Opinion
In this appeal we decide that a materialman must name all parties intended to be bound by an action to foreclose a mechanic’s lien within the time specified in Civil Code section 3144. 1 If the materialman does not have actual knowledge of a junior lienor’s interest in the property, the materialman can, however, satisfy the requirements of section 3144 by naming the junior lienor as a Doe defendant.
Grinnell Fire Protection Systems Company, Inc. (Grinnell), acting as a general contractor, performed work on a project called Seaport Village North (Seaport) in Redwood City. Grinnell began working on Seaport on or about October 24, 1980. Respondent, American Savings and Loan Association (sued under its former name, State Savings and Loan Association (State Savings)), recorded a deed of trust against the Seaport property on April 21, 1981. On August 13, 1981, Grinnell recorded a mechanic’s lien against Seaport because it had not been paid for the improvements it had made on the property. Grinnell moved to foreclose its mechanic’s lien on November 6, 1981. It named as defendants Ron Safren, George Safren, Safren Development Company, Seaport, and other Doe defendants who “claim some right, title, or interest in or to the said real property and Work of Improvement, which claims are junior and subordinate to the claim of [Grinnell].” It recorded a notice of pendency of action (a lis pendens) on the same day. The lis pendens gave notice that an action had been commenced to foreclose Grinnell’s mechanic’s lien. At the time Grinnell filed and recorded these documents, it had no actual knowledge that State Savings was the beneficiary of a deed of trust on the Seaport property.
On October 25, 1982, Grinnell gained actual knowledge of State Savings’ interest in the Seaport property, and it substituted State Savings as the party previously designated as Doe 2 in the complaint. State Savings purchased the Seaport property at a foreclosure sale in November of 1982. State Savings was served with the complaint on December 29, 1982. On November 15, 1984, State Savings moved for summary judgment on the ground that Grinnell’s foreclosure action was untimely because Grinnell had failed to name State Savings within 90 days of filing its mechanics’ lien against Seaport *355 as required by section 3144. Judgment was entered for State Savings, and this appeal follows.
Grinnell claims that it complied with the requirements of section 3144 when it commenced a foreclosure action naming the owners of the property within 90 days after recording the mechanic’s lien. It asserts that it could properly amend the foreclosure complaint to name a junior lienor, such as State Savings, as a Doe defendant when it gained actual knowledge of its interest in the property. We agree and reverse the judgment entered for State Savings.
I
The California mechanics’ lien derives from article XIV, section 3 of the California Constitution. The liens of mechanics, artisans, and materialmen are favored in California law . . because those parties have, at least in part, created the very property upon which the lien attaches ....’”
(Connolly Development, Inc.
v.
Superior Court
(1976)
This lien will, however, terminate unless the materialman brings an action to foreclose on the lien within 90 days after recording it. “No lien provided for in this chapter binds any property for a longer period of time than 90 days after the recording of the claim of lien, unless within that time an action to foreclose the lien is commenced in a proper court. . . .” (§ 3144.) Grinnell points out that the statute does not expressly require that all parties claiming some right, title or interest in the property be joined within the 90-day period, and argues that it satisfied the statutory requirements by filing the action within the 90-day period, and by joining all interested parties in the suit prior to judgment. State Savings counters that Grinnell’s interpretation of the statutory requirements is incorrect, and would, under
*356
the Supreme Court’s holding in
Connolly Development, Inc.
v.
Superior Court, supra,
Connolly Development, Inc. (Connolly) was the owner and developer of a shopping center. Connolly obtained a construction loan through Union Bank, and contracted to obtain materials for the improvement of the shopping center from Diamond International Corporation (Diamond). Diamond subsequently recorded a mechanics’ lien on the shopping center, and filed a bonded stop notice with Union Bank. Connolly and Union Bank challenged Diamond’s action to foreclose its mechanics’ lien on the ground that the mechanics’ lien and the stop notice violated procedural due process requirements.
(Connolly Development, Inc.
v.
Superior Court, supra,
The Supreme Court concluded that the imposition of a mechanics’ lien was a taking within the meaning of the due process clause of the Constitution because “it may severely hamper [the owner’s] ability to sell or encumber that property.”
(Connolly Development, Inc.
v.
Superior Court, supra,
Procedural due process mandates that an individual be afforded notice and an opportunity for a hearing before he is deprived of any significant property interest.
(Randone
v.
Appellate Department
(1971)
II
Grinnell argues that the applicable statute only requires that an action to foreclose be filed within the 90-day period, and that the statute does not mandate that subsequent encumbrances be made parties to the suit within that time. State Savings responds that California case law is contrary to Grinnell’s position. A review of apposite case law reveals that the courts have read into section 3144 a requirement that the materialman must satisfy the statute of limitations requirements as to each party to be bound by the judgment.
The decision that all parties to be bound by the judgment must be joined in the foreclosure action within 90 days of the filing of the mechanic’s lien appears to have been first reached in
Paramount Securities Co.
v.
Daze
(1933)
After a thorough analysis of analogous statutes and out-of-state case authority on the question, the court concluded that only parties joined within
*358
the 90-day period would be bound by the judgment in the foreclosure action. It cited with approval a pronouncement of the Washington Supreme Court on the same issue: “It follows of necessity that anyone interested, whether as owner, mortgagee, lien claimant, or otherwise, anyone who may defend against the lien, or show by competent evidence that it is not a lien as against his interest, has the right to invoke the statute, if the action be not commenced
as against him
within the statutory period.”
(Paramount Securities Co.
v.
Daze, supra,
Similarly, in
Riley
v.
Peters
(1961)
Various commentators have concluded based on these case holdings that “any person having an interest in the property when the suit is commenced must be included as a party defendant in order to be bound by the judgment. ” (13 Biel & Seneker, Cal. Real Estate Law and Practice (1986) Mechanics’ Liens, § 451.64[2]; 1 Miller & Starr, Current Law of Cal. Real Estate Mechanic’s Liens (1975) § 10:32, p. 573.) Although the language of section 3144 could be otherwise interpreted, we agree with the reasoning in the cited cases, and conclude that a junior encumbrancer has the right to dispute the validity, the amount, and the priority of the mechanics’ lien. The requirement that the materialman join all interested parties within 90 days after filing its lien can reasonably be read into the language of section 3144 to protect the junior encumbrancer’s rights.
Ill
Grinnell finally argues that it in any event satisfied the requirements of section 3144 by designating State Savings as a Doe defendant in its original complaint. When Grinnell gained actual knowledge of State Savings’ identity, it amended its complaint, and substituted State Savings as Doe 2. State Savings argues that Grinnell could not properly designate State Savings as a Doe defendant because Grinnell had legal knowledge of State Savings’ identity when it filed its foreclosure action. We conclude that *359 Grinnell could properly use a Doe designation for State Savings until it gained actual knowledge of its identity.
California Code of Civil Procedure section 474 provides that a plaintiff may designate a defendant by a fictitious name when the plaintiff is ignorant of the true name of the defendant. The purpose of the section is remedial. It is liberally construed to prevent the running of the statute of limitations where the plaintiff does not have actual knowledge of the name of the defendant.
(Motor City Sales
v.
Superior Court
(1973)
The plaintiff in
Irving
v.
Carpentier, supra,
This holding was repeated in
Hoffman
v.
Keeton
(1901)
Recent cases also hold that, under Code of Civil Procedure section 474, the plaintiff is charged only with actual knowledge rather than information the plaintiff could have obtained by reasonable diligence.
(Munoz
v.
Purdy
(1979)
This indication is further buttressed by language in
Union Tank etc. Co.
v.
Mammoth Oil Co.
(1933) 134 Cal.App.229 [
Authors of law review notes on mechanics’ liens have similarly concluded that a Doe pleading would be an appropriate way of satisfying the statute of limitations vis-á-vis junior encumbrancers. For instance, a law review article was published in which the then recent opinion in
Paramount Securities Co.
v.
Daze, supra,
The author of an article on
Packard Bell etc. Corp.
v.
Theseus, Inc., supra,
Furthermore, as Grinnell points out, other sections of the mechanic’s lien law contain language indicating that the Legislature did not intend to impose on the lien claimant the burden and expense of conducting a title search on the property against which the lien is filed. Thus, section 3084 provides that a claim of lien must contain “the name of the owner or reputed owner, if known,” and section 3097 similarly requires service of the preliminary 20-day notice on the “owner or reputed owner.” “The term ‘reputed owner’ clearly must mean something other than the actual owner or it is mere surplusage.”
(Brown Co.
v.
Appellate Department
(1983)
The cases cited by State Savings in support of its position that Grinnell’s constructive knowledge precludes the use of a Doe pleading are not persuasive. Although the law does presume that a lienholder has constructive knowledge of prior recorded deeds of trust
(American Medical International, Inc.
v.
Feller
(1976)
In
Rosencrantz,
four plaintiffs brought a suit in ejectment. Their complaint did not aver that they were “ignorant of the true name of any person intended to be made a defendant therein . . . .”
(Rosencrantz
v.
Rogers, supra,
The mechanics’ lien claimant occupies a favored position in California law. “The mechanics’ lien derives from the California Constitution itself; ... no other creditors’ remedy stems from constitutional command.”
(Connolly Development, Inc.
v.
Superior Court, supra,
The judgment is reversed.
White, P. J., and Barry-Deal, J., concurred.
A petition for a rehearing was denied August 11, 1986, and respondent’s petition for review by the Supreme Court was denied October 30, 1986.
Notes
All statutory references are to the Civil Code unless otherwise indicated.
