Greater Yellowstone Coalition v. TidwellGreater Yellowstone Coalition v. Tidwell
I. INTRODUCTION
Petitioners-Appellants Greater Yellowstone Coalition, Jackson Hole Conserva-
tion Alliance, and Wyoming Outdoor Council (collectively “GYC”) sent a letter to the United States Forest Service (“Forest Service”) and the United States Bureau of Land Management (“BLM”) requesting the agencies to undertake environmental analyses of Wyoming elk feedgrounds located on federal land. In the letter, GYC alleged the environmental analyses were required pursuant to the National Environmental Policy Act (“NEPA”),
II. BACKGROUND
Each winter the State of Wyoming feeds approximately 13,000 elk at twenty-two designated feedgrounds. All or part of twelve of the Wyoming feedgrounds are located on federal lands administered by either the Forest Service or BLM. The Forest Service authorizes use of the land in the Bridger-Teton National Forest for eight feedgrounds: Alkali, Fish Creek, Dog Creek, Dell Creek, Fall Creek, Forest Park, Upper Green River, and Muddy Creek. The Forest Service also authorizes a test-and-slaughter program at the Muddy Creek feedground. This program was
GYC contends that in recent years substantial scientific information has emerged demonstrating the unnatural concentration of elk on feedgrounds significantly increases the incidence of disease outbreak among feedground elk populations. Specifically, GYC points to research indicating brucellosis prevalence among elk averages twenty-four percent at the twelve feedgrounds where the Wyoming Game and Fish Department (“Wyoming”) vaccinates for the disease and thirty-two percent at a single feedground where no vaccination is conducted. By contrast, brucellosis prevalence among Wyoming elk not frequenting feedgrounds is only two percent. GYC, also claims the unnatural elk concentrations on Wyoming’s feedgrounds present a grave risk of a chronic wasting disease epidemic among the feedground elk populations. Chronic wasting disease affects the central nervous system and ultimately results in the death of infected animals.
The Forest Service authorizes use of the Bridger-Teton National Forest feed-grounds by the State of Wyoming through a special use permitting system pursuant to
Like the Forest Service, BLM allows the State of Wyoming to operate feed-grounds on certain federal lands. In 1981, BLM and Wyoming entered into a Memorandum of Understanding (“MOU”) regarding Wyoming’s use of BLM lands for elk feedgrounds. No land use permits were issued for the use of this federal land. The only environmental analysis of the feedgrounds was prepared in connection with the 1981 MOU. The environmental analysis did not consider any disease-related impacts of the feedgrounds.
On November, 17, 2005, GYC sent a letter to the Forest Service and BLM alleging various NEPA and federal regulatory violations based upon the lack of permits and environmental analyses for the feedgrounds. When the agencies did not take the actions requested by GYC to remedy these violations, GYC filed a Petition for Review of Agency Action in the United States District Court for the District of Wyoming against various Forest Service and BLM officials. The State of Wyoming and the Wyoming Stock Grower’s Association were granted intervention as of right as respondents by the district court.
Before the district court, GYC alleged: (1) the Forest Service was required under NEPA to conduct environmental analyses of its eight feedgrounds and the test-and-slaughter program, and failed to do so; (2) the Forest Service’s authorization of certain facilities for elk-feeding operations and the test-and-slaughter program with
On August 24, 2007, the district court issued a Memorandum Opinion and Order rejecting GYC’s claims. First, with respect to the Forest Service feedgrounds for which permits existed, the district court refused to compel supplemental environmental analyses because it concluded the major federal action was completed when the permits were issued. Second, with respect to the Forest Service feed-grounds without permits, the district court concluded GYC lacked standing to raise a NEPA challenge and there was no final agency action sufficient to raise a claim under the Administrative Procedure Act. Third, with respect to the test-and-slaughter program at the Muddy Creek feed-ground, the district court concluded GYC lacked standing on the permitting claim and the NEPA claim failed because the Forest Service’s authorization of the facilities was not a major federal action. Finally, with respect to the BLM feedgrounds, the district court rejected GYC’s permitting and NEPA claims, concluding BLM adequately authorized the feedgrounds pursuant to the 1981 MOU.
On appeal, GYC seeks review of the agencies’ decisions not to conduct the requested new or supplemental environmental analyses of the feedgrounds. GYC also seeks to enjoin use of the test-and-slaughter facilities until an environmental analysis is undertaken and requiring the Forest Service and BLM to undertake environmental analyses of the twelve Wyoming feedgrounds. After the briefs were filed in this appeal, the Forest Service granted long-term permits authorizing Wyoming to use the four previously non-permitted feedgrounds, including the test-and-slaughter program at Muddy Creek, for winter elk management activity. 2 In connection with the long-term authorizations, the Forest Service undertook an environmental analysis of the Alkali Creek, Fish Creek, Fall Creek, Muddy Creek (including the test-and-slaughter program), Dog Creek, and Upper Green River feed-grounds. The environmental analysis considered the risks and impacts of brucellosis and chronic wasting disease.
III. DISCUSSION
GYC brings its claims pursuant to
Respondents argue GYC’s claims as to the Alkali Creek, Fish Creek, Fall Creek, Muddy Creek, Dog Creek, and Upper Green River feedgrounds became moot in July 2008 when the environmental analysis of these feedgrounds was issued. GYC argues the claims fall within the voluntary cessation exception to the mootness doctrine.
“Under Article III of the Constitution, federal courts may adjudicate only actual, ongoing cases or controversies.”
Lewis v. Cont’l Bank Corp.,
An exception to the mootness doctrine can occur when a defendant voluntarily ceases a challenged action.
ARW Exploration Corp. v. Aguirre,
GYC brought this action alleging the lack of environmental analyses for the six feedgrounds in question violated NEPA. GYC sought to compel the Forest Service to undertake environmental analyses of the feedgrounds, including the test-and-slaughter program at Muddy Creek, to address current disease risks. The Forest Service did exactly this in its July 2008 environmental analysis. Thus, no live controversy exists with regard to these feed-grounds.
As to GYC’s contention that the Forest Service’s actions fall within the voluntary cessation exception to the mootness doctrine, there is no reasonable expectation the alleged wrongs involving the six feed-grounds in question will be repeated. The Forest Service has issued an environmental analysis addressing the threat of disease at these feedgrounds. It is thus impossible for the Forest Service to return to its allegedly illegal conduct of failing to conduct an environmental analysis addressing the brucellosis and chronic wasting disease risks at these feedgrounds. Because these issues became moot as a result of the unilateral activity of the Forest Service, however, vacatur is appropriate.
See Arizonans for Official English,
B. The Forest Park and Dell Creek Forest Service Feedgrounds
GYC has live claims as to the Forest Park and Dell Creek Forest Service feed-grounds. NEPA requires an environmen-
1. Forest Park
The last environmental analysis of the Forest Park feedground occurred in 1980. Under
GYC contends circumstances have changed since the 1980 Forest Park environmental analysis as a result of the discovery of the brucellosis and chronic wasting disease threats at feedgrounds, and thus the Forest Service must undertake a supplemental analysis to address these changes. The Forest Service points out that the duty to supplement an environmental analysis under NEPA ends after the major federal action is completed, and alleges the major federal action here was completed when the permit was issued. According to GYC, however, the elk feeding activities constitute an “ongoing” major federal action under NEPA because the Forest Park permit states it “may be amended in whole or in part by the Forest Service when, at the discretion of the authorized officer, such action is deemed necessary or desirable to incorporate new terms, conditions, and stipulations as may be required by law, regulation, land management plans, or other management decisions.”
In
Norton v. Southern Utah Wilderness Alliance,
the Supreme Court considered whether there was major federal action to occur or ongoing major federal action when allegedly new circumstances arose after BLM approved a land use plan for federal lands it administered in Utah.
that condition was met: The dam construction project that gave rise to environmental review was not yet completed. Here, by contrast, although the “approval of a [land use plan]” is a “major Federal action” requiring an EIS ... that action is completed when theplan is approved. The land use plan is the “proposed action” contemplated by [NEPA]. There is no ongoing “major Federal action” that could require supplementation ....
Id.
at 73,
Here, the Forest Service’s approval and issuance of the Forest Park permit, like BLM’s approval of the land use plan in
Norton,
was the major federal action contemplated by NEPA. Under
Norton,
that major federal action was completed when the permit was approved and issued.
See also Cold Mountain v. Garber,
2. Dell Creek
The Forest Service has never conducted an environmental analysis of the Dell Creek feedground. NEPA’s implementing regulations state major federal actions may include “new and continuing activities, including projects and programs entirely or partly financed, assisted, conducted, regulated, or approved by federal agencies.”
GYC relies heavily on this court’s statement in
Hart
that, “as long as agency decisions remain to be made or are open to revision, [NEPA] should be applied.”
Id.
at 1181. This statement, however, merely summarizes the holdings of two cases from other circuits in which the courts also were faced with whether or not to apply NEPA to major agency actions ongoing at the time NEPA became effective.
Id.
The courts in those cases concluded that for projects ongoing at the time of NEPA’s passage, Congress intended NEPA to apply unless the project had reached a stage of completion such that NEPA’s application could be considered a retroactive application not intended by Congress.
Swain v. Brinegar,
In the second case relied upon by GYC,
Morris County Trust for Historic Preservation v. Pierce,
HUD approved an urban renewal plan and entered into a loan and capital grant contract, again prior to the passage of NEPA.
The cases cited by GYC stand only for the proposition that if an agency began a project prior to the passage of NEPA, that alone would not shield the agency from NEPA compliance if the agency
remained meaningfully involved
in the project after NEPA became effective. They are not, however, authority for the existence of a major federal action merely because an agency retains a degree of discretion in a project. The district court was thus correct when it opined that “it would be a
More relevant to this analysis is
Norton v. Southern Utah Wilderness Alliance,
C. The BLM feedgrounds
In 1981, BLM and Wyoming entered into an MOU. The MOU stated its purpose was “to recognize and coordinate management of those winter elk feeding programs which impact Federal surface and/or mineral estates in Sublette County, Wyoming.” The agreement set forth the objectives and operating procedures of both agencies. BLM agreed to “[a]uthorize, through legal authority and this Memorandum, the continued use of existing facilities falling on public lands ■ [by Wyoming].” It also agreed to “[a]llow- [Wyoming] to maintain, reconstruct, or construct access roads, trails, facilities, etc., as mutually deemed necessary by [BLM] and [Wyoming].” An environmental analysis of the feedgrounds was prepared in connection with the MOU.
GYC claims NEPA demands an environmental analysis of disease threats related to the four BLM elk feedgrounds. GYC argues BLM’s failure to issue permits for the use of the affected federal lands in contravention of
(b) Contracts and cooperative agreements
Subject to the provisions of applicable law, the Secretary may enter into contracts and cooperative agreements involving the management, protection, development, and sale of public lands.
43 C.F.R. §§ 2920.1-1 , 1-2 provide- in relevant part:
§ 2920.1-1 Authorized Use Any use not specifically authorized'under other laws or regulations and not specifically forbidden by law may be authorized under this Part. Uses which may be authorized include residential, agricultural, industrial, and commercial, and uses that cannot be authorized under title V of [FLPMA] ... Land use authorizations shall be granted under the following categories:
(b) Permits shall be used to authorize uses of public lands for not to exceed 3 years that involve either little or no land improvement, construction, or investment. ...
§ 2920.1-2 Unauthorized Use (a) Any use, occupancy, or development of the public lands, other than casual use as defined in § 2920.0-5(k) of this title, without authorization under the procedures in§ 2920.1-1 of this title, shall be considered a trespass.
According to GYC, because agreements authorized under
The permitting regulations cited by GYC,
In managing the public lands, [BLM] shall, subject to this Act and other applicable law and under such terms and conditions as are consistent with such law, regulate, through easements, permits, leases, licenses, published rules, or other instruments as [BLM] deems appropriate, the use, occupancy, and development of the public lands ... Provided, That unless otherwise provided for by law, [BLM] may permit ... where the proposed use and development are similar or closely related to the programs of [BLM] for the public lands involved, cooperative agreements undersection 1737(b) of this title.
Moreover, an alternative reading would render
In light of the statute’s structure, the most likely purpose of the phrase “Subject to the provisions of applicable law” at the beginning of
Even assuming the phrase “Subject to the provisions of applicable law” creates ambiguity as to whether the permitting regulations must be followed when cooperative agreements are used, the statute’s legislative history further supports Respondents’ position.
United States v. Manning,
The Committee expects the Secretary of the Interior to use this authority whenever contracting or eooperativé agreements would be the more feasible or economical way to accomplish the purposes of this bill. These advantages would be particularly true where States and local government entities have competent organizations in being which could effectively carry out the Secretary’s programs. Examples of the types of activities which might be handled in this manner include, among others, fire prevention and suppression, law and regulation enforcement, supervision of the range especially in intermingled land areas, and construction of facilities.
H. Rep. No. 94-1163, at 16 (1976), as
reprinted in
1976 U.S.C.C.A.N. 6175, 6190. The House Report would not have called cooperative agreements
“more
feasible or economical” except in comparison to the procedure for allowing all other uses on public lands, i.-e.,
GYC asserts the MOU’s authorization of feedgrounds “through
legal authority
and this Memorandum,” means the MOU is not self-executing, but instead acknowledges the need for additional legal authority, i.e., a
Finally, GYC argues that even assuming the MOU properly authorized the feedgrounds, this is an ongoing major federal action requiring a supplemental analysis under NEPA due to changed circumstances. The federal action is ongoing, GYC contends, because the MOU provides BLM will review the MOU for “operating efficiency” annually and BLM may renegotiate the MOU based on the outcome of that review. As with the Forest Service permits discussed above, the major federal action here occurred when BLM entered into the MOU. That BLM reviews the MOU yearly and has the discretion to renegotiate does not by itself establish a continuing federal action.
See Norton,
Thus, we conclude BLM’s actions with regard to the four Wyoming feedgrounds in question were not arbitrary, capricious, an abuse of discretion, or otherwise not in accordance with law and affirm the district court’s denial of GYC’s request to compel BLM to undertake environmental analyses of these feedgrounds.
IV. CONCLUSION
GYC’s claims as to the six feedgrounds included in the July 2008 environmental analysis are moot. We therefore vacate the portions of the district court opinion addressing those feedgrounds. We affirm the decision of the district- court as to GYC’s remaining claims.
Notes
. We use the broad term “environmental analysis” to refer to both Environmental Assessments and Environmental Impact Statements because the differences are not significant for purposes of this decision.
. Long-term authorization was also granted at that time for the Upper Green River feed-ground.
. There is a six-year statute of limitations pursuant to
. GYC’s citation to a 2005 email indicating the Forest Service approved a request from Wyoming to build a small holding pen on the Dell Creek feedground does not change this analysis. This was a minor change initiated by Wyoming and merely approved by the Forest Service. There is no evidence the permit was formally amended. Nor was it a situation where the Forest Service attempted to influence the project in any material manner pursuant to the discretion given by the permit. Finally, there is no assertion that the approval of the holding pen itself was a major federal action.
See Citizens Organized to Defend the Env’t, Inc. v. Volpe,