90 Ct. Cl. 232 | Ct. Cl. | 1940
delivered the opinion of the court:
Upon the facts presented by the record in this case and set forth in the findings, we are of opinion that plaintiff should not have been charged with penalties for delay in the delivery of the radio transmitting equipment specified in the contract of December 10, 1935, and that it is entitled
We can hardly imagine a more justifiable cause for the contractor’s delay in promptly manufacturing and delivering the equipment than arose in this case. It was certainly unforeseeable by plaintiff and was beyond its control and without its fault or negligence. It was certainly due to acts of the Government.
We are not here concerned with any question of breach of the contract, but only with the question whether plaintiff or defendant should be held responsible for delay in performance within the time specified. It is well settled that where one of the parties to a contract demands strict performance as to time by the other party, it must comply with all the conditions requisite to enable the other party to perform his part, and a failure on the part of the one demanding performance to do that which it required of him (in this case to assure plaintiff that it would pay for what it bought) to enable the other party to perform without hindrance or delay within the time limit operates as a waiver of the time provisions of the contract. Ittner v. United States, 43 C. Cls. 336; The New Jersey Foundry & Machine Company v. United States, 44 C. Cls. 178; American Dredging Company v. United States, 49 C. Cls. 350; The United Engineering and Contracting Company v. United States, 47 C. Cls. 489, affirmed 234 U. S. 236. In the case last cited, it was held that “Here the delays of the Government prevented the claimant from a strict performance, and thereby it waived the contract time within which to perform, and that waiver operated to eliminate the definite date from which to assess liquidated damages; and though the claimant in continuing the work was thereby obligated to complete the same within a reasonable time the liquidated damage clause was not thereby restored and made applicable to an unreasonable time.” In case of failure to complete within a reasonable time, the Government, having delayed the contractor, would be limited in its claim to actual damages. The contractor in the case at bar completed the work within a reasonable time after it was given assur-
Plaintiff is entitled to recover and judgment in its favor for $13,692.20 will be entered. It is so ordered.