The plaintiff, a subcontractor, brought suit to recover a balance alleged to be due for materials furnished and for work performed in furtherance of a contract it had with the defendant, a general contractor, for the excavation and site development required in connection with the construction of the Dundee Elementary School in the town of Greenwich. The defendant filed a counterclaim alleging that by mistake a paragraph was omitted from the subcontract, asking for reformation of the subcontract to include the paragraph in question, and claiming damages for reimbursement
The facts as found by the court, with such corrections as are warranted, are as follows: The defendant entered into a contract, dated May 9, 1961, with the board of education of the town of Greenwich for the construction of the Dundee Elementary School. The defendant engaged several subcontractors to perform various work under the general contract. The plaintiff, one of the subcontractors engaged by the defendant, agreed under a contract dated May 15, 1961, to perform, inter alia, the site work outlined in § 31 of the specifications of the general contract, excluding, however, subsections 21 through 31 of § 31, which contained thirty-seven subsections numbered 1 through 37. The contract price was $114,230, with change orders bringing the total contract price to $118,718.07 and with further modifications bringing the adjusted contract price to $110,125.11. The parties stipulated to an unpaid balance due the plaintiff of $18,885.94.
The contract between the parties, prepared and dictated by Martin W. Witte, the defendant’s vice-president, was typed under his supervision in the defendant’s office and was signed by Witte and Frank E. Mazza, the plaintiff’s president.
The basic issue raised by the counterclaim is whether the defendant is entitled to have the contract between the parties reformed to include subsection 26 of § 31 of the specifications, entitled “Finished Grading.” Rider A, attached to and made a part of the contract, provided that subsections 21 to 31, inclusive, of § 31 of the specifications
A cause of action for reformation of a contract rests on the equitable theory that the instrument sought to be reformed does not conform to the real contract agreed upon and does not express the intention of the parties and that it was executed as the result of mutual mistake, or mistake of one party coupled with actual or constructive fraud, or inequitable conduct on the part of the other.
Moffett, Hodgkins & Clarke Co.
v.
Rochester,
A court in the exercise of its power to reform a contract must act with the utmost caution and can only grant the relief requested if the prayer for
The trial court concluded that the mistake was not mutual and that it was a unilateral mistake of the defendant not coupled with fraud or inequitable conduct on the part of the plaintiff. It refused to reform the written contract, concluding that the reformation as requested by the defendant, if granted, would not express the understanding and agreement of the parties.
In seeking to reverse the judgment of the court, the main thrust of the defendant’s argument, although it concedes the difficulty inherent in an attempt to “overthrow a decision of a trial judge on an issue of fact,” is that “the indisputable physical facts are so compelling” it must be found that the trial court reached an erroneous conclusion and that the “cumulative effect of the documentary evidence is so overwhelming . . . that the conclusion is inescapable that the finished grading was part of the plaintiff’s obligation under the contract.”
The evidence upon which both parties rely, which affects the basic issues in the case, consists of the testimony of Witte, the defendant’s vice-president, Mazza, the plaintiff’s president, and Herman Boxer and John S. Wason, general superintendent and construction superintendent, respectively, for the defendant. In addition, the defendant places great stress upon the following series of documents in support of its claims: The plaintiff’s original estimate made before the contract was executed; the plaintiff’s breakdown of contract prices; a schedule of values attached to the contract; fourteen requisitions signed by Mazza as the plaintiff’s president referring to finished grading; an agreement between the plaintiff and one of the subcontractors which the defendant claims shows an inconsistent position by the plaintiff; and a field memorandum reciting that the plaintiff would complete fifteen items before a certain date, one of which included finished grading, which the defendant claims indicates a stand at variance with the one which the plaintiff now takes as to responsibility for finished grading.
Although the defendant strenuously argues that all of this evidence is indisputable proof of the position it takes, we do not find this to be the clear
The paragraph sought to be added to the contract by the defendant was specifically omitted from the written contract, and Mazza testified that the plaintiff never contemplated performing any of the work described in the omitted paragraph, that the contract expressed the true understanding of the parties, and that the plaintiff performed all of the work it was required to do under the contract. He testified that the finished grading for which the plaintiff was responsible was done pursuant to subsection 32 of § 31 of the general specifications and was performed for the plaintiff by Patsy Crucitti and Sons, its subcontractor. Boxer, the general superintendent of the defendant, who assisted Witte in drawing the contract, testified that he knew the contract was the understanding between the parties.
The contract was drawn and signed by Witte, an officer of the defendant who was experienced in these matters and who had the assistance, in this connection, of Boxer, the defendant’s general superintendent. There is nothing in the record which required the trial court to interpret the language of the contract contrary to the common meaning of the words used. Its conclusion is fortified by the
In the view we take of the case, the claim of the defendant of unjust enrichment is without merit since the word “unjustly” as used in the equitable maxim that one shall not be allowed unjustly to enrich himself at another’s expense means unlawfully.
Sheasgreen Holding Co.
v.
Dworsky,
The final claim of the defendant as to the failure to produce a witness is without merit since there is no showing, among other reasons, that it was within the plaintiff’s power to produce the witness.
Secondino
v.
New Haven Gas Co.,
There is no error.
In this opinion the other judges concurred.
