Greenleaf Engineering & Construction Co. v. Teradyne, Inc.Greenleaf Engineering & Construction Co. v. Teradyne, Inc.
This dispute grows out of two contracts, each dated April 3, 1980. The first (Contract No. 1), between *572 Teradyne, Inc. (Teradyne), and Greenleaf Engineering & Construction Company, Inc. (Construction), provided that Construction was to perform services as project manager/construction manager with respect to the renovation of 1000 Washington Street, Boston. The second contract (Contract No. 2), between Teradyne and Greenleaf Engineers, Inc. (Engineers), provided that Engineers was to furnish other professional services as project engineer on the same renovation. Contract No. 2, but not Contract No. 1, contained a broad provision for arbitration.
Construction brought this action against Teradyne on April 21, 1982, to recover a fee for services related to Contract No. 1. The complaint alleged that on July 31, 1981, Construction and Teradyne had executed a settlement agreement. 2 In that Teradyne had released Construction “from all claims for costs and expenses due to any asserted failure” to perform under Contract No. 1. Construction under that agreement was to negotiate a settlement fee with Teradyne “as soon as practicable.”
Teradyne in its answer filed a counterclaim against Construction and also a third-party claim joining as third-party defendants Engineers and Sidney J. Greenleaf, individually. Both the counterclaim and the third-party claim asserted counts in contract, fraud, misrepresentation, and negligence against Construction, Engineers, and Greenleaf, as well as counts under G. L. c. 93A, § 11.
Greenleaf, as president of Construction and of Engineers, respectively, had signed both Contract No. 1 and Contract No. 2. It appeared, from pleadings (and exhibits thereto) and affidavits, that Greenleaf was a director and a shareholder of Construction. Engineers and Construction had the same mail address. Engineers apparently had been in existence for some time before negotiations for the two *573 contracts were completed. Construction, however, was not organized as a corporation until shortly before the contracts were signed.
A vice-president of Teradyne, Owen Robbins, by affidavit stated that he had dealt almost entirely theretofore with Greenleaf as the president of “Engineers and the controlling person in . . . [that] company” and had been persuaded by him that Greenleaf should assume “the dual roles of Project Engineer and Project Manager/Construction Manager.” Robbins’s affidavit, however, reveals that he, for Teradyne, knew that he was dealing with two separate corporations.
On a motion by Engineers, a Superior Court judge ordered Teradyne and Engineers to proceed to arbitration on the issues between them, as required by Contract No. 2. He denied Teradyne’s motion to require Construction to arbitrate its claims against Teradyne under Contract No. 1 and the settlement agreement, and stayed (pending arbitration) further court proceedings in the controversy between Teradyne and Engineers. Teradyne’s motions (G. L. c. 231, § 118) for relief from these interlocutory orders were denied by a single justice of this court. The case is before us on Teradyne’s appeal from the orders of the Superior Court. We agree with those orders essentially on the grounds concisely stated by the Superior Court judge. Because the orders under review are closely related, we discuss them both, although only one of the orders (that denying Teradyne’s motion to compel Construction to arbitrate) would seem to be appealable under G. L. c. 251, § 18, inserted by St. 1960, c. 374, § 1. See
School Comm. of Agawam
v.
Agawam Educ. Assn.,
1. Teradyne argues that the relationship among Greenleaf (as an individual), Construction, and Engineers is close and that Greenleaf’s influence in the affairs of Engineers and Construction is pervasive, particularly with respect to his and the corporations’ participation in both contracts. From this Teradyne contends that Engineers’ *574 obligation to arbitrate under Contract No. 2 should be treated as binding upon Construction under Contract No. 1.
The trial judge on this record was not required to regard the tripartite relationship among Construction, Engineers, and Greenleaf as so interwined that it was necessary for Construction to submit to arbitration its claims under Contract No. 1 and the settlement agreement (neither of which provided for arbitration). Teradyne had dealt sufficiently with Construction and Engineers separately, at least in negotiating the settlement agreement, as to permit the trial judge to treat the corporations as separate entities with respect to arbitration. The record, at least at this stage, does not show fraudulent, unconscionable, or ambiguous behavior, requiring disregard of the corporate entity of either corporation. See the discussion in
My Bread Baking Co.
v.
Cumberland Farms, Inc.,
2. Teradyne also contends that its claim against Engineers under G. L. c. 93A, § 11, cannot be referred to arbitration. Such a result is not required by
Hannon
v.
Original Gunite Aquatech Pools, Inc.,
The trial judge correctly declined to apply to the present case the principles of
Wineland
v.
Marketex Intl., Inc.,
*576
The trial judge correctly concluded that the present claims of Teradyne under its common law counts and c. 93A constitute “a private matter” which “does not significantly involve public interest factors ... as ... in antitrust cases.” He then relied (as we do) upon
Flower World of America, Inc.
v.
Wenzel,
The appeal from the order of the Superior Court that Teradyne proceed to arbitration under its third-party claims against Engineers (and staying further court proceedings on those claims) is dismissed. The order of the Superior Court refusing to direct Construction to arbitrate its claims against Teradyne is affirmed.
So ordered.
Notes
The trial judge recorded in his memorandum and order on the two motions now before us that Teradyne’s counsel at the oral argument before him conceded that Teradyne was assisted by counsel in the preparation of the settlement agreement.
Compare the results in
Interocean Shipping Co.
v.
National Shipping & Trading Corp.,
There it was stated (at 541) that c. 93A, § 9(6)-(8), “though not applicable to an action under § 11,” may “provide a useful analogy” (at least insofar as § 9 provides for a stay rather than dismissal) when for some reason exhaustion of administrative remedies may be desirable in an action under § 11.
Nelson
v.
Blue Shield of Mass., Inc.,
Now a Circuit Judge, U.S. Court of Appeals, 9th Circuit.