54 Mo. App. 666 | Mo. Ct. App. | 1893
— This action is for damages for injury to a steam shovel carried by respondent from St. Louis to Delta, Mo.
The damages prayed for are: (1) For the delay in the prosecution of certain work contracted to be done by appellant, of which it' is alleged respondent had knowledge; (2) Loss of the use of said steam shovel and expenses of repair thereof, and expenses of hire of laborers while it was undergoing repairs, and ge'neral loss of profits.
The answer of respondent contains a general denial, and a special defense that the injury to the steam shovel was caused by appellant’s conduct in loading same at too great a height to clear a tunnel on respondent’s line of railway through which it must pass, and misrepresenting this fact to respondent.
The evidence was conflicting as to the height of the Glenn Allen tunnel, where the shipment was injured. Appellant’s evidence tending to show that he was informed by the engineer of the respondent that' the height of this tunnel was 16 feet and 7 inches above the
The evidence of the appellant was that he had an agreement with the general freight agent of the respondent for the shipment of the shovel, and received a bill of lading therefor. In reply to a question as to what information he gave the freight agent the appellant replied: “I told him I had got a contract with the Houck road, and wanted to ship it down, and wanted a special rate, and he gave it to me.”
There was no dispute that the shovel was injured by colliding with the upper walls of Grlenn Allen tunnel, and that it was delivered in a damaged state. The evidence tended to show that the appellant took his shovel to Cape Grirardeau, and, having repaired it, then brought it back to Puxeco cut, where it was employed by him in excavating earth for several months; that it became disabled on October 7th, necessitating its being sent to St. Louis, and, after having been there repaired, it was returned and used by appellant until the completion of his work in January, 1890. The work in which the shovel was used was begun under a contract between appellant and the Cape Grirardeau & Northwestern Railway Company, made on April 14, 1890, which provided for the payment to the appellant of seven cents per cubic yard for all “dirt” loaded on cars by him and removed by the company. After operating under this contract more than two months, the appellant made a supplemental contract (under which he completed his work) with
The time occupied in the first repairs of the shovel at Cape Girardeau on June 21, 1890, was about two or three days. "When it was finally repaired in St. Louis on October 7, 1890, a delay of eighteen and one-half days supervened before it was returned. There was evidence tending to show the costs of these repairs and of the prices paid certain laborers, who were idle during these repairs, by appellant; also the profits which he could have earned during these delays, if his shovel had been employed under the two contracts with the Cape Girardeau & Southwestern Railway Company.
Upon the evidence and instructions, the jury found for plaintiff in the sum of $460. A motion for new trial made by the respondent was sustained by the court, which assigned the following reasons for granting the new trial:
“I am of opinion that the instruction given for plaintiff as to the measure of damages is erroneous. It was the purpose of that instruction to tell the jury to award plaintiff, among other things, the value of the use of the machine while undergoing repairs. But the language used, when carefully considered, does not*670 confine the jury to the value of the use of the machine, but tells the jury, to award plaintiff the damages he suffered by being deprived of the use. This left the jury at .liberty to adopt their own view of what constituted plaintiff’s loss arising from not being able to use the machine — in fact it gave them no rule at all to guide them in determining what were the elements - constituting his legal damages.”
The part of the instruction thus referred to stated the rule as to the damages as follows, to-wit:
"First. In such sum as they find from the evidence it reasonably cost plaintiff, to put said shovel in as good condition as it was at the time defendant received it, and,
“ Second. If they find that plaintiff had entered upon a contract to do work, and was shipping said shovel to Delta for that purpose, and that defendant’s agents knew that plaintiff was shipping said shovel to Delta to be used upon such work, then they will find, as additional damage, the sum plaintiff lost by being deprived of the use of said shovel for the time it was idle while-being repaired.”
Prom this action of- the court, appellant brings the case to this court under the act of 1891, authorizing an appeal from an order granting a new trial. Session Acts, 1891, page 70.
While the only error now assigned is the action of the trial court in granting the new trial for the reason stated by him in making that order, yet we are not confined to a consideration of that ground alone, but have the right to examine all the grounds stated in respondent’s motion for new trial in the light of the record before us; and, if we findthat the trial, judge should have granted the new trial for any of these reasons other than that given by him, it is our duty to affirm his ruling.