79 N.J.L. 235 | N.J. | 1910
The opinion of the court was delivered by
It was error to direct a verdict; the issues should have been submitted to the jury under proper instructions. The certificate of the engineer was not conclusive. Under the thirty-seventh clause of the contract payment is to be made upon the completion of the work, the certificate of the engineer and upon the said work being accepted by