Grigerik v. SharpeGrigerik v. Sharpe
Opinion
The dispositive issues in this certified appeal are: (1) whether the seven year limitation period of
The plaintiff brought this action against the defendants in two counts.
With respect to the negligence count, the defendants pleaded, as a special defense, the two year limitations
On the defendants’ appeal to the Appellate Court, the court concluded that the two year statute of limitations provided by
On his appeal regarding the negligence count, the plaintiff claims that the Appellate Court improperly concluded that the two year limitation period of
The Appellate Court opinion sets forth the following facts that the jury reasonably could have found. “In 1983, Edward Lang purchased a tract of undeveloped land on Reservoir Road in the town of Killingworth. The property contained a hill, a marshy area, trees and many vines and bushes. Lang removed some of the trees and bushes and also obtained the release of a power line easement that the utility company no longer needed. Because the land was adjacent to a reservoir, it was within a designated watershed area.
“In 1985, Lang negotiated with the plaintiff for the sale of the land. The plaintiff offered $9000 for the property ‘as is.’ He told Lang, however, that he would pay $16,000 if Lang would do the work necessary to obtain the town’s approval of the land as a building lot. Lang agreed to do so. Both of them accompanied the sanitarian for Killingworth when he examined the property. He told them that, because the land was within a watershed district, they needed an engineer to prepare a site plan for drainage.
“Lang hired the defendant Gary Sharpe, a professional engineer, and the corporate defendant [Angus McDonald-Gary Sharpe and Associates, Inc.] to prepare a site plan, to design a subsurface sanitary sewage disposal system and to perform the necessary soil testing. Lang told Sharpe that he needed the site plan in order to obtain approval of the land as a building lot and that he had a buyer for the land if the town granted approval.
“In the spring of 1986, the plaintiff cleared the land and applied to the town sanitarian for the permits necessary to begin construction of a house in August. The new town sanitarian for Killingworth denied the plaintiffs application for a building permit even though his predecessor had told the plaintiff that the septic system would be approved. The new sanitarian said he was concerned about the suitability of the soil conditions and whether the percolation tests had been performed in the presence of the previous sanitarian. He told the plaintiff that additional percolation tests would have to be performed by an engineer in the presence of a representative of the state department of health (department) during the following spring when the soil would be saturated.
“When the percolation tests were performed on March 5, 1987, it was concluded that a curtain drain would have to be installed on the land in order to control the seasonally high groundwater. After the plaintiff had constructed the curtain drain, more percolation tests were completed and submitted to the department. On May 20, 1987, that department informed the plaintiff that the tests indicated that the land was unsuitable for a septic sewage disposal system. Additional percolation testing was done in the spring of 1989 in the presence of a department representative, who determined that the tests indicated that minimum public health standards for a septic system could not be met and that the building permits could not be issued.
I
We first consider the plaintiffs claim, asserted in his appeal; see footnote 7 of this opinion; that the Appellate Court improperly concluded that
“The process of statutory interpretation involves a reasoned search for the intention of the legislature. ... In other words, we seek to determine, in a reasoned manner, the meaning of the statutoiy language as applied to the facts of this case, including the question of whether the language actually does apply. In seeking to determine that meaning, we look to the words of the statute itself, to the legislative history and circumstances surrounding its enactment, to the legislative policy it was designed to implement, and to
In 1986, the Appellate Court was presented with the issue of whether
R.A. Civitello Co. was decided in February, 1986. By April, 1986, however, the legislature already had considered and passed Public Acts 1986, No. 86-266, § 2 (P.A. 86-266).
Our conclusion that
“In the construction of the statutes, words and phrases shall be construed according to the commonly approved usage of the language; and technical words and phrases, and such as have acquired a peculiar and appropriate meaning in the law, shall be construed and understood accordingly.”
In the ordinary case, therefore, the seven year statute of limitations begins to run from the date of the substantial completion of the improvement for which the architect or engineer performed the services. In this case, therefore, had the proposed septic system that was the subject of the defendants’ services been installed, the seven years would have begun to run from the date when the system was first used or available for use. The case before us, however, presents the question of whether
“When two constructions are possible, courts will adopt the one which makes the [statute] effective and
We recognize that our conclusion that
II
We next consider the claim raised in the defendants’ cross appeal; see footnote 7 of this opinion; that, regarding the plaintiffs breach of contract count, the Appellate Court improperly concluded that it is the intent of the promisee only, rather than the intent of both contracting parties, that determines whether a third party has enforceable rights under a contract. As noted earlier, the jury found that the plaintiff was a foreseeable third party beneficiary of the contract between the defendants and Lang, and returned a verdict in favor of the plaintiff on the plaintiffs breach of contract count.
The plaintiff argues that the Appellate Court properly concluded that, in Stowe v. Smith,
This claim originated with the defendants’ challenge in the Appellate Court to: (1) the trial court’s instructions to the jury regarding the determination of whether a third party beneficiary relationship existed between the plaintiff and the defendants; see footnote 5 of this opinion; and (2) the trial court’s subsequent failure to grant the defendants’ motion to set aside the verdict, following the jury’s express determination as evidenced by its responses to certain interrogatories,
The traditional rule requiring that courts consider the intentions of both parties in construing a contract is well settled. Lar-Rob Bus Corp. v. Fairfield,
The law regarding the creation of contract rights in third parties in Connecticut is equally well settled. In Knapp v. New Haven Road Construction Co.,
The requirement that both contracting parties must intend to confer enforceable rights in a third party rests, in part at least, on the policy of certainty in enforcing contracts. That is, each party to a contract is entitled to know the scope of his or her obligations thereunder. That necessarily includes the range of potential third persons who may enforce the terms of the contract. Rooting the range of potential third parties in the intention of both parties, rather than in the intent of just one of the parties, is a sensible way of minimizing the risk that a contracting party will be held liable to one whom he neither knew, nor legitimately could be held to know, would ultimately be his contract obligee.
In Stowe v. Smith, supra,
To the extent that a third party to whom a promisor had made no express commitment was held to have stated a cause of action, Stowe plausibly could be interpreted as having altered Connecticut law regarding the intent necessary for a third party beneficiary to have enforceable rights under a contract. We conclude, however, that the holding in Stowe was consistent with our prior decisions regarding the intent necessary for a third party to possess rights under a contract and, therefore, that the plaintiffs and the Appellate Court’s reliance on Stowe is misplaced.
Specifically at issue in Stowe was the sufficiency of the plaintiffs complaint. The complaint had alleged that “the testatrix and the defendant intended that the defendant, by his agreement to prepare [the testatrix’s] will in accordance with her instructions, would assume a direct obligation to the intended beneficiaries of the testatrix.” Id., 196. Thus, the underlying premise of the complaint was that both contracting parties intended that the plaintiff would have enforceable rights under the contract. The question before the court was not whether a dual or singular intent was controlling. The question was, instead, the validity of the attorney’s argument “that as a matter of law a promisor cannot intend to assume a direct obligation to a third party unless the promisor’s performance is to be rendered directly to that party.” Id., 197. We rejected that argument, and held that “ [contracts for the benefit of a third party
Indeed, in Stowe we began our analysis of the issue by reaffirming the traditional rule governing the creation of third party beneficiary rights under Connecticut law. “We have stated that a third party seeking to enforce a contract must allege and prove that the contracting parties intended that the promisor should assume a direct obligation to the third party.” (Emphasis added.) Id., 196. It is true that, in a footnote to this sentence, we referred to the differing views of Professors Corbin and Williston.
In support of the view that the presence of a third party beneficiary issue is determined solely by the intention of the promisee, the Appellate Court also relied on 2 Restatement (Second), Contracts § 302 (1981), and concluded that “[t]he notion that the promisor and
We decline, therefore, to alter our traditional test for determining whether a third party has enforceable contract rights. We reaffirm that the intent of both parties, rather than just one of the parties to a contract, determines whether a third party is to be afforded third party beneficiary status under a contract.
Applying this standard to the facts of the present case, we conclude that the plaintiff cannot prevail on his breach of contract claim. The jurors specifically found that the plaintiff had not proven that he was an intended beneficiary of the contract between Lang and the defendants. See footnote 15 of this opinion. The plaintiff, therefore, did not establish that it was the intent of the parties that he be a third party beneficiary of the contract.
Although the jury found that the plaintiff was a foreseeable beneficiary of the contract, we agree with the Appellate Court that foreseeability is a tort concept, and the fact that a person is a foreseeable beneficiary
With respect to the negligence count, the judgment of the Appellate Court is reversed and the case is remanded to that court with direction to consider the defendants’ claim that the trial court abused its discretion in permitting the plaintiff to amend his complaint after the jury had been selected; in the event that the Appellate Court finds no abuse of discretion, that court is directed to affirm the judgment of the trial court on the negligence count. With respect to the breach of contract count, the judgment of the Appellate Court is reversed and the case is remanded to that court with direction to remand it to the trial court with direction to render judgment for the defendants on that count.
In this opinion the other justices concurred.
Notes
“(b) Notwithstanding the provisions of subsection (a) of this section, in the case of such an injury to property or the person or such an injury causing wrongful death, which injury occurred during the seventh year after such substantial completion, an action in tort to recover damages for such an injury or wrongful death may be brought within one year after the date on which such injury occurred, irrespective of the date of death, but in no event may such an action be brought more than eight years after the substantial completion of construction of such an improvement.
“(c) For purposes of subsections (a) and (b) of this section, an improvement to real property shall be considered substantially complete when (1) it is first used by the owner or tenant thereof or (2) it is first available for use after having been completed in accordance with the contract or agreement covering the improvement, including any agreed changes to the contract or agreement, whichever occurs first.
“(d) The limitation prescribed by this section shall not be asserted by way of defense by any person in actual possession or the control, as owner, tenant or otherwise, of such an improvement at the time any deficiency in such an improvement constitutes the proximate cause of the injury or death for which it is proposed to bring action.”
The original complaint named Gary Sharpe as the only defendant. Thereafter, the trial court granted the plaintiffs motion to add Angus McDonald-
The amended complaint contained four counts at the commencement of the trial. The first two counts, which named only Sharpe as the defendant, were withdrawn before the case was submitted to the jury, leaving two counts, each of which was directed against both defendants. All references to the first and second counts, therefore, refer to the third and fourth counts, respectively, of the amended complaint.
The trial court instructed the jury as follows: “In light of all the evidence, you must determine whether [the plaintiff] was an intended, contemplated or foreseeable third party which was to derive a benefit from the contract for professional services entered into between the defendants and [Lang]. You must determine that it was intended, contemplated and foreseeable that any buyer of the property would derive a benefit from the contract or you may determine that it was intended, contemplated or foreseeable that [the plaintiff] specifically would derive a benefit from the contract. If you find that it was intended that [the plaintiff] was an intended, contemplated or foreseeable beneficiary to tire contract, then you must find that [the plaintiff] was a third party beneficiary to the contract. In summary, if you determine that [the plaintiff] was a third party beneficiary to the contract and that tire defendants breached the contract, then [the plaintiff] is entitled to the damages caused him as a result of the breach.”
The defendants took exception to the charge, and requested a charge to the effect that a determination that both contracting parties intended Lang to have a direct obligation to the plaintiff was requisite to a finding for the plaintiff on the breach of contract count.
The Appellate Court, therefore, declined to address an additional claim of the defendants, namely, that the trial court improperly had permitted the plaintiff to amend his negligence count at the beginning of the trial. As a result of our disposition of this appeal, it will be necessary for the Appellate Court to consider this claim upon the remand. In addition, the Appellate Corut rejected two evidentiary claims by the defendants, which are not involved in this appeal.
We granted the plaintiffs petition for certification to appeal from the Appellate Court, limited to the following issue: “Did the Appellate Court correctly conclude that the two year statute of limitations (
We granted the defendants’ cross petition for certification to appeal from the Appellate Court, limited to the following issues: “1. Did the Appellate Court properly hold that only the intent of the promisee, and not the intent of both contracting parties, is dispositive of the rights of an alleged third-party beneficiary of a contract?
“2. Where the jury had specifically found that the plaintiff was neither an ‘intended’ nor ‘contemplated’ beneficiary of a contract between the defendant and another, but only a ‘foreseeable’ beneficiary of that contract, did the Appellate Court properly remand the case for retrial on the third-party beneficiary claim rather than entering judgment for the defendants?” Grigerik v. Sharpe,
The Appellate Court also noted that “Sharpe testified at trial that Lang had not informed him of his intention to sell the property.” Grigerik v. Sharpe, supra,
Prior to the amendments of Public Acts 1986, No. 86-266, § 2,
“(b) Notwithstanding the provisions of subsection (a) of this section, in the case of such an ipjury to property or the person or such an injury causing wrongful death, which injury occurred during the seventh year after such substantial completion, an action in tort to recover damages for such an injury or wrongful death may be brought within one year after the date on which such injury occurred, irrespective of the date of death, but in no event may such an action be brought more than eight years after the substantial completion of construction of such an improvement.
“(c) For puiposes of subsections (a) and (b) of this section, an improvement to real property shall be considered substantially complete when (1) it is first used by the owner or tenant thereof or (2) it is first available for use after having been completed in accordance with the contract or agreement covering the improvement, including any agreed changes to the contract or agreement, whichever occurs first.
“(d) Nothing in this section shall be construed to extend the period prescribed by the laws of this state for the bringing of any action.
The Appellate Court also noted that at the time the original version of
Section 1 of P.A. 86-266 pertained to certain workers’ compensation claims against architects and engineers. It is not involved in this appeal.
Legislative history supports this interpretation of the meaning of improvement under
Moreover, adoption of the defendants’ suggested interpretation could provide incentives for wasteful behavior. For example, customers who discover a defective plan or design more than three years after a design is initiated would have no incentive to stop or delay the development of a structure in accordance with the defective plan. Stopping the construction would leave the consumer barred from bringing any action because the limitations period of
It is conceivable that, because of a defective design, the planned improvement is not effectuated and the property owner waits more than seven years to bring an action. That would be the situation, for example, if the plaintiff
Three of the interrogatories posed to the jury related to the third party beneficiary issue. Those interrogatories and responses were as follows:
“1. Did the plaintiff prove, by a fair preponderance of the evidence, that Joseph Grigerik was an intended third-party beneficiary to the contract between Edward Lang and Gary Sharpe in 1985?
“No.
“2. Did the plaintiff prove, by a fair preponderance of the evidence, that Joseph Grigerik was a contemplated third-party beneficiary to the contract between Edward Lang and Gary Sharpe in 1985?
“No.
“3. Did the plaintiff prove, by a fair preponderance of the evidence, that Joseph Grigerik was a foreseeable third-party beneficiary to the contract between Edward Lang and Gary Sharpe in 1985?
“Yes.”
“Commentators generally look upon the intent oí the promisee, if the promisee had any relevant intent, as governing whether a third party may enforce a contract as a donee beneficiary. Restatement (Second), Contracts, c. 6, Introductory Note and § 133 (Tent. Draft 1973); 2 Williston, Contracts (3d Ed.) § 356A, pp. 836, 839 n.19; 4 Corbin, Contracts § 776, p. 16.
“Williston has criticized Colonial Discount Co. v. Avon Motors, Inc., [supra,
“Corbin views the ideas that lie behind such terms as ‘purpose,’ ‘motive,’ and ‘intention’ as obscure and elusive. 4 Corbin, [supra] § 776, pp. 11-15. The problem before the courts, he says, ‘is to draw the line between those third persons whose benefit is so indirect and incidental that it is not sound policy to let them enforce the contract, and those other persons whose benefit is so direct and substantial and so closely connected with that of the promisee that it is economically desirable to let them enforce it. The law would profit greatly if the courts would concentrate upon this aspect of the problem and cease to state the questions merely in terms of the supposed “intent” of the parties.’ [Id.,] § 786, p. 95.” Stowe v. Smith, supra,
Third party beneficiaries “can be loosely grouped into two classes; (1) donee beneficiaries, and (2) creditor (or obligee) beneficiaries. The third
Relying on the first Restatement of Contracts, the Appellate Court determined that because “Lang’s puipose in contracting with the defendants was to fulfill his obligation to the plaintiff to convey an approved building lot to him . . . [and] [t]he evident purpose of the transaction with the defendants was to enable Lang to sell his land to the plaintiff at the enhanced price agreed on for the lot,” the plaintiff would qualify as a creditor beneficiary of the contract. Grigerik v. Sharpe, supra,