Opinion
Code of Civil Procedure section 337.15,
1
enacted in 1971, imposes “an absolute requirement that a suit against a contractor to recover damages for a construction defect be brought within 10 years of the date of substantial completion of construction, regardless of the date of discovery of the defect.”
(Regents of University of California
v.
Hartford Acc. & Indem. Co.
(1978)
Procedures
Petitioners, Grange Debris Box and Wrecking Co., Inc. and Fred Grange (referred to collectively as Grange hereafter), were brought into this action at the third level of pleading. The original action was against several oil companies, including Exxon Corporation. Exxon cross-complained against the City of San Rafael and others. San Rafael, in turn, cross-complained against Grange and others.
The subject matter of the lawsuit is a piece of property used as the site of a gasoline filling station before being redeveloped for a commercial office *1353 building. On September 19, 1990, the building owner, Tri Equities, Inc., brought an action against Exxon and other oil companies claiming they contaminated the site by releasing hydrocarbons into the soil and water table in the 1960’s and 1970’s. Exxon cross-complained against San Rafael and others, contending when San Rafael purchased the site for redevelopment it agreed to hold Exxon harmless for any claims for damage to the property. Exxon also claimed San Rafael negligently permitted contamination in 1979 while excavating and preparing the site for construction of an office building.
On March 13, 1992, San Rafael cross-complained against Grange and others for indemnity in the event of a recovery against San Rafael. The cross-complaint alleged San Rafael contracted with Grange to demolish the existing structures on the site, remove underground tanks, remove and dispose of debris, cap sewer laterals and undertake minor grading and other miscellaneous work. It further alleged Grange was contractually required to indemnify and hold San Rafael harmless for any liability from the Exxon cross-complaint or the underlying complaint.
Grange demurred to the cross-complaint on statute of limitations grounds and requested judicial notice of a certificate of completion. The certificate showed Grange completed its work on July 24, 1979, more than 11 years before the original complaint and 12V2 years before the cross-complaint against Grange. After hearing, the court overruled the demurrer. The court took judicial notice of the “Notice of Completion” but reasoned that because San Rafael was barred by section 337.15, subdivision (e), from asserting the 10-year limitation period against Exxon, Grange was barred from asserting it against San Rafael’s claim for indemnity. This petition followed.
Statute of Limitations
Section 337.15, subdivision (a) states the statute of limitations for latent construction defects in the following terms: “No action may be brought to recover damages from any person, or the surety of a person, who develops real property or performs or furnishes the design, specifications, surveying, planning, supervision, testing, or observation of construction or construction of an improvement to real property more than 10 years after the substantial completion of the development or improvement for any of the following: (1) Any latent deficiency in the design, specification, surveying, planning, supervision, or observation of construction or construction of an improvement to, or survey of, real property. (2) Injury to property, real or personal, arising out of any such latent deficiency.”
*1354
The statute does not define a development or an improvement, but decisional law has imported definitions from other statutes. In
Liptak
v.
Diane Apartments, Inc.
(1980)
The
Liptak
court examined definitions of “development” and “improvement” and concluded that, as used in section 337.15, “ ‘an improvement’ is in the singular and refers separately to each of the individual changes or additions to real property that qualifies as an ‘improvement’ irrespective of whether the change or addition is grading and filling, putting in curbs and streets, laying storm drains or of other nature. [][] A developer has the overall control over the development of a ‘tract of raw land’ and the myriad of improvements to the land which eventually complete the development. A person contributing to ‘an improvement’ carries out only one of niany steps towards completion of the development.”
(Liptak
v.
Diane Apartments, Inc., supra,
Application of the Statute of Limitations
The original action by Tri Equities against Exxon and others alleges contamination of the soil and water, not construction defects. Thus, section 337.15 does not apply to Tri Equities’ complaint. However, Exxon’s cross-complaint against San Rafael and its redevelopment agency, filed in late 1991 or early 1992, alleges negligent contamination in 1979 while excavating and preparing the site for construction of an office building.
Section 337.15 appears to bar the Exxon cross-complaint because it alleges a latent defect during improvement of the property more than 12 years before filing of the complaint. However, subdivision (e) of section 337.15 prevents San Rafael from asserting the statute of limitations: “The limitation prescribed by this section shall not be asserted by way of defense by any person in actual possession or the control, as owner, tenant or otherwise, of such an improvement, at the time any deficiency in the *1355 improvement constitutes the proximate cause for which it is proposed to bring an action.”
The superior court, citing
Martinez
v.
Traubner
(1982)
Martinez
disapproved a contrary holding in
Ernest W. Hahn, Inc.
v.
Superior Court
(1980)
If section 337.15 were silent about the application of the 10-year statute to indemnity cross-complaints, the Martinez dictum might encourage us to sustain the superior court’s ruling. However, subdivision (c) of the statute specifically addresses the issue: “As used in this section, ‘action’ includes an action for indemnity brought against a person arising out of that person’s performance or furnishing of services or materials referred to in this section, except that a cross-complaint for indemnity may be filed pursuant to subdivision (b) of Section 428.10 [which authorizes transactionally related cross-complaints] in an action which has been brought within the time period set forth in subdivision (a) of this section.” (Italics added.)
Pursuant to subdivision (c) of section 337.15, if the action is timely under subdivison (a) (brought within 10 years of substantial completion of the development or improvement), a transactionally related cross-complaint may be brought outside the 10-year period. The subdivision does not cover the situation presented here—a cross-complaint in an untimely action in which the defendant is an owner who is barred by subdivision (e) from asserting the defense of untimeliness.
*1356
Sandy
v.
Superior Court
(1988)
Sandy
first determined that the cross-complaints based on Sandy’s negligence in 1971 were not transactionally related to the complaint about Daon’s improvements between 1979 and 1981. (See
Time for Hiring, Inc.
v.
Guy Hatfield Homes/All American Development Co.
(1991)
Sandy explained the policy danger in allowing the action to proceed against Sandy: “[The risk of perpetual exposure to liability for contractors and others in the construction industry] is inherent in [Daon’s] interpretation of section 337.15. Daon is a subsequent improver of the property. The association has sued Daon more than 10 years after the completion of the *1357 original project, a date at which all then concerned with the initial construction should have been entitled to assume freedom from liability provided there was no complaint on file on that 10-year anniversary alleging damages resulting from the original work. No such complaint was then on file. Yet, by the fortuitous circumstance that a subsequent improver may have exposed itself to liability for the work it has done, is that repose suddenly to be ended, and the original workers on the project rendered liable beyond the time when the statute says they may be sued? Plainly this is not what the Legislature intended, [f] . . . [SO This interpretation insures a finite, predictable period of exposure to liability for completed work. Ten years after completion of a work of construction, if no complaint is yet on file against any of the participants, they may all assume their exposure has ended. Under the contrary interpretation, this repose could never occur; instead every subsequent renovation would raise the liability spectre anew. Hardy would be the person who ventured into the construction industry under such conditions, assuming he could get liability insurance at all. [Citations.]” (Sandy v. Superior Court, supra, 201 Cal.App.3d at pp. 1285-1286.)
Finally,
Sandy
addressed the relationship between section 337.15 and rules about accrual of causes of action: “Daon argues that a cause of action for indemnity does not accrue until loss by payment occurs; therefore Daon’s cross-complaint cannot yet be barred as to Sandy. (Citing
Valley Circle [Estates
v.
VTN Consolidated, Inc.], supra,
33 Cal.3d [at p. 611].) However, although the general proposition is correct, we hold that in this situation the specific provisions of section 337.15 control regarding latent defects, and provide a 10-year cutoff which applies even in advance of the judgment against the tortfeasor seeking indemnity. This narrow issue appears to be of first impression in California. We believe such interpretation of the statutes is essential to prevent clear violation of the legislative intent reflected by the 10-year statute. Otherwise, as we have stated, perpetual liability would result. This result works no injustice here because, as explained above, Daon is not liable to plaintiffs for the claimed defective design of Sandy, but solely for its own work on the project. The Legislature has decreed that even as to latent defects, 10 years is long enough for there to be liability exposure.”
(Sandy
v.
Superior Court, supra,
San Rafael’s Contentions
Stare Decisis
We have asked San Rafael to explain why the superior court was not required to follow
Sandy,
particularly its discussion of Klingbeil’s indemnity
*1358
cross-complaint. San Rafael gives us two inadequate answers: (1)
Sandy
conflicts with
Martinez
and a prior decision by this court
(Grimmer
v.
Harbor Towers
(1982)
We disagree with San Rafael’s explanation of stare decisis and the role of dicta. Although
Hickman
v.
Mulder, supra,
The issue in
Hickman
was whether an action for willful waste was barred by antideficiency statutes when the plaintiff repurchased the property for less than the full amount of the default.
Cornelison
v.
Kornbluth
(1975)
Hickman
notwithstanding, dicta of the California Supreme Court does not
control
lower courts. “Such dictum, while not controlling authority, carries persuasive weight and should be followed where it demonstrates a thorough analysis of the issue or reflects compelling logic. [Citations.]”
(Smith
v.
County of Los Angeles
(1989)
The Supreme Court dictum in Martinez neither demonstrated a thorough analysis of the issue before us nor reflected a compellingly logical *1359 interpretation of section 337.15. By contrast, Sandy thoroughly analyzed the issue of cross-complaints in actions brought outside the 10-year period and stated a compelling interpretation of section 337.15. Furthermore, the Martinez dictum did not suggest San Rafael should be permitted to seek indemnity for property damage claims filed outside the 10-year limit. It stated only that it would be unreasonable to hold a possessor of property like San Rafael liable for personal injury claims if a contractor such as Grange created the latent defect leading to the injury. Thus, even if applied to this case, the dictum would not justify the superior court’s ruling.
Express Indemnity
Finally, San Rafael contends section 337.15 does not apply to cross-complaints asserting express contractual indemnity. San Rafael notes Sandy did not specifically address applicability of section 337.15 to express indemnity cross-complaints.
Section 337.15 does not distinguish between implied equitable indemnity cross-complaints and express indemnity cross-complaints. It broadly defines an “action” to include an action for indemnity arising out of performance or furnishing of services or materials. San Rafael asks us to carve out a case law exception to the statute, but provides us no evidence that the Legislature intended such an exception.
If, as the allegations here suggest and our experience confirms, construction agreements often provide for indemnification, this exception could eviscerate the rule and thwart the Legislature’s purpose of protecting contractors from suits over construction undertaken decades earlier. We agree with the dictum in
Regents of University of California
v.
Hanford Acc. & Indem. Co., supra,
Disposition
Having concluded the superior court erred in relying upon the Maninez dictum instead of Sandy’s directly applicable holding, we need only consider whether the court should have sustained the demurrer and whether we should issue a writ of mandate to compel it to do so.
When a complaint shows on its face (or with the help of judicially noticed facts) the cause of action is apparently barred by the statute of limitations, plaintiff must plead facts which show an excuse, tolling, or other *1360 basis for avoiding the statutory bar. (5 Witkin, Cal. Procedure (3d ed. 1985) Pleading, §§ 877-881, pp. 319-323.) The cross-complaint and judicially noticed notice of completion here show more than 11 years between completion of the work and the cross-complaint and filing of the action against San Rafael and more than 12 years before filing of the cross-complaint against Grange. The complaint asserts no facts showing a legal exception, tolling, or excuse. Thus, the court erred in overruling the demurrer.
Although we are generally reluctant to issue writs at the pleading stage, we may be persuaded to do so where the error is clear and substantially prejudices petitioner. (See
Omaha Indemnity Co.
v.
Superior Court
(1989)
In the proceedings in superior court, San Rafael stated on information and belief that discovery would show repairs were required with respect to Grange’s work, causing a tolling of the statute of limitations for the period of repair.
(Cascade Gardens Homeowners Assn.
v.
McKellar & Associates
(1987)
Let a writ of mandate issue directing the Marin County Superior Court to vacate its order overruling Grange’s demurrer and to enter a new order sustaining the demurrer. Upon request, the court may exercise its discretion in determining whether to grant San Rafael leave to amend the cross-complaint.
Merrill, J., and Werdegar, J., concurred.
Notes
All further statutory references are to the Code of Civil Procedure.
