Grove Isle Association, Inc., Appellant, vs. Jerry M. Lindzon, Appellee.
No. 3D22-913
Third District Court of Appeal State of Florida
November 10, 2022
Lower Tribunal No. 20-15859
Before EMAS, LINDSEY and GORDO, JJ. EMAS, J.
An Appeal from a non-final order from the Circuit Court for Miami-Dade County, David C. Miller, Judge.
Law Offices of Geoffrey B. Marks, and Geoffrey B. Marks, for appellant.
Halpern Rodriguez, LLP, and Priscilla S. Zaldivar and Marc A. Halpern, for appellee.
INTRODUCTION
Grove Isle Association, Inc. (the Association), appeals a nonfinal order granting Jerry M. Lindzon‘s motion for leave to amend his complaint to assert a claim for punitive damages.1 Because Lindzon failed to satisfy the requirements for establishing entitlement to assert a claim for punitive damages against a corporation pursuant to
FACTUAL AND PROCEDURAL BACKGROUND
Lindzon owns a unit at Grove Isle Condominium. He alleges his unit suffered severe water damage due to a failing roof assembly. After the Association allegedly ignored his complaints about the failing roof, Lindzon sued the Association for violation of the Declaration of Condominium and under
The roof was repaired during the pending litigation. However, when Lindzon began to repair the damage to his own unit, his contractor discovered exposed rebar. This discovery, and the parties’ attempt to address the newly discovered damage, led to the underlying motion to amend the complaint to assert a claim for punitive damages. In his amended complaint, Lindzon added counts for negligence and fraudulent misrepresentation, and sought punitive damages. He also described the following sequence of events:
- The reroofing project began in March 2021, after the underlying lawsuit was filed.
- In October 2021, the re-roofing project was completed, and Lindzon hired a contractor to restore his unit.
- In November 2021, Lindzon‘s contractor “discovered multiple areas on the common element slab surrounding the Unit with exposed, rusted rebar, spalling and cracked concrete.” Lindzon twice notified the Association about specific areas of damage to the concrete slab, and each time “the Association inspected the Unit.”
- “On January 31, 2022, the Association‘s own contractor confirmed that the work to be performed by the Association include[d] repairs to rebar which require[d] input from a structural engineer and proper permitting.”
- Rodriguez eventually advised Lindzon that work on the slab was set to commence on February 7.
- Days before the work was set to commence, Lindzon requested a copy of the scope of work and permit information. Upon receiving the request, Rodriguez stated: “[i]t‘s such
a small job that I don‘t think it‘s [permits] really necessary.” - When Lindzon insisted on a copy of the scope of work and permit information, Rodriguez canceled the work, stating that “he instructed his contractor to proceed without a permit, and now that Lindzon requested it, the repairs would be significantly delayed.”2
In sum—and relevant to the asserted punitive damages claim—Lindzon alleged: “In an effort to save money, the Association was not intending to retain a structural engineer or pull the necessary permits to perform the repairs to the slab contrary to the advice of the Association‘s own contractor.”
Attached to the motion to amend were the letters to the Association, and the correspondence between the Association contractor and Rodriguez.
Following a hearing, the trial court granted Lindzon‘s motion to amend, concluding that “the proffered misrepresentation regarding the lack of need for a building permit, the willful neglect to get a building permit in the face of expert advice to do [so] evidences a willful and wanton disregard of the Plaintiff[‘]s rights and safety.” This appeal followed.
STANDARD OF REVIEW
The parties agree that our standard of review is de novo. Tallahassee Mem‘l Healthcare, Inc. v. Dukes, 272 So. 3d 824 (Fla. 1st DCA 2019) (reviewing de novo the trial court‘s decision of whether a party should be allowed to plead punitive damages); Est. of Williams ex rel. Williams v. Tandem Health Care of Fla., Inc., 899 So. 2d 369, 376 (Fla. 1st DCA 2005). See also E.R. Truck & Equip. Corp. v. Gomont, 300 So. 3d 1230 (Fla. 3d DCA 2020) (Scales, J. concurring).
DISCUSSION AND ANALYSIS
The Association contends that (1) Lindzon “failed to meet the requirements of alleging and proving entitlement to pleading a claim for punitive damages against a corporation“; and (2) because the amended complaint does not allege acts independent of its contractual and statutory claims, amendment to the complaint was barred by the independent tort doctrine. We agree with the Association‘s first contention and reverse the order granting leave to amend to assert a claim for punitive damages.3
“Under Florida law, the purpose of punitive damages is not to further compensate
Florida courts have repeatedly described the substantial impact of granting a motion for leave to amend to assert a claim for punitive damages. See, e.g., TRG Desert Inn Venture, Ltd. v. Berezovsky, 194 So. 3d 516, 520 n.5 (Fla. 3d DCA 2016) (“From a practical perspective, the granting of a motion for leave to amend a complaint to add a punitive damages claim can be a ‘game changer’ in litigation.“) For instance, once a plaintiff is allowed to proceed with his punitive damages claim, the defendant becomes subject to financial discovery and, potentially, to uninsured losses. Id.; see also Est. of Despain v. Avante Grp., Inc., 900 So. 2d 637, 641 (Fla. 5th DCA 2005) (“[A]lthough section 768.72(1) is procedural in nature, it also provides a substantive right to parties not to be subjected to a punitive damage claim and attendant discovery of financial worth until the requisite showing under the statute has been made to the trial court“.) For these reasons, “punitive damages are reserved for truly culpable behavior and are intended to express society‘s collective outrage.” KIS Grp., LLC v. Moquin, 263 So. 3d 63, 65-66 (Fla. 4th DCA 2019) (quotation omitted).
(a) “Intentional misconduct” means that the defendant had actual knowledge of the wrongfulness of the conduct and the high probability that injury or damage to the claimant would result and, despite that knowledge, intentionally pursued that course of conduct, resulting in injury or damage.
(b) “Gross negligence” means that the defendant‘s conduct was so reckless or wanting in care that it constituted a conscious disregard or indifference to the life, safety, or rights of persons exposed to such conduct.
Here, Lindzon sues only the Association; Rodriguez is not a defendant in the action. Coronado Condo. Ass‘n, Inc. v. La Corte, 103 So. 3d 239, 240 n.1 (Fla. 3d DCA 2012) (“La Corte did not sue the individual property managers or the contractor repairing the balconies; the Association is the sole defendant.“) Therefore, in seeking punitive damages, Lindzon necessarily intends to impute the property manager‘s alleged intentional misconduct or gross negligence to the Association. To impute an employee‘s negligence or misconduct to the employer under the punitive damages statute, a plaintiff must establish the employee‘s conduct meets the criteria specified in subsection (2) above (i.e., that the employee was “guilty of intentional misconduct or gross negligence“) and establish one of the following:
(a) The employer, principal, corporation, or other legal entity actively and knowingly participated in such conduct;
(b) The officers, directors, or managers of the employer, principal, corporation, or other legal entity knowingly condoned, ratified, or consented to such conduct; or
(c) The employer, principal, corporation, or other legal entity engaged in conduct that constituted gross negligence and that contributed to the loss, damages, or injury suffered by the claimant.
Lindzon‘s amended complaint fails to satisfy any of the three alternative requirements of
(Fla. 3d DCA 2017) (“The plaintiffs assume that the alleged misconduct of the individual construction managers, superintendents, construction workers—who were not, on the record before us, officers or managing members of the limited liability companies—is, without more, misconduct of the four corporate petitioner/defendants for purposes of section 768.72. But that is contrary to the plain language of the statute“) (emphasis added); La Corte, 103 So. 3d at 240-41 (holding that the third amended complaint failed to comply with the procedural requirements of
CONCLUSION
Because Lindzon failed to satisfy the requirements for establishing entitlement to assert a claim for punitive damages against a corporation pursuant to
