193 Iowa 697 | Iowa | 1922
— The petition demurred to alleges that, on July 12, 1920, the defendant Cass County and the defendant Wilson Concrete Company, hereinafter spoken of as the contractor, entered into a written agreement, whereby said contractor undertook, for a stated consideration, to furnish the necessary labor and materials, and to construct a bridge or culvert and bulkhead on the primary road between the cities of Atlantic and Lewis, according to the plans and specifications prescribed therefor, and made a part of the contract. Among the specifications so included are the following:
“The contractor shall assume all responsibility for damages sustained by persons or property, due to the carrying on of his work, and shall maintain such watchman, barriers, and red*699 lights as will effectually prevent accidents. The contractor shall be responsible for all accidents and save the county harmless from all damages resulting from any accidents which may occur on old or temporary structures to be replaced under this contract after the date of the completion as specified in the contract. Any extension of time granted the contractor on which to complete his contract shall not relieve him or his bondsmen of their responsibility under this contract. The responsibility o£ the contractor for maintaining barriers and lights shall cease when the crew is moved from the work, provided the engineer and member of the board for that district shall have two days’ notice before the crew is moved. If ordered by the county engineer, the contractor shall erect barriers with suitable signs at convenient crossroads at either side of the work, under construction to divert traffic from that road. The board and engineer shall use every precaution possible to guard the safety of the traveling public, and to divert traffic from the road on which construction work is in progress, but the failure of the board or engineer to- notify the contractor to maintain barriers, red lights, or watchmen shall not operate to relieve the contractor from his responsibility.”
It is further alleged that, in pursuance of such agreement, the contractor did proceed with the construction of said bridge or culvert, the same being constructed of 36-inch tile; that said tile were first laid on the west side of the road, after which the tile and bulkhead on the east side or end were put in place; and that, in so doing, the contractor willfully and negligently obstructed said bridge, by placing thereon, and partly over said culvert, and wholly within the limits of the bulkhead, and upon top of said bridge, a pile of dirt, three or four feet in height, and sloped over into that part of the bridge which had previously been open to travel; that, on or about September 30 or October 1, 1920, the contractor finished pouring the concrete into the forms for the bulkhead, and on October 2, 1920, removed its men and apparatus from the bridge, but left the’forms still on the bulkhead and the pile of dirt on the bridge, wholly within the limits of the bulkhead, all of which was known to the defendant Zelmer, supervisor of the district in which the work was done; and that said contractor and the county and its board of supervisors left
I. Giving first attention to the plaintiffs’ demand for recovery against the county and its officers, it is to be said that, while appellants do not expressly concede the nonliability of said defendants, it is manifest that they recognize that the trend of our more recent decisions sustains the ruling of the trial court in this respect. See Snethen v. Harrison v County, 172 Iowa 81,
These matters are chiefly relevant to the contractor’s contention in this case that it does not occupy the relation of independent contractor, but is rather the mere employee or representative of the county, and as such is not chargeable with liability for damages. In our opinion, there is no room to doubt that the appellee Wilson Concrete Company was neither the servant, agent, nor representative of the county, but that its relation to the comity was that of independent contractor. Fitzgibbon v. Western Dredging Co., 141 Iowa 328; Wood V. Independent 8ch. Dist., 44 Iowa 27; Bennett v. Incorporated Town of Mt. Vernon, 124 Iowa 537; Teeters v. City of Des Moines, 173 Iowa 473; Humpton v. Unterkircher, 97 Iowa 509; Solberg v. Schlosser, 20 N. D. 307 (127 N. W. 91). The contractor undertook to furnish all the necessary labor, materials, tools, and equipment, and to perform the entire contract for construe
“Where the contractor undertakes simply to excavate the ditch on the line, according to the plan laid down for his guidance, he does not, in our judgment, assume any liability for the care of the water naturally accumulating behind his dredge: He must not, of course, by his own negligent act or omission increase the amount of water in the ditch beyond that which naturally accumulates from its construction according to the authorized plan, nor by his negligent opening or breaking-down or weakening the banks contribute to the escape of the water, to the injury of others; and for failure of duty in this respect, his liability cannot be questioned.”
The same doctrine finds i-ecognition in Bennett v. Incorporated Town of Mt. Vernon, 124 Iowa 537, 542. There the contractor, in digging a sewer for the city, disconnected a tile leading into the cellar of the plaintiff, who sued the city and contractor jointly. In holding the city not liable, because its codefendant .was an independent contractor, we said that the contractor could rightfully disconnect the tile, 'if it was found necessary to the proper performance of the work, but that “he had no right to so prosecute the work as to create a nuisance. * * * For his mere act in disconnecting the tile and digging the ditch in a proper and lawful manner, there can be no recovery; but he should be held liable for any nuisance he may have created.”
To this same effect is the holding of the Minnesota court in Nye v. Dibley, 88 Minn. 465 (93 N. W. 524), where a contractor,
“Defendants were engaged in a public work upon a highway, under a contract with the public authorities, and had the undoubted right to make such reasonable use of the highway as was necessary in carrying forward the work. But they had no right to its exclusive use, and were bound so to use it as not to interfere unnecessarily with public travel thereon. ’ ’
See, also, Ramsey v. National Contracting Co., 49 App. Div. 11 (63 N. Y. Supp. 286); Tompert v. Hastings Pav. Co., 35 App. Div. 578 (55 N. Y. Supp. 177).
III. Thus far, we have omitted to consider the bearing upon this appeal of the allegation of the petition showing that, by a provision embodied in the contract, the appellee contractor assumed all the responsibility for damages sustained by persons or property due to the carrying-on of the work, and should maintain such watchmen and barriers and red lights as would effectually prevent accidents. It was also still further provided that the board and engineer should use every precaution to guard the safety of the traveling public while the work was in progress, but that the failure of the board or engineer in this respect should “not operate to relieve the contractor from its responsibility.” Notwithstanding the general exemption of the county and its officers from personal liability, it was, nevertheless, -within -tlieir power, in letting the contract for the bridge, to protect the public interest and promote the safety of travelers by requiring the contractor to exercise reasonable care to avoid the creation of a nuisance. Indeed, the law imposed that duty upon the contractor even though no such stipulation had been embodied in the agreement. The express agreement to that effect is of importance, however, as witnessing the contractor’s understanding of its obligation to exercise due care.
IY. The case presented by this appeal is not within the reason or principle which was held controlling in Vanhorn v. City of Des Moines, 63 Iowa 447; Becker v. Keokuk Waterworks, 79 Iowa 419; or Boston Ins. Co. v. Chicago, R. I. & P. R. Co., 118 Iowa 423. The appellee contractor in this case was not a public officer or agency, nor engaged in pei’forming governmental functions. It was an independent contractor, which had undertaken to construct the bridge with its own labor and materials. Its legal responsibilities, so far as third persons are concerned, were neither greater nor less than are assumed by every contractor who undertakes to produce a given result, for an agreed consideration. The employees engaged in the work are its own, and it alone is responsible for the damages, if by its negligence some third person is injured. For illustration, let us suppose that the contractor had taken the job to construct a courthouse for the county, and in prosecution of the work, it had erected a grossly defective and dangerous scaffold, which fell and killed or injured some of its workmen, or a traveler lawfully on the walk beneath, — would counsel contend for an instant that, because the county was not responsible for such injury, the contractor, by whose fault the calamity occurred, would also be immune against an action for damages? Had the alleged nuisance in the highway in this case been chargeable to a defective plan adopted by the county or its engineer, a very different question would be presented; but, as alleged, and as the demurrer admits, the obstruction was of the contractor’s own creation;
It is argued, however, that this obligation 'had ceased, because the work had been completed and turned over to the county. But such is not the record. It is true that the contract provides that the contractor’s duty in this respect should cease when the “crew is moved from the work, provided the engineer and member of the board for that district shall have two days’ notice before the crew is moved.” The petition alleges that, while the crew had been withdrawn, the contractor had not given the required notice to the engineer or supervisors, and that it was while the obstruction was thus left unguarded that the accident occurred. These allegations are admitted by the demurrer, and for the purposes of this appeal, must be taken as true.
The allegation with respect to the passage over the bridge and its width must, in fairness, be read and construed with reference to its statement of the attendant circumstances; and, so doing, we think it not within our province to say, as a matter of law, that plaintiffs, driving in the nighttime, without knowl
The cited case of Person v. Polk County, 193 Iowa 733, is not at all in point in its facts or in the principle applied. In that case, the county alone was charged with negligence in the maintenance of a bridge, but the court found against the plaintiff on the facts, holding that the accident was not the result of any defect in the bridge, but rather of plaintiff’s loss of control of his car, which was due to a defect in the highway before he entered upon the bridge.
Further discussion is not called for. For the reasons stated, the holding of the trial court sustaining the demurrer to the petition as against Cass County, Iowa, and its auditor and board of supervisors, is affirmed, and its further order sustaining said demurrer in favor of the defendant contractor is reversed, and the cause will be remanded to the trial court, with direction to overrule the demurrer of the contractor, and for further proceedings in harmony with this opinion. — Affirmed in part; reversed in part.