GRAHAM CONTRACTING, INC., а Florida Corporation, Petitioner,
v.
FLAGLER COUNTY, Respondent.
District Court of Appeal of Florida, Fifth District.
Ernest H. Eubanks of Pitts, Eubanks & Ross, P.A., Orlando, for petitioner.
Noah C. McKinnon, Jr., Bunnell, and Cynthia S. Tunnicliff of Carlton, Fields, Ward, Emmanuel, Smith & Cutler, P.A., Tallahassee, for respondent.
COWART, Judge.
This case involves a contractual right to have disputes аrising out of the contract resolved by arbitration and whether that right has been impliedly waived under the circumstances.
Petitioner, Graham Contracting, contracted with Flagler County to build an addition to the Flagler County Courthouse. The contract required arbitration of "all claims, disputes and other matters in question betwеen the parties ... arising out of or relating to this agreement or the breach thereof." The contract also required that a demand for arbitration be made "within a reasonable time after the claim, dispute or other matter in question has arisen."
Graham Contracting commenced work in May of 1982. On June 22, 1982, while рilings were being installed to support the addition to the courthouse, the foundation of the existing courthouse shifted, damaging the old courthouse. Flagler County instructed Graham Contracting to cease work until further notice. On December 22, 1982, Flagler County served a complaint on Graham Contracting. On January 11, 1983, Graham Contracting served a motion to dismiss the complaint for failure to state a cause of action. On March 31, 1983, a meeting between Graham Contracting and Flaglеr County was held to discuss completion of construction. Graham Contracting was advised that Flagler County would request completion of construction. On April 13, 1983, Graham Contracting submitted documentation of additional costs that it would incur due to the delay in construction caused by the county instructing Graham Contracting to cease work in June of 1982. Flagler County refused to pay these additional costs and Graham Contracting served a demand for arbitration pursuant to the contract. On April 29, *972 1983, Graham Contracting filed a motion in the trial court to compel arbitration. On May 16, 1983, a hearing was held on Graham Contracting's motion to compel arbitration and on its earlier filed motion to dismiss for failure to state a cause of action. The trial court dismissed Flagler County's first complaint but denied Graham Contracting's motion to compel arbitration. Graham Contracting then filed this petition for writ of certiorari.[1] We grant the petition.
In the instant case, the contract required that the demand for arbitration be made "within a reasonable time after the claim, dispute or other matter in question has arisen." The trial court found that а dispute became apparent on June 22, 1982, when the foundation of the old courthouse shifted and Graham Contracting was told to cease work until further notice. The court then found that Graham Contracting's demand for arbitration made ten months later was not made within a reasonable period of time, relying оn Lyons v. Krathen,
Respondent also contends that Graham Contracting waived its right to arbitration by filing its motion to dismiss Flagler County's complaint for failure to statе a cause of action. In R.W. Roberts Construction Company v. Masters and Company,
Petitioner's motion to dismiss and transfer the action is a contention that the proceeding is in the court of thе wrong county, not that it doesn't belong in court at all. This position seems totally inconsistent with petitioner's later assertion that no court was the proper forum, because arbitration was appropriate.
Id. at 1115.
*973 See also, King v. Thompson and McKinnon, Auchinschloss, Kohlmeyer, Inc.,
Thus, in the instant case, there is no basis in the record for a finding of a waiver of thе right to arbitrate through delay in asserting that right and the filing of a motion to dismiss Flagler County's complaint for failure to state a cause of action is not so incоnsistent with the right to arbitrate that a waiver may be implied therefrom. Therefore, we quash the order of the trial court which denied Graham Contracting's motion to compel arbitration.
QUASHED.
DAUKSCH and SHARP, JJ., concur.
NOTES
Notes
[1] This court has previously held that a petition for writ of certiorari is an appropriate method to review an order denying a motion to compel arbitration. Paine, Webber, Jackson & Curtis, Inc. v. Lucas,
[2] Cf. Carcich v. Rederi A/B Nordie,
It is not "inconsistency," but the presence or absence or prejudice which is determinative of the issue. As an аbstract exercise in logic it may appear that it is inconsistent for a party to participate in a lawsuit for breach of a contract, and later to ask the court to stay that litigation pending arbitration. Yet the law is clear that such participation, standing alone, does not constitute а waiver, Chatham Shipping Co. v. Fertex Steamship Corp.,
