Lead Opinion
[¶ 1] Grаtech Company, Ltd., (“Gra-tech”) appeals the district court’s judgment confirming an arbitration award in favor of Wold Engineering, P.C., (“Wold”) and against Gratech. Wold cross-appeals that part of the district court’s judgment denying it attorney’s fees. We hold that the district court’s order confirming the arbitration award was proper because the arbitration award was neither completely irrational nor evidenced a manifest disregard for the law. We hold that a district court must provide its rationale for its decision on a request for attorney’s fees so that this Court can properly review whether there was an abuse of discretion. Therefore, we affirm the district court’s judgment confirming an arbitration award in favor of Wold, and reverse and remand that part of the judgment denying Wold attorney’s fees for the district court to explain its reasoning.
I
[¶ 2] Gratech entered into a contract with the North Dakota Department of Transportation (“NDDOT”) on August 18, 1997, to work on U.S. Highway 281 in Rolette County. Wold entered into a subcontract with the NDDOT on April 9,1998, to perform enginеering work on the U.S. Highway 281 project.
[¶ 3] Gratech encountered poor soil conditions, which required additional sub-cutting, plowing, discing, and drying of the soil. Gratech requested additional compensation from the NDDOT. When the NDDOT denied Gratech’s claim for additional compensation, Gratech filed a demand for arbitration. The arbitration panel сoncluded Gratech’s failure to file a written notice of claim precluded arbitration of all but one of Gratech’s claims against the NDDOT. This Court, in Gratech Co. v. North Dakota Dep’t of Transp.,
[¶ 4] In a complaint against Wold dated April 11, 2002, Gratech alleged breach of duty, bad faith, misconstruction of a contract, negligent misrepresentation, and deceit. Gratech, in its complaint, claimed Wold, contrary to the contract, classified plowing, discing, and drying as unplanned subcuts, or incidental work, and refused to pay for them. Purportedly unknown to
[¶ 5] Wold answered on May 16, 2002, seeking dismissal of Gratech’s complaint, attorney’s fеes, and a jury trial. On February 18, 2003, Wold moved for summary judgment, claiming Gratech’s claims were barred by res judicata or collateral estop-pel, or alternatively, Gratech was required to arbitrate all claims. Gratech moved for partial summary judgment on liability. The district court granted Wold’s motion and denied Gratech’s motion. In Gratech Co. v. Wold Engineering, P.C.,
[¶ 6] Subsequently, Gratech filed a demand for arbitration against Wold. On April 7, 2005, Wold moved for summary disposition of the arbitration proceedings based on res judicata, collateral estoppel, statute of limitations, and exclusivity of remedy. The motion was denied by the arbitrator, although he found Wold had satisfied the second, third, and fourth elements of collateral estoppel. The arbitrator determined the first element of collateral estoppel had not been established, as a matter of law and, therefore, required an evidentiary hearing. Following a four day hearing, on January 11, 2006, the arbitrator awarded Gratech nothing on its claims against Wоld, but awarded Wold costs. In his explanation of the award, the arbitrator stated that the claim was barred by res judicata and collateral estoppel. The arbitrator found that “the facts giving rise to Gratech’s claim in the first arbitration against ND/DOT are the same in this, the second arbitration.”
[¶ 7] On January 13, 2006, Gratech moved to vacate the arbitratiоn award and sought a new arbitrator. Wold moved to have the arbitration award confirmed. On September 13, 2006, the district court denied Gratech’s motion to vacate the arbitration award. The district court entered judgment confirming the arbitrator’s award in favor of Wold, but denying Wold’s request for attorney’s fees. Gra-tech appeals the district court’s judgment confirming the arbitration award and Wold cross-appeals that part of the district court’s judgment denying it attorney’s fees.
II
[¶ 8] Gratech argues the district court’s judgment confirming the arbitration award in favor of Wold should be reversed and the arbitration award vacated because the arbitration award was completely irrational, or alternatively, evidences a manifest disregard for the law. This Court has said before, “without a transcript, we would not be able to conduct a meaningful review of the ... factual findings.” Superpumper, Inc. v. Nerland Oil, Inc.,
[¶ 9] Gratech relies on N.D.C.C. § 32-29.3-23 to support its claim that the arbitration award should be vacated.
1. Upon motion to the court by a party to an arbitration proceeding, the court shall vacate an award made in the arbitration proceeding if:
[[Image here]]
d. An arbitrator exceeded the arbitrator’s powers;
[[Image here]]
3 .... If the award is vacated on a ground stated in subdivision ... d ... of subsection 1, the rehearing may be before the arbitrator who made the award or the arbitrator’s successor.
N.D.C.C. § 32-29.3-23.
[¶ 10] In Nelson Paving Co. v. Hjelle,
[¶ 11] In Scherbenske Excavating, Inc. v. North Dakota State Highway Dep’t,
Obviously, the effect of applying the clearly irrational standard of review is to give to the arbitrators every benefit of every doubt. It affords them the widest latitude to exercise their authority and arrive at their decision without the customary restraints of traditional judicial review. It is but a reflection of the strong public policy favoring the arbitration process. We find no reasons compelling or persuasive enough to warrant revising the completely irrational standard of review and therefore we decline to overrule or modify Nelson Paving.
Scherbenske,
[¶ 12] The Court of Appeals for the Eighth Circuit has adopted an expanded standard of review. “We have allowеd that, beyond the grounds for vacation pro
[¶ 13] “Arbitration is not a рerfect system of justice, nor [is it] designed to be.” Hoffman,
[¶ 14] Grаtech argues the arbitrator manifestly disregarded the law on collateral estoppel. “Collateral estoppel bars relitigation of issues which were necessarily litigated and decided, or which by implication must have been litigated and decided, in a prior action.” Riverwood Commercial Park v. Standard Oil Co.,
Four tests must be met before collateral estoppel will bar relitigation of a fact or issue involved in an earlier lawsuit: (1) Was the issue decided in the prior adjudication identical to the one presented in the action in question?; (2) Was there a final judgment on the merits?; (3) Was the party against whom the plea is asserted a party or in privity with a party to the prior adjudication?; and (4) Was the party against whom the plea is asserted given a fair opportunity to be heard on the issue?
Id.
“[0]nly parties or their privies may take advantage of or be bound by the former judgment.” Id. “In general, privity exists if a person is so identified in interest with another that he represents the same legal right.” Id. “Fundamental fairness underlies any determination of privity.” Id.
[¶ 15] Gratech contends we should adopt the standard of review adopted by the Court of Appeals for the Eighth Circuit. This case is not one in which this Court needs to address a change in the applicable standard of review because under eithеr the completely irrational standard or the manifest disregard for the law standard, we would affirm the district
Ill
[¶ 16] Wold cross-appeals, arguing that the district court improperly denied its request for attorney’s fees without any explanation. Wold contends that the district court’s judgment should be remanded as it pertains to attorney’s fees so that the district court can provide an explanation for its decision to deny attorney’s fees, or if appropriate, award attorney’s fees.
[¶ 17] A successful litigant is not entitled to attorney’s fees unless they are expressly authorized by statute or by agreement of the parties. In re Estate of Lutz,
•On application of a prevailing party to a contested judicial proceeding under section 32-29.3-22, 32-29.3-23, or 32-29.3-24, the court may add reasonable аttorney’s fees and other reasonable expenses of litigation incurred in a judicial proceeding after the award is made to a judgment confirming, vacating without directing a rehearing, modifying, or correcting an award.
This section specifically provides that a district court may award attorney’s fees incurred in a judicial procеeding. In this case, the district court had the discretion to award or not award attorney’s fees to Wold.
[¶ 18] This Court reviews a district court’s decision regarding attorney’s fees under the abuse of discretion standard. City of Medora v. Golberg,
[¶ 19] Whether this Court reviews the reasonableness of attorney’s fees under Rule 52 of the North Dakota Rules of Civil Procedure or under the abuse of discretion standard, facts are required. City of Bismarck v. Thom,
IV
[¶ 21] We affirm the district court’s judgment confirming the arbitration award in favor of Wold and reverse and remand for a redetermination of attorney’s fees based on an expressed rationale.
Concurrence Opinion
concurring in part and dissenting in part.
[¶24] I join in the majority’s affir-mance of the district court’s judgment confirming the arbitrator’s award. I would also affirm the district court’s denial of attorney fees. Section 32-29.3-25(3), N.D.C.C., provides:
On application of a prevailing party to a contested judicial proceeding under section 32-29.3-22, 32-29.3-23, or 32-29.3-24, the court may add reasonable attorney’s feеs and other reasonable expenses of litigation incurred in a judicial proceeding after the award is made to a judgment confirming, vacating without directing a rehearing, modifying, or correcting an award.
The award of attorney fees to a prevailing party is not mandatory, but discretionary, under this statute. In the cases cited by the majority, аttorney fees were awarded in litigation, either for unexplained or inappropriate reasons, or the awards were measured by inappropriate standards. City of Medora v. Golberg,
