were not to ■excuse plaintiff from proceeding to complete the Contract, but were to operate merely as an extension of the 4ime within which by the terms of the contract plaintiff was required to perform its work. In our opinion there was error in holding that the- provisions of the 6th and 7th paragraphs limited, thus, the provisions of the 11th. From the fact that by paragraph 6 plaintiff was obliged to finish the work in 300 days, and by paragraph 7 this time was extended for plaintiff’s benefit in the case of delays caused by the owner, the general contractor, or otherwise, as specified, it does not follow that plaintiff was not entitled to finish the work more speedily if it could do so; of that a breach of paragraph 11 by defendant, so serious as to result in a total suspension of the work, with no reasonable prospect that it could be. resumed within any reasonable time, left plaintiff still under an obligation to hold itself in readiness to proceed, and without remedy except an action for damages under that paragraph.
The opinion of the Circuit Court of Appeals (241 Fed. Rep. 550) shows, that counsel for plaintiff in that court stated that the quantum meruit had been disregarded, and that the trial proceeded solely upon the ground of a breach of the special contract; but the bill of exceptions fails to bear this out, and error can not be attributed to the trial court on that theory. There was no waiver of the general claim for materials, and the evidence referred to furnished a ground of recovery upon that" claim, irrespective of plaintiff’s right to recover damages for breach of the special contract.
But. upon the latter question also it was admissible,
The Circuit Court of Appeal^ considered that the furnishing of the. materials in question was a matter so entirely outside of the contract that it could not properly be considered as an element of damage for its breach, and that plaintiff’s remedy to recover their value must be by action of tort for conversion. But the evidence showed no tortious conversion: it tended to show that the articles were appropriated by defendant with plaintiff’s consent; and it hardly is necessary to say that, if tort there were, plaintiff could waive it and sue upon the implied ássump-sit.
Great Falls Mfg. Co.
v.
Attorney General,
Nor was this a matter entirely outside of the contract. The materials in question consisted in the main of tools and appliances that had been brought to the building by plaintiff for use in the performance of the contract, were so used, presumably were fitted for further use on the building, and upon the interruption of the work were left in position in the control of defendant and ready to be employed by it whenever it should proceed with the
(3) The next ground of error upon which the Circuit Court of Appeals based its decision was an instruction given to the jury, in substance, that if defendant failed to make payments on account as called for by the contract, — “a substantial failure, amounting substantially to the withholding of the whole payment, not necessarily the whole payment, but the bulk of the.payment”— such failure constituted a breach on the part of defendant justifying plaintiff in stopping work and entitling it to recover damages from defendant; and the refusal of a requested instruction to the effect that "The delay of defendant to make payments on estimates, in the absence of a positive refusal to pay anything, was not ground for a rescission or termination of the contract by plaintiff,” and that plaintiff’s remedy was to recover interest on the deferred payments.
The Circuit Court of Appeals very properly held that in a building or construction contract like the one in question, calling for the performing of labor and furnishing of materials covering a long period of time and involving large expenditures, a stipulation for payments on account to be made from time to time during the progress of the work must be deemed so material that a substantial failure to pay would justify the contractor in declining to proceed. In addition to the provisions of paragraph 12,. already referred to, the concluding paragraph of the contract was as follows: “And the said general contractors hereby promise and agree with the said sub-contractor to employ, and do hereby employ him to provide the materials and to do the said work according to the terms
But it was held that defendant’s refusal to pay was justified because plaintiff’s requisitions were not made out in accordance with the provisions of the contract.' There were but two requisitions in evidence, one dated December 30, 1911, the other March 9, 1912. Both were held defective, in'that they included not only 85 per cent, of the estimated amount of the concrete construction, which was the principal subject-matter of plaintiff’s contract, but also a like percentage of the amount earned in setting granite under the accepted option in paragraph 25. The court held that the provision for monthly instalments related only to the former, and that as to the granite work plaintiff was not entitled to payments on account in advance of its completion. In our opinion, however defendant’s acceptance of the option to call upon plaintiff to set the granite blocks did not make a separate contract, but merely added something to the work that plaintiff was to do under the contract previously made; and by necessary inference it subjected the granite setting to the appropriate general provisions respecting the method of performance and the time when the work was to be paid' for.
Were it otherwise, the requisition of March 9 could not be rejected merely on the ground that it called for a pay
(4) The court held the requisition of March 9 to be defective upon the further ground that it was based upon the unit price of $1.07 per cubic foot, pursuant to the understanding said to have been arrived at between the parties on February 2, instead of the actual cost of the; work erected in the building as required by paragraph 12 of the contract. It was held that since the complaint alleged that plaintiff’s demands for payment were made “in accordance with the terms of the contract,” evidence to show the agreement made on February 2 about unit prices was not admissible without an amendment of the complaint setting up a modification of the contract.'
This view cannot be upheld. The allegation quoted from the complaint did but touch upon the performance of a condition precedent, concerning which the former niceties of pleading no longer obtain. And besides, evidence of the agreement of February 2 about unit prices was introduced at the first trial and was particularly referred to in our opinion reviewing it (
(5) The final ground upon which the reversal was rested was an instruction given by the trial court to the jury upon the question of damages in the following terms: “If you find he [meaning plaintiff] was justified in terminating the contract as he did on May 22 upon the principles above given you, you can consider the reasonable expenditures incurred by the plaintiff, the unavoidable losses incident to stoppage, .the amount of work actually performed, the amount plaintiff was actually entitled to by reason of such work at. the contract price, and the profits which plaintiff -could have made if allowed to com- . píete the. work under the contract. So the different items that you may, if you come to the question, take into account, are the outlays less the material on hand, the amount of work actually performed and the profits, if you find there were any which were not speculative. The measure of profits is the contract price less what is shown to you as the expense of carrying out the contract, if that is shown to you to your satisfaction.” The appellate-court held this instruction to be misleading because it embodied a duplication of elements. Respecting this a difficult question would be presented if defendant were
At the second trial this part of the charge was given by the court of its own motion, not at plaintiff’s request; nor was it excepted to by defendant. The statement of the Circuit Court of Appeals to the contrary (241 Fed. Rep. 555) is not borne out by the record. The proposition criticized is not contained in any of the instructions requested by plaintiff; and even had it been requested there is no exception touching it unless it be the following:
“I
will ask on behalf of the defendant an exception '. . . to the action of his Honor . . . in giving all instructions requested by plaintiff.” This is altogether too general to be regarded as directing the mind of the trial court to any single, and precise point of alleged error so as to call for a reconsideration of the ruling, and hence could not furnish a basis for reversing the judgment. That an exception must.be specific need not be emphasized.
McDermott
v.
Severe,
There was another exception, couched in these terms: “To that part of the charge to the effect that if the plaintiff had the right to terminate the contract under the authority of the
•Behan case,
the measure of damages would be not only the expenses incurred by the plaintiff, but also reasonable profits.” This, however, refers to another passage in which the trial court quoted from the headnote in
Having found that none of the grounds relied upon by the Circuit Court of Appeals for reversal of the judgment of the trial court is tenable, it remains to consider what judgment ought to have been rendered upon the record and bill of exceptions, in view of the assignments of error other than those we have thus far considered.
United States
v.
U. S. Fidelity Co.,
Judgment of the Circuit Court of Appeals reversed, and that of the District Court affirmed.