226 Pa. 345 | Pa. | 1910
Opinion by
The plaintiff’s son was a structural iron worker in the employ of the defendant, a contractor engaged in building a blast furnace for the Cambria Steel Company. He was killed by the falling of a swinging scaffold on which he was working at the top of the furnace, eighty-five feet from the ground. It was customary to suspend scaffolds by ropes, and the scaffold in use had been suspended by ropes provided by the defendant, but because of the danger of the ropes.being worn and weakened by the edge of the steel structure at the top of the furnace, John Shipman, who had charge of the work, decided that steel hangers should be used in place of ropes or in addition thereto. He directed a blacksmith in the employ of the defendant to go to the open-hearth department of the steel company and get steel rods and make hangers. All the steel in this department was brittle and unsuited for making hangers. No test was made of the rods, nor was any inquiry made as to the quality of the steel. There was testimony that the rods were of insufficient thickness. The accident was caused by the breaking of one of the hangers. Shipman had been in charge of the work nearly two years; he hired and discharged the men and had full supervision and control of the work. He was supplied by the defendant with materials and appliances necessary in carrying on the work, and he had
The question whether under the testimony Shipman was a vice principal or a fellow workman was submitted to the jury with full and accurate instructions, to which no exceptions were taken. The appellant’s contention is that there was not sufficient evidence to sustain the finding of the jury that he was a vice principal, and that in selecting material for building the scaffold, outside of that provided, he was merely a fellow workman, for whose' error in judgment the employer was not liable. This contention cannot be sustained. There was ample evidence to sustain a finding that Shipman had been placed in entire charge of a distinct branch of the defendant’s business, not merely to superintend it but to control it, with no one else to exercise any discretion or oversight. Moreover, in building the scaffold he was providing a place to work, and in so doing he was charged with the duty of his employer, which could not be delegated so as to relieve from liability for its improper performance. The case was not, as in Ross v. Walker, 139 Pa. 42, and Staebler v. Warren-Ehret Co., 223 Pa. 129, a case in which the employer had furnished material ample in quantity and quality for doing the work. Shipman had been directed to procure the material for the scaffold from the steel company, and in doing this he was charged with the performance of his employer’s duty and was vested with a discretion as to what was necessary,, which it could not delegate except at its peril. The case cannot be distinguished in principle from the recent case of Carr v. Gen. Fire Extinguisher Co., 224 Pa. 346, in which a corporation was held liable for the action of a foreman who had instructions to draw on the company’s storehouse for supplies of tools and appliances, but procured a defective ladder elsewhere in the use of which a workman was injured.
It is argued that in the absence of proof of the plaintiff’s age, there was no evidence from which the jury could determine the proper measure of damages. Her age should have
The judgment is affirmed.