DECISION AND ORDER
Greater Eastern Transport (“GET”) brought this action, invoking the Court’s diversity jurisdiction under 28 U.S.C. § 1332, against Waste Management of Connecticut, Inc. (“Waste Management”) alleging breach of contract and breach of the implied duty of good faith and fair dealing. Waste Management asserted counterclaims for breach of contract and breach of the implied duty of good faith and fair dealing and now moves for summary judgment pursuant to Federal Rule of Civil Procedure 56(c). For the reasons set forth below, Waste Management’s motion is granted in part and denied in part.
I. BACKGROUND
On or about August 30, 1999, Waste Management and GET entered into a subcontractor service agreement. (Subcontractor Service Agreement, dated Aug. 30, 1999 (“Agreement”), Declaration of Clay J. Pierce, dated May 13, 2002 (“Pierce’s Deck”), Ex. A.) Under the Agreement, GET undertook to transport waste, at a rate of $14.25 per ton, from the municipal waste transfer station in Stamford, Connecticut, which is operated by Waste Management, to various disposal sites designated by Waste Management, including Peekskill, New York, and Essex County, New Jersey. (Agreement ¶¶ 1, 9.) The contract was for a term of five years and contained the following termination clause:
In the event [Waste Management] no longer utilizes its Stamford transfer station for transferring Waste, [Waste Management] may terminate this agreement upon thirty (30) days prior written notice; or upon ninety days prior written notice to GET. This agreement may not otherwise be terminated except as set forth above.
(Agreement ¶ 11.)
The Agreement entitled Waste Management to designate “additional disposal facilities, and additional transfer stations in Connecticut provided that an equitable adjustment be made in the per ton rate as set forth below.” (Agreement ¶ 1.) Such an equitable adjustment was to be negotiated “in good faith ... based on the change in actual over the road miles.” (Agreement ¶ 9.) The Agreement also provided for an annual price adjustment in the transport rate based on the percentage change in the Consumer Price Index (“CPI”). (Agreement ¶ 9.)
In the Spring of 2000, Waste Management instructed GET to deliver waste to a facility in Scranton, Pennsylvania. (Id. at ¶ 15.) Negotiations over an equitable adjustment to the rate for transporting the waste to this site failed. (Id. at ¶ 20.) On or about May 10, 2000, Waste Management, without providing notice to GET, placed drivers and truck tractors from another company called Upstate (“Upstate”), one of GET’s competitors, at the Stamford transfer station and instructed GET only to load the trailers at a rate of $4.00 per ton and not to transport the waste. (See id. at ¶¶ 21-25.) In a letter dated June 8, 2000, Waste Management gave GET ninety days notice that it was terminating the Agreement effective September 11, 2000. (Id. at ¶ 26; Letter from Paul Penograth to Martin Sternberg, dated June 8, 2000 (“Termination Letter”), Pierce’s Decl., Ex. F.)
On June 30, 2000, GET filed its complaint in this action, alleging that Waste Management breached the contract and the implied duty of good faith and fair dealing when it (1) refused to negotiate a reasonable rate for transferring waste to the Scranton, Pennsylvania transfer station; (2) placed the Upstate drivers at the Stamford transfer station; 1 and (3) terminated the contract with the Termination Letter. (Id. at ¶¶ 28-37.) In its Answer dated August 28, 2000, Waste Management asserted counterclaims for breach of contract and of the implied duty of good faith and fair dealing. (Answer ¶¶. 12-17.) Waste Management- now moves for summary judgment pursuant to Federal Rule of Civil Procedure 56(c).
Waste Management contends that “the clear- language of the Agreement gave Waste Management the right to terminate it upon ninety days prior written notice.” (Defendant’s Memorandum of Law in Support of Motion for Summary Judgment, dated Apr. 5, 2002 (“Def.’s Mem.”), at 6.) It further argues that the Agreement became an “unenforceable agreement to agree” when Waste Management added the Scranton, Pennsylvania facility. (Id. at 16 (internal quotations omitted).) Finally, Waste Management argues. that GET is barred from recovering lost profits. (Id.)
GET counters that the-agreement is ambiguous and that the Court therefore must examine extrinsic evidence. GET claims this evidence demonstrates that Waste Management did not have the right to terminate the contract upon ninety days prior written notice. (Plaintiffs Memorandum of Law in Opposition to Defendant’s Motion for Summary Judgment, dated May 13, 2002 (“Pl.’s Mem.”), at 9-12.) GET further argues that the Agreement has clear language providing a basis for determining the rate for transporting waste to an additional disposal facility and that the Agreement therefore is not indefinite. (Id. at 14-16.)
II. DISCUSSION
A. CHOICE OF LAW
Because the Court’s jurisdiction in this action is based on diversity of citizen
B. STANDARD OF REVIEW
A motion for summary judgment may be granted only if there is no genuine issue as to any material fact and the moving party is entitled to judgment as a matter of law.
See
Fed.R.Civ.P. 56(c);
Celotex Corp. v. Catrett,
C. TERMINATION PROVISION
Waste Management moves to dismiss the third count of GET’s complaint, claiming that the Agreement allowed Waste Management to terminate the contract for any reason upon ninety days prior written notice. (Def.’s Mem. at 6.) The Court grants this part of Waste Management’s motion. Under Connecticut law:
A contract must be construed to effectuate the intent of the parties, which is determined from the language used interpreted in the light of the situation of the parties and the circumstances connected with the transaction. [T]he intent of the parties is to be ascertained by a fair and reasonable construction of the written words and the language used must be accorded its common, natural, and ordinary meaning and usage where it can be sensibly applied to the subject matter of the contract .... [A]ny ambiguity in a contract must emanate from the language used in the contract rather than from one party’s subjective perception of the terms.
Tallmadge Bros. Inc.,
GET explains that the thirty-day and ninety-day termination provisions are in direct conflict due to a drafting error that renders the entire clause ambiguous, and argues that the Court therefore should examine extrinsic evidence in ascertaining the meaning of the contract and the parties’ intent. (Pl.’s Mem. at 5, 9-11.)
See Lee v. BSB Greenwich Mortgage Ltd. P’ship,
The ambiguity GET alleges does not “emanate from the language of the agreement,” but from GET’s “subjective interpretation of that language.”
Tallmadge Bros. Inc.,
The use of the word “or” before the ninety-day termination provision indicates that it expresses an alternative to the preceding thirty-day termination provision. The Oxford English Dictionary defines “or” as, “a particle co-ordinating two (or more) ... clauses, between which there is an alternative.” 10 Oxford English Dictionary 882 (2d ed.1989). In the instant case, the alternative is between two termination provisions, one conditional on Waste Management no longer using the Stamford facility, the other not.
The punctuation of the clause also indicates that there are two separate termination provisions. As one court noted:
While the presence or absence of punctuation, generally cannot control the construction of plain language, once the sense of a contract has been gathered from its language, punctuation may be more readily used to assist in reading the contract to effectuate the contract purposes of the parties and to confirm its meaning.
Shoreline Care Ltd. v. Town of North Branford,
No. CV-92-03316958, 1993 WL
Here, the semicolon before the phrase “or upon ninety days prior written notice” indicates that the clause is independent from that which precedes it.
See Amusement Consultants, Ltd. v. Hartford Life Ins. Co.,
This construction of the Termination Clause presents two methods of ending the contract and thus gives effect to the entire provision and the parties’ expectations on the basis of the contract language itself.
See Tallmadge Bros. Inc.,
GET’s reading, on the other hand, requires a determination that effectively nullifies some language of the Agreement as either meaningless or surplusage, and to that extent, solely on the basis of one party’s subjective interpretation, frustrates a plausible construction of the entire clause and the expectations associated with such a complete provision.
See Tallmadge Bros. Inc.,
Accordingly, the Court concludes that the plain language of the contract provides two separate termination provisions: one which is applicable if Waste Management continues to operate the Stamford facility, the other which is applicable if it does not; and that Waste Management therefore properly terminated the contract with the Termination Letter. Waste Management’s motion for summary judgment is granted with respect to the third count of GET’s complaint. 3
D. AGREEMENT TO AGREE
Waste Management moves to dismiss the first two counts of the Complaint, claiming that the contract became an unenforceable “agreement to agree” upon Waste Management’s attempt to add the Scranton, Pennsylvania transport site. (Def.’s Mem. at 16.) The Court denies this part of Waste Management’s motion.
There is a presumption that the language used by sophisticated commercial parties, such as the parties in this case, is definitive.
See United Illuminating Co.,
The Agreement’s provision regarding the designation of additional disposal facilities is not indefinite both because the parties have previously acted upon it and because the Agreement provides an objective method for determining the transport rate for the Scranton facility. In the Fall of 1999, Waste Management specified an additional disposal facility in Bridgeport, Connecticut, to which GET transported waste “at a rate lower than $14.25/ton because of the relatively short distance between Stamford and Bridgeport.” (Complaint ¶ 14.) Waste Management also requested that GET haul waste to the Harlem River Railyard in the Bronx, New York, which GET did at a rate of $14.25/ ton “because the distance and time required to transport trailers to the Bronx approximated the time required to ship to Peekskill or Essex County.”
(Id.)
Waste Management presents no reason why the standards that served the parties in reaching agreement with respect to transport of waste to the other additional facilities were
Moreover, the Agreement is enforceable because it provides an objective method for determining rates for transporting waste to new facilities.
Compare Meaney,
E. DAMAGES
Waste Management further argues that there can be no recovery for the lost profits resulting from any breach prior to its termination of the contract because “the damages are too speculative to be recovered.” (Def.’s Mem. at 18.) The Court denies this part of Waste Management’s motion because it has found that the contract terms were not indefinite and that there is a reasonable mechanism for determining the price for added facilities.
See Torosyan v. Boehringer Ingelheim Pharm.,
The Court agrees with Waste Management, however, that “any damages resulting from [any] breaches would be cut off as of the effective date of the termination.” (Pl.’s Mem. at 6 n. 3.) GET cannot recover damages for any time beyond Waste Management’s valid termination of the contract because GET elected to continue in the contract. The contract therefore was not terminated by Waste Management’s alleged breach. As another court in this district noted:
When a party materially breaches a contract, the non-breaching party must choose between two remedies- — he can elect to terminate the contract and recover liquidated damages or he can continue the contract and recover damages solely for the breach. A party can indicate that he has chosen to continue the contract by continuing to perform under the contract or by accepting the performance of the breaching party. Once a party elects to continue the contract, he can never thereafter elect to terminate the contract based on that breach although he retains the option of terminating the contract based on other, subsequent breaches.
Because GET continued to perform and accept Waste Management’s performance after the first alleged breach, GET cannot now terminate upon that breach. The contract was finally terminated by Waste Management’s Termination Letter. Therefore, GET can recover damages only in an amount equal to the contract value less the amount actually paid, for the time between the first alleged breach and September 11, 2000, when Waste Management properly terminated the contract.
See Silver v. I Goldberg & Partners, Inc.,
No. 92 Civ. 6989(HB),
Accordingly, Waste Management’s motion to limit any damages recoverable by GET to the period between any alleged breach and September 11, 2000, when Waste Management properly terminated the contract, is granted.
III. CONCLUSION AND ORDER
For the reasons set forth above, it is hereby
ORDERED that Defendant’s motion for summary judgment on the applicability of the ninety-day termination provision in the contract herein is GRANTED; and it is further
ORDERED that Defendant’s motion for summary judgment on the unenforceability of the contract is DENIED; and it is further
ORDERED that Defendant’s motion to limit damages as specified herein is GRANTED.
SO ORDERED.
Notes
. GET's contention of ambiguity does not, in and of itself, establish that the provision is ambiguous.
See United Illuminating Co.,
. There was no semicolon in the contract, and the court therefore found that the phrase "active full time” modified each term in the list. See id.
. Waste Management admits that it gave ninety days notice only after the acts alleged in Counts (1) and (2). (Def.'s Mem. at 6 n. 3.) The Court considers the motion to dismiss the first two counts below.
