229 Ct. Cl. 762 | Ct. Cl. | 1982
This is one of a number of cases brought in this court by Gregory Lumber Company (Gregory), stemming from contracts to purchase standing timber from the Government. Defendant has moved for summary judgment on the ground that the case is not properly here. This panel has heard oral argument in this case, and we consider it alone, on its own specific facts. We make no attempt to decide other suits by this plaintiff in which the facts may differ. Moreover, we
The first issue is whether plaintiff may sue in this court under the "direct access” provision of the Contract Disputes Act of 1978, 41 U.S.C. § 609(a)(1) and (3). There is a dispute whether the contract claim in issue was still pending before the contracting officer on the effective date of the Act (March 1, 1979), but we can assume arguendo with plaintiff (but without deciding) that that claim was still pending and was decided thereafter on November 6, 1979. Even so, suit was not filed here until March 9, 1981 — much beyond the twelve month limit established by the Act, for a "direct access” action. § 609(a)(3). This definite limitation period was not tolled by plaintiffs efforts to seek review of the contracting officer’s decision by the Interior Board of Contract Appeals. Under the "direct access” provision, such administrative review was clearly not a mandatory prerequisite. Indeed, it was not a prerequisite at all; the presupposition of the "direct access” system is that suit here may be commenced immediately after the contracting officer’s decision, without resort to a board of contract appeals. See Tuttle/White Constructors, Inc. v. United States, 228 Ct. Cl. 364, 359, 656 F.2d 644, 646-47 (1981). Congress has set the twelve-months limit, and this court cannot and should not read into it exceptions and tolling provisions Congress did not contemplate or authorize. Soriano v. United States, 352 U.S. 270 (1957). Accordingly, plaintiffs petition, to the extent that it invokes the "direct access” part of the Contract Disputes Act, is beyond our jurisdiction and must be dismissed.
The second issue is whether plaintiff may proceed in this court under the Tucker Act. Gregory contends that it may, because (a) it clearly brought suit within six years (see 28 U.S.C. § 2501) of the contracting officer’s final decision (whenever it may have been) and (b) the contract did not require or contemplate exhaustion of any administrative remedies within the Interior Department. The result, says plaintiff, is that it is entitled to a full de novo trial in this court. Defendant insists, to the contrary, that Gregory was required to exhaust its remedy through the Interior Board of Land Appeals. Since this suit was begun, that Board has
Belatedly, defendant presses on us, alternatively and conditionally, the proposition that plaintiff may be wholly out of court because it elected (by appealing to the Board of Contract Appeals) to come under the Contract Disputes Act but has failed to seek timely review by this court of that Board’s decision that the Act did not cover plaintiff.
The somewhat complicated facts are these: Plaintiff first presented its claim to the contracting officer on June 20, 1978; this was denied on November 21, 1978. On December 8, 1978, Gregory appealed to the Interior Board of Contract Appeals and, on the same day, also appealed to the Interior Board of Land Appeals. The Government sought and obtained a stay of proceedings from the Land Appeals Board. However, after the present suit was filed in this court (on March 9, 1981), the latter Board decided (on April 30, 1981) the claim adversely to plaintiff; this was confirmed by that Board on June 2, 1981. Meanwhile, on June 28, 1979, the Interior Board of Contract Appeals issued a rule to show cause why the appeal to it should not be dismissed for lack of jurisdiction under the Contract Disputes Act (or otherwise). The parties took opposing stands. On September 28, 1979 the Contract Board of Appeals dismissed the claim for lack of jurisdiction and confirmed that ruling on November 23, 1979. After the contracting officer (in plaintiffs view) reconsidered the claim and denied it on November 6, 1979,
Tuttle/White Constructors, Inc. v. United States, 228 Ct. Cl. 354, 656 F.2d 644 (July 29, 1981), was quite different. There, the claimant was expressly told that it could elect under the Contract Disputes Act, but failed to do so. It proceeded as if under the prior law until well into the pre-Disputes Act disputes-process. We held that that contractor had deliberately elected not to come under the Contract Disputes Act. Here, on the other hand, plaintiff was never told that it could elect — indeed, the Government emphatically urged that there was no coverage under the Disputes
For these reasons, we hold that (1) plaintiff cannot avail itself of the "direct access” provision of the Contract Disputes Act; (2) plaintiff has not elected to come under the Disputes Act;
We also remand to the Trial Division, for disposition, plaintiffs motions respecting its request for reconsideration of the court’s order regarding suspension of discovery.
The defendant strongly disputes the plaintiffs position that there was such a reconsideration after the Contract Disputes Act went into effect.
In Everett the trial judge had previously decided the other way.
For this reason it is unnecessary to decide other issues (e.gthe necessity for certification) which arise only under the Contract Disputes Act.