Granholm, Jennifer M v. FERCGranholm, Jennifer M v. FERC
Jennifer M. GRANHOLM ex rel. Michigan Department of Natural
Resources, Petitioner,
v.
FEDERAL ENERGY REGULATORY COMMISSION, Respondent.
Upper Peninsula Power Company, Intervenor.
No. 98-1276.
United States Court of Appeals,
District of Columbia Circuit.
Argued May 4, 1999.
Decided June 11, 1999.
On Petition for Review of Orders of the Federal Energy Regulatory Commission.
Pamela J. Stevenson, Assistant Attorney General, State of Michigan, argued the cause for petitioner. With her on the briefs were Thomas L. Casey, Solicitor General, and Alan F. Hoffman, Assistant Attorney General. John C. Scherbarth, Assistant Attorney General, entered an appearance.
David H. Coffman, Attorney, Federal Energy Regulatory Commission, argued the cause for respondent. With him on the brief was Jay L. Witkin, Solicitor.
Amy S. Koch and Linda C. Ray were on the brief for intervenor Upper Peninsula Power Company.
Before: GINSBURG, SENTELLE, and RANDOLPH, Circuit Judges.
Opinion for the Court filed by Circuit Judge RANDOLPH.
RANDOLPH, Circuit Judge:
Michigan's Attorney General, on behalf of the state's Department of Natural Resources, filed a petition for judicial review of three Federal Energy Regulatory Commission orders issued in connection with an application by the Mead Corporation for a hydroelectric power license. We hold that Michigan's failure to seek rehearing of the Commission's "Order on Remand" deprives the court of jurisdiction.
This proceeding has its genesis in orders the Commission issued in 1995 and 1996. In Mead Corp., 72 F.E.R.C.p 61,027 (1995), the Commission granted Mead's application for a new license to continue operation and maintenance of a hydroelectric power project in Michigan under Part I of the Federal Power Act,
Michigan sought rehearing, asserting that the Commission should have considered the Michigan recommendations under § 10(j). In Mead Corp., 76 F.E.R.C. p 61,352 (1996), the Commission denied rehearing after reiterating that Michigan's recommendations were not subject to § 10(j), and that the public interest did not require performance of those studies.
Michigan then sought judicial review of the 1995 and 1996 orders in this court. The case was docketed as No. 96-1453, but on August 5, 1997, after Michigan submitted its initial brief, the Commission filed an unopposed motion for voluntary remand so that the Commission could reconsider whether it should have reviewed Michigan's recommendations under § 10(j). The Commission's motion was prompted, in part, by this court's intervening decision in Kelley v. FERC,
On April 22, 1998, the Commission issued its "Order on Remand," Upper Peninsula Power Co., 83 F.E.R.C. p 61,071, at 61,362 (1998) ("remand order")1, further elucidating, but adhering to, its prior ruling. Without seeking rehearing of the remand order, Michigan petitioned for judicial review of the 1995, 1996, and 1998 orders, contending once again that the Commission erred in considering Michigan's recommendations under § 10(a) rather than the more deferential § 10(j).
On July 30, 1998, the Commission moved to dismiss for lack of jurisdiction on the ground that Michigan failed to seek rehearing of the remand order as required by § 313(a) of the Federal Power Act,
Section 313(a) of the Federal Power Act provides that "[n]o proceeding to review any order of the Commission shall be brought by any person unless such person shall have made application to the Commission for rehearing thereon."
As the court explained in Northwest Pipeline Corp. v. FERC,
Michigan acknowledges § 313(a)'s petition-for-rehearing requirement and the line of authorities just cited, but tries to avoid the consequences by analogizing its situation to that in Southern Natural Gas Co. v. FERC,
Michigan's theory is that since the Commission, in its order on remand, did nothing more than attempt to improve the rationale supporting its earlier decisions, Southern Natural Gas excused the State from having to seek rehearing under § 313(a). Michigan misses the point that Southern Natural Gas, given its reasoning, is confined to the question whether this court has jurisdiction if the petitioner failed to seek rehearing of a Commission order on rehearing, a question not entirely resolved by the statute. The situation here is not comparable. Michigan stands on no different footing than any other petitioner who has failed to seek rehearing from a Commission order rendered in an initial proceeding. That the proceeding here was on remand from this court is of no moment. As far as § 313(a) is concerned, the case before the agency was in the same posture as if it had begun anew.3 Nothing in § 313(a) exempts Commission orders issued on remand from the rehearing requirement. In such circumstances, requiring parties to seek rehearing before petitioning for judicial review--requiring, that is, parties to comply with the terms of § 313(a)--will not entail a cycle of agency orders, the key concern in Southern Natural Gas. The rehearing requirement is triggered anew only if the court orders the case remanded and the agency issues a fresh decision.
Michigan also thinks it did not have to seek rehearing because this would have done no good and, at all events, the arguments it would have raised before the Commission on rehearing are the same as those the Commission is now opposing in this court.4 A party's belief that nothing would change on rehearing is irrelevant. Section 313(a) speaks in absolutes. It brooks no exceptions. Our precedents are as firm as can be on this point: an application for rehearing must be filed before the litigant seeks judicial review "even if the point sought to be appealed was raised, considered, and rejected in the original proceeding." ASARCO,
Dismissed.
Notes
By order dated February 19, 1997, not under review here, the Commission also approved the transfer of the license from Mead to Upper Peninsula Power Company. See Mead Corp., 78 F.E.R.C. p 62,121 (1997). For simplicity, this opinion refers to the licensee as "Mead."
The court in ASARCO interpreted § 19(a) of the Natural Gas Act, the counterpart to § 313(a) of the Federal Power Act. See
Because the court here remanded the "case"--instead of merely remanding the record and holding the case in abeyance--the court did not retain jurisdiction. See D.C.CIR. R. 41(b)
The remand order did not, as Michigan supposes, simply reach the same conclusion as the 1995 licensing and 1996 rehearing orders--that the Michigan studies did not constitute § 10(j) recommendations--and address only the points raised in Michigan's prior brief, submitted in case No. 96-1453. The remand order also held that even if some of Michigan's requests were considered under the more deferential § 10(j), instead of § 10(a), the record provided substantial evidence for the Commission's conclusion that the studies and protective devices suggested by Michigan need not be included as license conditions