*1 GRYNBERG, Jack Jack d/b/a Associates, Plaintiff-Appellee Cross-Appellant, al., Defendants-Ap- ROBERTS,
Victor et
pellants Cross-Appellees.
No. 15007.
Supreme New Mexico. Court of
April
561
Expenditures.”
“Authorization For
signed
1974 each defendant had
such an
agreement for each of the six wells in-
volved in this suit. Each authorization
agreement listed for each well the estimat-
“intangible drilling
ed dollar amounts for
costs,”
costs,”
“tangible completion
and
“intangible completion costs”. Additional-
agreements recorded each defend-
ly, the
specific percentage
working
inter-
ant’s
proportion-
separate
est and his
estimated
well.
ate total cost for that
against
working
A claim of lien
the
against every
filed
est
each well was
by Grynberg in 1977. At that
defendant
for each
Grynberg
time
filed a document
date,
listing
defendant
the
invoice number
owed
each
and amount of indebtedness
on each invoice. Included was
defendant
to date” on each
the amount of “interest
(cid:127)
total indebtedness. These doc-
defendant’s
period from 1974 to
uments covered a time
Jr.,
Behles,
Martin,
Carls-
Martin &
W.T.
portion
A
of the 1974-1975 cost was
bad,
defendants-appellants and cross-
for
defendants and was
paid by certain of the
appellees.
summary.
not included in the 1977 debt
Kirk, Albuquerque, Chad Dick-
James E.
case,
complaint in the instant
In his
erson, Artesia,
plaintiff-appellee and
requested “reasonable interest”
Grynberg
cross-appellant.
alleged
drilling
operation
and
costs he
on
Find-
were owed to him the defendants.
OPINION
Gryn-
ings by the trial court showed
SOSA, Senior Justice.
berg
required
pay twenty percent
to
appeals
Plaintiff
from a failure
to cov-
interest on the amount he borrowed
prejudgment
interest
trial court to award
However, the
er the defendant’s costs.
Plaintiff
in a suit for breach of contract.
found it could not allow
court
several other
Grynberg sued Roberts and
on monies bor-
reimbursement for interest
agreement
of an
defendants for breach
Grynberg submitted no evi-
rowed because
cost to drill
pay proportionate shares of the
the amounts or
dence whatsoever as to
The trial
operate certain oil wells.
borrowed, or the actu-
sums were
dates the
granted judgment Grynberg
on the
court
covering
costs.
paid in
these
al interest
indebtedness,
principal
failed to award
but
Gryn-
ascertained and awarded
The court
interest” on the
requested
“reasonable
him
of monies owed to
berg exact sums
We reverse on that is-
principal awarded.
individually under each
each defendant
sue.
agreement,
no interest.
but awarded
question
appeal
is whether
The sole
prejudg-
Grynberg claims he is due
should attend
interest
him,
on the amount awarded
ment interest
Grynberg.
the amount awarded
money
had use of that
since he has not
owing
initially due and
from the time it was
that since 1975 the
The trial court found
Grynberg did not seek
present.
paid
share of the
defendants had not
their
paid
for the actual
their
reimbursement
drilling
operational costs under
Citing to
money
borrowed.
agreement
agreements.
In evidence were
Shaeffer
Kelton,
619 P.2d
parties,
titled
forms entered into
56-8-3,
forerunner,
he
trial court erred
not
tion
asserts that the
its
statutory
awarding
50-6-3,
interest allowed on
Section
allow prejudgment
a contract under NMSA
due on
certain instances. O’Meara and
(Orig.Pamp.
Section
and Cum.
adopted
stated in Re-
56-8-3,
Supp.1984).
governing the
Section
(1932):
statement
provides:
contract
interest rate on a
parties
If the
not
have
*3
interest,
The
in the
of
rate of
absence
otherwise, simple
determined
at
rate,
fixing
a written contract
a different
statutory legal
the
is
rate
as
recoverable
percent
shall
than
be not more
fifteen
damages
of
for breach
contract as fol-
annually
following
in
cases:
the
lows:
contract;
money
A. on
due
(a) where the defendant
a
commits
money
B. on
received to the use of
pay
breach of a
to
contract
a definite
another and retained without the owner’s
of money,
perform-
sum
or to render a
expressed
implied;
consent
or
the
ance
value of
in
is
money
which
money
upon
C. on
due
the settlement
in the
or
stated
contract
is ascertainable
day
of matured
from
the
accounts
the
by mathematical calculation from a stan-
balance is ascertained.
dard fixed in the
or
contract
from estab-
§
1978,
(Cum.Supp.1984).
NMSA
56-8-3
prices
subject
lished market
mat-
Previously,
provided
ter,
this statute
an
interest is
on the
allowed
amount of
percent.
1978,
est
rate of six
NMSA
debt money
the
or
from
value
the time
§
(Orig.Pamp.).
due,
56-8-3
performance was
after making all
the deductions to which the defendant
The facts in
are similar
those
Shaeffer
may be entitled.
in the instant case. There the defendant
buyer breached a construction contract.
In
This
recognized
court
in Shaeffer
Shaeffer, a
in which two members of
case
that under both the common law and
panel
this
we
participated,
stated
be-
1978,
56-8-3,
NMSA
Section
where the
cause
plaintiff
of the debt owed the
the
amount of
under the
indebtedness
contract
defendant, plaintiff was
to dis-
unable
breaching
is ascertainable
party,
the
charge a construction loan and:
injured party
the
is entitled to interest
aas
[plaintiff]
been
has also
forced make
right
of
matter
monies at the
those
* * * In
costly
payments.
addi-
rate.
tion, he
earning
has lost the use and
§
adopting
337(a),
In
Restatement
power
$17,000
of
of his own funds used
when the
indicated that
amount
Shaeffer
project. Simple
to finance the
interest is
owed is
a
“ascertainable
mathematical
estimating
allowed as a means of
these
calculation from a standard fixed in the
probable gains
compensation
and as
from established market
prevention.
their
prices,”
applicable.
Section
is
95
187,
563
ex-
interest could not
claimed as
agreements stated the
While
be
a
well. The
each
right in
express
matter of
absence of an
working interest and
percentage of the
act
law,
agreement
early
at
common
accord-
defendant
percentage of costs each
ing
viewpoint,
to the modern
there are
Secondly,
the documents
would owe.
many circumstances
interest can
where
listed
filed with the court
so claimed. 45
be
Am.Jur.2d Interest
numbers,
dates,
exact amounts due
invoice
Usury
amount due for
per invoice and the total
defendant.
each
(Emphasis
STOWERS, J., dissenting. STOWERS, Justice, dissenting.
I dissent.
An award of interest is not
appropriate in this case. IRVINE, Petitioner, James Scott The facts in this case show that defendants did not a pay breach contract to a definite sum of money, or to render a HOSPITAL, INC., ST. JOSEPH Marvin Sachs, Doyle Simmons, M.D., performance value of which is H.J. Mur- rell, M.D., X-Ray Associates, P.A., stated in the is ascertainable Respondents. mathematical calculation from a standard fixed the contract or from prices market No. 15663. subject matter. See Restatement of Supreme Court of New Mexico. § 337(a) (1932). The defendants April 16, 1985. chargeable are not with interest on a sum unless the amount is fixed the contract
or the defendants could have determined
*5
the amount with
certainty
reasonable
Steven E. Schonberg,
Livingston,
Paul
proper
(Sec-
make a
tender. Restatement
P.C.,
Schonberg,
Steven E.
Louis S. Mar-
ond)
Contracts
354 comment c
jon,
Albuquerque,
petitioner.
for
agreements
The trial court found
between
Civerolo,
Butkus,
Richard C.
Carl J.
Civ-
parties
agree:
and the terms of those
erolo,
Wolf, P.A.,
Hansen &
Albuquerque,
ments based on written estimates of costs
respondent
for
Joseph Hospital.
St.
expenses,
correspondence, verbal
Casados,
J.E.
Kelly, Gallagher
Ellen M.
understandings, and the actions and con-
Casados, P.C., Albuquerque,
&
for Marvin
parties.
duct of the
The terms of the
Sachs.
agreements and the amounts due under
Lasater, Jr.,
W. Robert
Mark C. Meier-
those terms were not
prior
determinable
Dickason, Sloan,
ing, Rodey,
Robb,
Akin &
the trial court’s
agree-
construction of the
P.A., Albuquerque,
Doyle Simmons,
for
Thus,
ments.
the amounts owed
Murrell,
M.D. and H.J.
M.D.
defendants
were not ascertainable math-
Black, Campbell,
Black,
Bruce D.
Byrd &
ematical
prior
judgment
calculation
P.A.,
Fe,
Associates,
X-Ray
Santa
for
Inc.
of the trial court.
Kennedy
See
v. Mou-
tray, 91 N.M.
